This is a Request for Information (RFI) from the National Park Service (NPS) seeking scaffolding services for the Chalmette Monument at Jean Lafitte National Historical Park in New Orleans, Louisiana. The NPS requires a scaffold system to provide full access to a 100-foot tall stone obelisk, enabling masonry repair work. The rental period is three months, with two additional weeks each for mobilization and demobilization, planned to begin in January 2026. The government intends to issue a Firm Fixed Price Contract and is conducting market research to refine requirements.

Interested vendors are asked to submit a capabilities statement by November 21, 2025, at 12:00 ET to Heather Madsen, Contracting Officer. The RFI requests detailed information including an all-inclusive cost estimate, NAICS code, business size, socio-economic categories, GSA contracts, labor categories, and pricing validity. The scaffold must meet specific OSHA safety requirements, including full coverage on all four sides of the monument, debris netting, integrated stairs, and weight-bearing specifications. Delivery will be to the Chalmette Monument at Chalmette Battlefield in New Orleans, Louisiana.

View the file

Other files

File Type Posted
P1280211.JPG JPG image
P1270210.JPG JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P2126Q0003

1. REQUEST NO.

5a. ISSUED BY

NAME

a. NAME

c. STREET ADDRESS

d. CITY

10. PLEASE FURNISH QUOTATIONS TO

THE ISSUING OFFICE IN BLOCK 5a ON

OR BEFORE CLOSE OF BUSINESS (Date)

2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG.1

RATING

6. DELIVERY BY (Date)

7. DELIVERY

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

PAGE OF PAGES

5b. FOR INFORMATION CALL: (No collect calls)

TELEPHONE NUMBER

AREA CODE NUMBER

8. TO:

b. COMPANY

e. STATE f. ZIP CODE

c. CITY

d. STATE e. ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

THIS RFQ

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

IS IS NOT A SMALL BUSINESS SET ASIDEX

11/06/2025 0044031512

1 7

P.O.Box 25287 MS WCP Denver CO 80225

NPS, WASO - WCP Contracting 05/17/2026

NPS, San Juan NHS

Fort San Cristobal

Old San Juan

PR 00901-2094

202 354-3978HEATHER MADSEN

11/21/2025 1200 ES

FOB DESTINATION

OTHER

(See Schedule)X

ITEM NO.

(a)

SUPPLIES/SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

SCAFFOLDING RENTAL SUBJECT TO AVAILABILTY OF

FUNDS The HPTC Masonry Section (National Park Service) is soliciting estimates for the design and construction of a scaffold system which allows full access to the approximately 100 ft tall/6800 SF stone obelisk allowing HPTC day labor services to execute masonry repairs safely and efficiently.

00010 Scaffold Assembly, Disassembly and Rental Product/Service Code: W054 Product/Service Description: LEASE OR RENTAL OF

EQUIPMENT- PREFABRICATED STRUCTURES AND

SCAFFOLDING

Continued ...

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations

13. NAME AND ADDRESS OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

a. NAME OF QUOTER

AREA CODE

NUMBER

15. DATE OF QUOTATION

b. TELEPHONE are are not attached

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA - FAR (48 CFR) 53.215-1(a)

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 7

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2126Q0003

Delivery: 05/17/2026

Period of Performance: 01/17/2026 to 05/17/2026

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

United States Department of the Interior

NATIONAL PARK SERVICE

1849 C Street, N.W.

Washington, D.C. 20240

CONTRACTING OFFICE

P.O. Box 25287, M.S. WCP 7333 West Jefferson Ave, Suite 100 Denver, Colorado 80225 Lakewood, Colorado 80235

IN REPLY REFER TO:

10. C.

November 06, 2025

This is a Request for Information (RFI)/Sources Sought notice issued in accordance with FAR 15.201(e) to conduct market research. This RFI is issued solely for information and planning purposes - it does not constitute a Request for Quote (RFQ)/Request for Proposal (RFP) or a promise to issue an RFQ/RFP in the future. This request for information does not commit the Government to contract for any supply or service whatsoever. The National Park Service (NPS) is not, at this time, seeking quotes/proposals and will not accept unsolicited quotes/proposals.

Responders are advised that the U.S. Government will not pay for any information or administrative costs incurred in response to this RFI; all costs associated with responding to this RFI will be solely at the interested vendor's expense. Not responding to this RFI does not preclude participation in any future RFP, if any is issued. Any information submitted by respondents to this RFI is strictly voluntary. All submissions become Government property and will not be returned.

In support of this effort NPS is conducting market research to further refine requirements and establish the best acquisition approach. Please note that requirements defined to date will likely change before a final request for quote/proposal is released, if any.

Please respond by providing a capabilities statement in support of the company’s ability to support the following requirements and a cost estimate to accomplish the work described herein:

SCAFFOLDING RENTAL “SUBJECT TO AVAILABILTY OF FUNDS” The Historic Preservation Training Center (HPTC) Masonry Section of the National Park Service are soliciting estimates for the design and construction of a scaffold system which allows full access to the approximately 100 ft tall/6800 SF stone obelisk allowing HPTC day labor services to execute masonry repairs safely and efficiently.

PERIOD OF PERFORMANCE

To be Determined

TYPE OF CONTRACT

The government intends to issue a Firm Fixed Price Contract.

DESCRIPTIONS/SPECIFICAITONS/WORK STATEMENT

1. BACKGROUND

The Chalmette Monument was constructed between 1855 and 1908 to commemorate the Battle of New Orleans, which was fought on January 8th, 1815, between the British Army and the United States Army.

The monument is constructed of Tuckahoe and Georgia marble and measures approximately 100’ tall, 16’ 8” square at the base and 14’ square at the top. It is situated on a marble stepped base that measures 40’ square and 8’ high. An iron spiral staircase is located inside the shaft that leads to an observation platform at the top of the tower where three narrow windows are located at each elevation. Multiple brass elements exist throughout the monument: the entrance door and jambs, window grilles and screens, the stair handrail and nine commemorative plaques that dot the circumference of the grass lawn. The monument is a contributing structure in the Chalmette Unit of Jean Lafitte National Historic Landmark District.

A recent site visit revealed extensive atmospheric and bio-growth staining on the exterior stone as well as vegetation growth in the mortar joints. Many stone joints have loose, or missing mortar and several stones have begun to spall. Multiple bronze windows in the tower have missing components and plaques are in need of refinishing. The lightning protection system mounted on the roof is missing a number of original air terminals.

The HPTC Masonry Section (National Park Service) is soliciting estimates for the design and construction of a scaffold system which allows full access to the 100’ tall/6800 SF stone obelisk allowing HPTC day labor services to execute masonry repairs safely and efficiently.

The anticipated duration of the masonry stabilization is approximately three months of which the scaffold will need to be fully accessible. Mobilization and demobilization by scaffold Contractor shall need to be done outside that window.

Jean Lafitte National Historical Park will have ultimate approval of construction timeline as it will affect their operations and facilities directly.

2. LOCATION

Chalmette Battlefield Park Lafitte St.

New Orleans, LA 70119

3. SCOPE OF WORK

Independently, and not as an agent of the Government, the Contractor shall provide all labor, materials, equipment and travel necessary to design, erect, assemble and disassemble OSHA compliant scaffolding at the Chalmette Monument.

The Contractor shall ensure the following design, working conditions and safety criteria are met:

a. Scaffold shall be designed with the understanding that the approximately 41’ square base cannot be the sole load bearing surface as the structural integrity of the substrate cannot be confirmed.

b. Scaffold design shall include a designated hoisting bay, reaching at minimum the landing below the pyramidion, to support a ½ - 1 ton electric hoist on a beam roller. 120V/100’ electric hoist to be supplied by contractor.

c. Decking adjacent to hoist bay shall support up to 1000lbs.

d. Drilling or otherwise attaching the scaffold to the stone surface shall not be permitted.

e. Scaffold shall be erected on all four sides of monument.

f. Scaffolding shall be erected to allow workers to reach all surfaces of the stone surface and allow for hand cleaning and masonry repointing. The distance between each level shall be approximately seven feet. This includes the full surface area of the pyramidion which is at a 15.5/12 pitch.

g. Scaffold shall be assembled to allow for interior access from the front door throughout the duration of the project.

h. Scaffold shall include at least one staircase for entry.

i. Debris netting shall be installed on all vertical sections over the entire height of the scaffold.

j. Access to each scaffold level shall be via an integrated stair within the confines of the perimeter of the safety rail.

k. Section of overhead protection shall be included at the front entrance and be rated minimally at 150 P.S.F.

l. Each scaffolding level shall be fully planked and outfitted with guard rails and toe boards to comply with OSHA safety standards.

m. The finished scaffold shall provide safe work platforms that comply with all elements of OSHA 1926 Subpart L.

n. During the erection and dismantling of the scaffold, the Contractor shall comply with all appropriate OSHA codes, particularly OSHA 1926.501 and OSHA 1926 Subpart L.

o. The Contractor shall confirm in writing that the erected scaffold was inspected by the Contractor’s competent person to meet all OSHA safety specifications prior to turning it over for use by the National Park Service.

3. GOVERNMENT RESPONSIBILITIES

a. Ensure adjacent soil is adequately compacted/sound for scaffold and equipment.

b. Ensure any electrical power lines are de-energized, relocated or shrouded.

c. Ensure all buried utilities will be undisturbed during construction.

d. Ensure scaffold inspections are performed by a qualified person at the beginning of shifts.

e. Assign designated areas for loading and unloading of scaffold components and equipment.

f. Provide continuous access to the monument throughout construction and in coordination with scaffold crew working hours.

g. Management of pedestrian and vehicular traffic throughout construction.

h. Closure of site to public throughout construction.

i. The restoration of site grounds post construction.

j. Access to restroom facilities.

k. Parking.

4. CONTRACTOR RESPONSIBILITES

a. The coordination of delivery, mobilization, erection, dismantling and unloading of scaffold with National Park Service COR.

b. The Contractor shall obtain all necessary licenses and/or permits as required to perform this work including any specific Louisiana state requirements.

c. The Contractor shall take all reasonable precautions necessary to protect persons and property from injury or damage during the performance of this contract.

d. The Contractor shall be responsible for any injury to themself, their employees, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by their employees’ fault or negligence and shall maintain personal liability and property damage insurance having coverage for a limit as required by the laws of the State of Louisiana.

e. Further, it is agreed that any negligence of the Government, its officers, agents, and employees, shall not be the responsibility of the contractor hereunder with the regard to any claims, loss, damage, injury, and liability resulting there from.

5. PERIOD OF PERFORMANCE

Period of performance shall begin upon award of the Contract and end when the Contractor completes demobilization on site.

The rental period for the scaffolding shall be three months, of which the scaffold will need to be fully accessible. Mobilization and demobilization by the Contractor shall be done outside that rental window in accordance with the following schedule:

Mobilization: 2 weeks for complete mobilization beginning in January 2026 Rental Period: 3 Months beginning once mobilization is complete Demobilization: 2 weeks to complete demobilization

6. HOURS OF OPERATION

All Contract deliveries shall be coordinated with NPS COR no later than two weeks prior.

All on-site activities shall be coordinated with NPS COR daily. Site will need special approval to be open during any federal holidays.

GOVERNMENT HOLIDAYS:

New Year’s Day………………………………………… January 1 Martin Luther King’s Birthday…………………………. 3rd Monday in January President’s Day…………………………………………. 3rd Monday in February Memorial Day……………………………………………Last Monday in May Juneteenth………………………………………………...Jun 19th Independence Day………………………………………..July 4th Labor Day……………………………………………… 1st Monday in September Columbus Day……………………………………………2nd Monday in October Veteran’s Day……………………………………………November 11 Thanksgiving Day………………………………………. Last Thursday in November Christmas Day………………………………………........December 25

Any other day designated by the President as a national holiday. When one of the holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a legal holiday by the US Government.

All deliveries shall be made to:

Chalmette Monument Chalmette Battlefield, Jean Lafitte National Historical Park and Preserve Lafitte Rd.

New Orleans, LA 70043

Contractor and NPS POC shall determine the start and end time of work week and days prior to award, if any.

A written target schedule shall be agreed upon prior to arrival of Contractor to site.

PLEASE SEE ATTACHMENTS TO THIS RFI FOR PICTURES OF THE SITE.

ADDITIONAL QUESTIONS:

1.) Please provide an all inclusive estimate of cost associated with the execution and performance of said requirement.

2.) Please identify the NAICS code you believe is most appropriate for this requirement.

3.) Please indicate the size of your business.

4.) Please identify all socio-economic categories that apply to your business.

5.) Please provide any feedback or questions you may have related to this requirement and the Draft SOW.

6.) Please provide a URL to a capability website for your company.

7.) Please provide your company’s Unique Entity Identifier (UEI)

8.) Please identify all GSA contracts that your company holds and are applicable to this requirement (if any).

9.) Please include the contact name and information to include email address for your Small Business Representative (if applicable).

10.) Please provide information on any suggested labor categories and associated labor rates your company would utilize to fulfil the requirements identified above. Service Contract Act (SCA) is applicable to this requirement.

11.) Please identify when ESTIMATED pricing expires.

Please submit your capability statement to the following:

Heather Madsen Contracting Officer Contracting Operations National Department of the Interior/National Park Service E-Mail: heather_madsen@nps.gov Submission of the capability statement is due no later than Friday, November 21, 2025, at 1200

ET.

File details come from the government source that posted it. Updated .