140L5221Q0009

1. REQUEST NO.

5a. ISSUED BY

NAME

a. NAME

c. STREET ADDRESS

d. CITY

10. PLEASE FURNISH QUOTATIONS TO

THE ISSUING OFFICE IN BLOCK 5a ON

OR BEFORE CLOSE OF BUSINESS (Date)

2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG.1

RATING

6. DELIVERY BY (Date)

7. DELIVERY

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

PAGE OF PAGES

5b. FOR INFORMATION CALL: (No collect calls)

TELEPHONE NUMBER

AREA CODE NUMBER

8. TO:

b. COMPANY

e. STATE f. ZIP CODE

c. CITY

d. STATE e. ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

THIS RFQ

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

IS IS NOT A SMALL BUSINESS SET ASIDEX

05/04/2021 0040524142

1 82

1387 S. VINNELL WAY

BOISE ID 83709

BLM ID-STATE OFC HR&ADM SVC (ID953)

Multiple

BLM-ID SHOSHONE FIELD OFFICE (Twin

400 W F ST.

SHOSHONE

ID 83352-1522

208 373-3914Nathaniel Bertels

05/21/2021 1000 MD

FOB DESTINATION

OTHER

(See Schedule)X

ITEM NO.

(a)

SUPPLIES/SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

Legacy Doc #: BLM Period of Performance: 06/01/2021 to 07/20/2021

00010 JUNIPER BUTTE FENCE REPAIRS

Product/Service Code: Y1PZ Product/Service Description: CONSTRUCTION OF

OTHER NON-BUILDING FACILITIES

Delivery: 07/20/2021

00020 BADGER FENCE REPAIRS

Product/Service Code: Y1PZ Product/Service Description: CONSTRUCTION OF Continued ...

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations

13. NAME AND ADDRESS OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

a. NAME OF QUOTER

AREA CODE

NUMBER

15. DATE OF QUOTATION

b. TELEPHONE are are not attached

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA - FAR (48 CFR) 53.215-1(a)

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 82

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140L5221Q0009

OTHER NON-BUILDING FACILITIES

Delivery: 07/20/2021

00030 CONNER SUMMIT FENCE REPAIRS

Product/Service Code: Y1PZ

Product/Service Description: CONSTRUCTION OF

OTHER NON-BUILDING FACILITIES

Delivery: 07/20/2021

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

SOLICITATION NO: 140L5221Q0009

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 3

Type of Contract: Construction, Firm-Fixed Price (FFP) Idaho County: Owyhee County, Cassia County, Twin Falls County Type of Construction: Highway

Magnitude: Between $100,000 and $250,000 NAICS: 238990 Size Standard: $16.50 Million Set-Aside: Total Small Business

Bureau of Land Management Contracting Officer’s Representative (COR) Contracting Officer

Name: Bart Koonce Patricia Fort

Email: bkoonce@blm.gov pfort@blm.gov

Site Visit: See Section L.7

Questions Due Date: Monday, May 17, 2021 at 10:00AM Mountain Daylight Time

Proposal Due Date: Friday, May 21, 2021 at 10:00AM Mountain Daylight Time.

Award Selection Process: Lowest Price mailto:bkoonce@blm.gov mailto:pfort@blm.gov

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 4

General

(a) The Bureau of Land Management (BLM) is seeking quotations for construction services as attached in the accompanying statement of work. The BLM intends to conduct this acquisition by use of simplified acquisition procedures in accordance with FAR Part 13. More than one award may be made to the Offeror(s) that submit a quotation that has been determined to be the lowest price reasonable offeror.

(b) The Government will not award any contract if the resulting contract would not represent a "best value" to the Government.

(c) To assure timely and equitable evaluation of quotations, respondents are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete quotation. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements. Failure to adhere to quotation requirements, at the time of submission, may result in the quotation being unacceptable to the Government and eliminated from consideration for award. It is the responsibility of offerors to ensure their quote is received by the recipient and by the due date and time.

(d) Offerors are cautioned to submit adequate information to enable the Government to fully ascertain each offeror’s capability to perform the requirements in accordance with the requirements of the request for quotation (RFQ).

(e) If a respondent believes that requirements in these instructions contain an error, omission, or are otherwise flawed, the respondent shall immediately notify the Contracting Officer in writing (email is the preferred method) with supporting rationale by the question deadline specified on the cover page of this document.

(f) This RFQ does not commit the Government to any costs incurred in the preparation and submission of a quote or for any other costs incurred by any firm submitting a quote in response to this solicitation. Note specifically that the Offeror will not be participating in a sealed bid procurement process under this acquisition method. Issuance of this RFQ does not constitute an award commitment on the part of the Government.

(g) Quotation must be valid for a minimum of 60 days.

(h) Respondents must complete the System for Award Management (SAM) at https://www.sam.gov/portal/public/SAM/ (previously ORCA and CCR). The Government will obtain respondent representations and certifications through this system.

(i) Award is subject to and based on the availability of funds. This project is currently funded based upon an independent cost estimate.

(j) Including all other factors, to qualify for award, a respondent must be determined responsible in accordance with Federal Acquisition Regulation Part 9.

(k) Respondents shall not contact any government personnel related to this requirement other than the Contracting Officer.

(l) All questions should be emailed directly to the Contracting Officer. Only written RFI’s will be considered and responded to by the Government. BLM responses to RFIs will be posted as an amendment to the solicitation.

(m) The successful Offeror shall submit appropriate Performance and Payment Bonds in accordance with clause 52.228-1 or Alternative Payment Protection in accordance with clause 52.228-13 within 10 days of contract award.

SUBMIT ONLY REQUESTED ITEMS NOT THE ENTIRE SOLICITATION

https://www.sam.gov/portal/public/SAM/

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 5

TABLE OF CONTENTS

Part I - The Schedule

Section A - Solicitation/Contract Form See Standard Form 18

Section B - Bid Schedule 6

Section C - Specifications/Drawings 9

Section D - Packaging and Marking 26

Section E - Inspection and Acceptance 27

Section F - Deliveries or Performance 28

Section G - Contract Administration Data 29

Section H - Special Contract Requirements 31

Part II - Contract Clauses

Section I - Contract Clauses 34

Part III - List of Documents, Exhibits, and Other Attachments

Section J - List of Attachments 53

Part IV - Representations and Instructions

Section K - Representations, Certifications, and Other Statements of Offerors 71

Section L - Instructions, Conditions and Notices to Offerors 77

Section M - Evaluation Factors for Award 82

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 6

PART I - THE SCHEDULE

SECTION B: BID SCHEDULES

Offerors are to complete Blocks 13 - 16 of the SF-18.

More than one contract award may be made under this solicitation. You may quote on a single fence or any combination of fences.

Juniper Butte Fence Repairs

Pay Item Number Description

Estimated Quantity

Unit of

Issue

Unit Price Total Cost

0001 02824 Steel Pipe Three Post End Panel 10 Each $ $

0002 02824 Steel Pipe Two Post Stress Panel 12 Each $ $

0003 02824 Steel Pipe Single Post Installation

1 Each $ $

0004 02824 Barbed Wire Gate (4 Wire)

10 Each $ $

0005 02824 Barbed Wire Fence Construction (4 Wire)

10,504 Foot $ $

0006 02824 Inspect and Repair Existing Barbed Wire Fence (3 or 4 Wire)

40,689 Foot $ $

0007 02827 Barbed Wire Removal (4 Wire - Complete)

10,504 Foot $ $

JUNIPER BUTTE FENCE REPAIRS TOTAL $

PERIOD OF PERFORMANCE: 50 Calendar Days

PERFORMANCE PER PROJECT:

Juniper Butte – 15 days Badger – 30 days Conner Summit – 5 days

ESTIMATED START DATE: 06/01/2021

Fuels and Fire: Some of the fences may be located in areas of heavy fuels. The Contractor shall obey and enforce fire prevention measures such as spark arresters, avoidance of high fuel areas where possible, and all other instructions from the Contracting Officers Representative.

Materials removed from the Conner Summit fire are the responsibility of the contractor for disposal or recycling.

Burned and damaged wood posts are the responsibility of the contractor.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 7

Badger Fence Repairs

Pay Item Number Description

Estimated Quantity

Unit of

Issue

Unit Price Total Cost

0001 02824 Steel Pipe Three Post End Panel 28 Each $ $

0002 02824 Steel Pipe Two Post Stress Panel 23 Each $ $

0003 02824 Steel Pipe Three Post Corner Panel

4 Each $ $

0004 02824 Steel Pipe Four Post Corner Panel

3 Each $ $

0005 02824 Steel Pipe Five Post Corner Panel

23 Each $ $

0006 02824 Steel Pipe Single Post Installation

5 Each $ $

0007 02824 Barbed Wire Gate (4 Wire)

12 Each $ $

0008 02824 Inspect and Repair Existing Barbed Wire Fence (3 or 4 Wire)

54,194 Foot $ $

0009 02824 Steel T-Post Installation 1,400 Each $ $

0010 02824 Stand Up Net Wire Fence and Repair (Net and 2 Strands Barbed Wire)

29,638 Foot $ $

BADGER FENCE REPAIRS TOTAL $

PERIOD OF PERFORMANCE: 50 Calendar Days

PERFORMANCE PER PROJECT:

Juniper Butte – 15 days Badger – 30 days Conner Summit – 5 days

ESTIMATED START DATE: 06/01/2021

Fuels and Fire: Some of the fences may be located in areas of heavy fuels. The Contractor shall obey and enforce fire prevention measures such as spark arresters, avoidance of high fuel areas where possible, and all other instructions from the Contracting Officers Representative.

Materials removed from the Conner Summit fire are the responsibility of the contractor for disposal or recycling.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 8

Conner Summit Fence Repairs

Pay Item Number Description

Estimated Quantity

Unit of

Issue

Unit Price Total Cost

001 02824 Steel Pipe Three Post End Panel 6 Each $ $

002 02824 Steel Pipe Two Post Stress Panel 5 Each $ $

003 02824 Steel Pipe Three Post Corner Panel

1 Each $ $

004 02824 Steel Pipe Five Post Corner Panel

1 Each $ $

005 02824 Barbed Wire Gate (3 & 4 Wire)

5 Each $ $

006 02824 Inspect and Repair Existing Barbed Wire Fence (3 or 4 Wire)

16,209 Foot $ $

CONNER SUMMIT FENCE REPAIRS TOTAL $

PERIOD OF PERFORMANCE: 50 Calendar Days

PERFORMANCE PER PROJECT:

Juniper Butte – 15 days Badger – 30 days Conner Summit – 5 days

ESTIMATED START DATE: 06/01/2021

Fuels and Fire: Some of the fences may be located in areas of heavy fuels. The Contractor shall obey and enforce fire prevention measures such as spark arresters, avoidance of high fuel areas where possible, and all other instructions from the Contracting Officers Representative.

Materials removed from the Conner Summit fire are the responsibility of the contractor for disposal or recycling.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 9

SECTION C: SPECIFICATIONS/DRAWINGS

DIVISION 1 SECTION 01009

GENERAL REQUIREMENTS GENERAL INFORMATION AND REQUIREMENTS

Rev. 05-91

PART 1: GENERAL

1.01 SUMMARY

A. Description of Work

Juniper Butte Fire:

Furnishing labor and equipment to inspect and repair approximately 40,689 feet of three or four strand barbed wire pasture fence, rebuilding gates, replacing corners, and panels, using schedule 40 black pipe for structure replacement, remove and construct approximately 10,504 feet of four strand wire fence with Government-furnished property.

Badger Fire:

Furnishing labor and equipment to inspect and repair approximately 54,194 feet of three or four strand barbed wire pasture fence, rebuilding gates, replacing corners, and panels, using schedule 40 black pipe for structure replacement Government-furnished property.

Furnishing labor and equipment to inspect and repair approximately 29,638 feet of net wire fence with two barbed wires on the top. Much of the net wire fence had wood in-line posts that were totally burned and the fence is now laying on the ground. The wire is still in good condition. This portion of the contract will need t-posts driven into the ground and the net wire and the two barbed wire attached to the t-posts. This will also include the rebuilding gates, replacing corners, and panels, using schedule 40 black pipe for structure replacement Government-furnished property.

Conner Summit Fire:

Furnishing labor and equipment to inspect and repair approximately 16,209 feet of four strand barbed wire pasture fence, rebuilding gates, replacing corners, and panels, using schedule 40 black pipe for structure replacement Government-furnished property.

Furnishing labor and equipment to construct barbed wire fence and associated gates, corners, and panels with Government-furnished property. Work includes the total construction of approximately 2,600 feet of three strand wire protection fence using Easy Fence Panels & Braces.

B. Locations Location 1 – Juniper Butte Fire: Located approximately 26-30 miles southwest of Castleford, Idaho in Owyhee County. The work location is shown on the provided maps.

Location 2 – Badger Fire: Located approximately 9 to 14 miles west south of Hansen, Idaho in Cassia and Twin Falls Counties. The work location is shown on the provided maps.

Location 3 – Conner Summit Fire: Located approximately 2-8 miles west northwest of Malta, Idaho in Cassia County. The work location is shown on the provided maps.

C. Work Data Sheets: Designates the type and quantity of work required for proposed construction, and dimensions required for typical drawings.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 10

1.02 WORK SCHEDULING:

A. Work Schedule: The work schedule shall be submitted at the pre-work conference. When requested, the Contractor shall submit an updated schedule within 3 calendar days. As a minimum, the starting and completion dates for all major work items must be included.

1.03 REFERENCES:

A. N/A

1.04 DEFINITIONS:

A. Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing.

1.05 QUALITY ASSURANCE:

A. N/A

1.06 DELIVERY, STORAGE, AND HANDLING:

A. Delivery: The Contractor shall protect products incorporated into the work from damage while in transit to the site. Products must be stored in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.

B. Storage: The Contractor shall provide temporary storage facilities for products complying with manufacturer's recommendations which will protect them from damage until installation on the project and final acceptance.

C. Handling: The Contractor shall load and unload products in such a manner as to protect them from damage until installation on the project.

1.07 PROJECT/SITE CONDITIONS:

A. Access Roads: Access roads are shown on the Work Location Map. Vehicle travel is permitted along the fence line. Maps of these areas will be provided. The topography along the fence line may limit or prevent travel.

B. Rocky ground: The project site includes some rock formations which prevent posts from being driven. A rock drill may be required at these work sites to assure proper installation of posts.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 11

C. Environmental Considerations:

1. No blading or scraping of the ground along the fence line or on any Bureau of Land Management administered land is needed or permitted. Access roads shall not be constructed along fence lines or to the job sites but travel along the fence line is permitted.

Rocky conditions exist along portions of the fences. It is recommended that interested contractors visit and inspect the site before offering a quote.

No cross-country travel with motorized vehicles shall take place when ground is muddy causing ruts to form. The Contractor shall repair all ruts and scarred ground created by construction, repair, or removal as directed by the Contracting Officer.

Camping at or near the job site is permitted as long as it does not exceed a maximum of 14 days in any one location. Camping is prohibited within 100 yards of any isolated water source springs, seeps, water troughs, windmills, small reservoirs, etc. Toilet facility requirements shall follow all Federal and State regulations. When a camp site is no longer needed, all garbage must be removed and properly disposed of.

Clean-up: All trash and excess materials must be removed from the project site on completion of construction and disposed of in a manner, and at a location, approved by the Contracting Officer.

Cultural Considerations: Because fragile and irreplaceable cultural resources may be present in the area, project activities and any other action which causes disturbance of the earth's surface shall be limited to those areas approved by the BLM. Deviations from routes flagged or shown on the drawings are not allowable without prior approval of the Contracting Officer. The Contractor shall insure that he/she, their employees, or their representatives do not collect archaeological artifacts. Should the condition of the cultural resources in the area be altered during construction due to unauthorized activity by the Contractor or his employees, the Contractor shall be responsible for all costs of mitigating the cultural resources involved. If deterioration of the archaeological sites is found to be occurring during the construction phase, work on the project shall be terminated until a data recovery plan is prepared and completed in accordance with the National Historic Preservation Act.

The Contractor shall immediately bring to the attention of the Contracting Officer any and all cultural resources including, but not limited to, historic and prehistoric sites or artifacts, buried artifacts, and buried features such as fire pits, burials, and house floors discovered as a result of construction operations. The Contractor shall immediately suspend all activities that might harm the object(s) and shall leave such discoveries intact until instructed to proceed by the Contracting Officer.

Pursuant to 43 CFR J0.4(g) the Contractor must notify the Contracting Officer by telephone, with written confirmation, immediately upon the discovery of human remains, funerary items, sacred objects, or objects of cultural patrimony. Further, pursuant to 43 CFR 10.4(c) and (d), the Contractor must stop activities in the immediate vicinity of the discovery and protect it from construction activities for 30 days or until notified to proceed by the Contracting Officer.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 12

PART 2: PRODUCTS

(There are no applicable requirements.)

PART 3: EXECUTION

3.01 PROJECT MEETINGS:

A. Pre-Work Conference:

1. Pre-Work Conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

2. The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.

3. The Contractor shall be prepared to summarize and explain procedures planned for the project.

B. Progress Meetings:

1. Shall be held at the project site, or as determined by the Contracting Officer.

2. Meetings may be called by either the Contracting Officer or the Contractor. Request shall state who should attend and include an agenda.

C. Final Inspection:

1. To be held at the project site, or as determined by the Contracting Officer.

2. Notify the Contracting Officer in writing at least 3 working days before the completion date so the Government can schedule final inspection.

3. The Contractor or the Contractor's authorized representative shall be present during this inspection.

3.02 PREPARATION:

A. Work Layout: The location of burned structures will be obvious by partial structures present or the existence of twist wires, from burned wood structures, present within the fence line. Gates can also be identified by structures burned and wires present. The Contractor shall, immediately upon entering the project site for the purpose of beginning work, locate all reference marks and take such actions to prevent their destruction. Stress panels shall be located as specified for barbed wire fences.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 13

3.03 DISPOSAL OF DEBRIS

A. Requirements: Items or debris not designated as salvage for the government, shall become the property of the Contractor. Burned and damaged wood posts shall be removed at the expense of the contractor and should be considered in the contractor’s bid. The Contractor is responsible for the disposal of materials in a legal manner and the payments of all disposal fees.

Burning of removed materials is not permitted on the work site.

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT:

A. Units: The work described in this section will not be measured for payment

4.02 BASIS OF PAYMENT:

A. Payment: No direct payment for the work described under this section will be made.

Consideration for these items shall be included in the bid price for other items of the Contract.

END OF SECTION

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 14

DIVISION 1 SECTION 01019

GOVERNMENT FURNISHED PROPERTY

Rev. 05-91

PART 1: GENERAL

A. Section Includes: The materials to be furnished by the Government and their locations.

1.02 DELIVERY, STORAGE, AND HANDLING

A. Location: The Government-Furnished property will be provided by the Bureau of Land Management’s Shoshone Field Office. The office address is: 400 W F Street, Shoshone, ID 83352.

B. Time: Property will be available Monday through Friday, from 8:00 am to 3:30 pm except on holidays. An appointment is required to assure that a person is available. Appointments are made by calling Bart Koonce at 208-732-7236 a minimum of 24 hours prior to intended pickup time.

C. Return of Unused Property: Return unused materials to the same place as they were picked up unless the Contracting Officer states otherwise.

D. Loading, Offloading and Transporting Property: The Contractor is responsible for providing the necessary material-handling equipment to load and offload materials at the work site. The Contractor shall transport materials to the work site. Unless otherwise noted, a Government forklift and operator will be available at the Government office.

PART 2: PRODUCTS

2.01 MATERIALS

A. Materials to be furnished by the Government: 12-gauge Barbed Wire, 12-gauge Barbless Wire, Schedule 40 Pipe 7’x 2.0”, Schedule 40 Pipe 7’x 1.25”, 5’6” T-Posts, Fence Clips, 4’ Wood Stays, Metal Gate Closers, Galvanized Staples, metal twist sticks, bolts, nuts, brace bands, and metal flat bars. For the temporary fence on Conner Summit, Easy Panel structures and hose clamps will be provided along with the listed materials above.

PART 3: EXECUTION

(There are no applicable requirements.)

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 15

PART 4: MEASUREMENT AND PAYMENT

4.01 METHOD OF MEASUREMENT

A. Units: The work described in this Section will not be measured for payment.

4.02 BASIS OF PAYMENT

A. Payment: No direct payment for the work described under this Section will be made.

Consideration for this item shall be included in the bid price for other items of the Contract.

END OF SECTION 01019

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 16

DIVISION 2 SECTION 02824

SITEWORK WIRE FENCES AND GATES

Rev. 01-93

PART 1: GENERAL

1.01 SUMMARY

A. This Section includes: Constructing barbed wire fences, including associated panels, corners, and gates.

B. Related Sections: General Information and Requirements Section 01009 Government-Furnished property Section 01019

1.02 REFERENCES

A. N/A

1.03 SUBMITTALS

A. General: Submittals shall be according to Section 01009 – General Information and Requirements

PART 2 - PRODUCTS

2.01 GOVERNMENT-FURNISHED MATERIALS

A. The government shall furnish specified materials required for the performance of the contract work in accordance with Section 01019 - Government Furnished Property.

PART 3: EXECUTION

3.1 PREPARATION

A. Clearing: Will not be needed since all fences will be within last year’s fire area. At the time of construction, grass will be growing, but will not be enough to need cleared.

3.02 INSTALLATION: REFER TO WORK DATA SHEET

A. General: Construct the wire fence in accordance with the drawings.

B. Ratio of Wood to Steel Line Posts: All steel.

C. Setting Posts: Set posts plumb and to the spacing and grades as shown on the drawings, unless staked otherwise. Space within 6 inches of that dimension shown on the drawings or in the Work Data Sheet.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 17

D. Driving Line Posts: Steel Posts: Drive into the ground to the depth shown on the drawings. The anchor plate shall be below the ground surface. Posts shall be driven plumb. When rock formations prevent driving remove anchor plate and excavate or drill holes a minimum of 18 inches deep and slightly smaller than the diameter of the post, then drive post solidly into the rock formation.

E. Corner Panel, Stress Panel, and End Panel Assemblies: Construct as shown on the drawings or as staked in the field. Construct all panels to replace burned out structures, and a maximum of 1320 ft center-to-center for barbed wire sections on standard barbed wire fences. Construct three post end panels at the end of fence runs unless shown otherwise on the drawings.

F. Wire: Stretch tightly and securely attach to steel posts with standard wire clips or tie wire twisted tight. Wire is properly stretched when it is springy to the touch. Terminate wire at each end post, gate post, corner post, or stress panel. Wrap wire around the post two times and tie off by wrapping around the incoming wire a minimum of four times.

G. Brace Wire: Double-loop and twist tight. A steel rod shall be used, leaving one end of the steel rod long enough to fasten behind the horizontal brace or wire may be twisted tight from the brace wire and looped over the brace pipe to prevent wire from unwinding. All structures shall be wired in an “X” pattern, the same as the Stress Panel drawing.

H. Gates: Installed according to the Work Data Sheet and the drawings. ALL GATES SHALL

BE 4 WIRES WITH 4 GATE STAYS.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this section will be measured and paid for by each and by the foot for each type of fence as measured along the ground surface next to the completed fence, including distance across gate openings, end, stress, and corner panels. Line Items will be paid for as the actual number constructed. Note: Gates do not include adjacent end or corner panels.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 18

4.2 BASIS OF PAYMENT

A. Payment: Prices and payment will be full compensation for the work described in this section.

Payment will be made under:

Juniper Butte Pay Item Pay Unit 01 02824 Steel Pipe-Three Post End Panel Each 02 02824 Steel Pipe-Two Post Stress Panel Each 03 02824 Single Pipe Post Installation Each 04 02824 Barbed Wire Gates (4 – wire) Each 05 02824 Barbed Wire Fence Construction (3 Wire) Foot 06 02824 Inspect and Repair Existing Barbed Wire Fence (3-4) Foot

Badger Pay Item Pay Unit 01 02824 Steel Pipe-Three Post End Panel Each 02 02824 Steel Pipe-Two Post Stress Panel Each 03 02824 Steel Pipe-Three Post Corner Panel Each 04 02824 Steel Pipe-Four Post Corner Panel Each 05 02824 Steel Pipe-Five Post Corner Panel Each 06 02824 Single Pipe Post Installation Each 07 02824 Barbed Wire Gates (4 - wire) Each 08 02824 Inspect and Repair Existing Barbed Wire Fence (3 or 4 wire) Foot 09 02824 Steel ‘T’ Post Installation Each 10 02824 Stand Up Net Wire Fence, Attach, Repair Existing Net Wire (2 wires) Foot

Conner Summit Pay Item Pay Unit 01 02824 Steel Pipe-Three Post End Panel Each 02 02824 Steel Pipe-Two Post Stress Panel Each 03 02824 Steel Pipe-Three Post Corner Panel Each 04 02824 Steel Pipe-Five Post Corner Panel Each 05 02824 Barbed Wire Gates (4 - wire) Each 06 02824 Inspect and Repair Existing Barbed Wire Fence (4 wire) Foot

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 19

DIVISION 2 SECTION 02827

SITEWORK FENCE REMOVAL, RELOCATION

Rev. 01-93

SECTION 02827

FENCE REMOVAL, RELOCATION

PART 1: GENERAL

1.1 SUMMARY

A. Section Includes: Removing wires, posts and gates.

B. Related Sections:

General Information and Requirements Section 01009

PART 2: PRODUCTS

2.1 MATERIALS

A. Requirements: All materials removed are considered disposable and considered to be the responsibility of the Contractor.

PART 3: EXECUTION

3.1 REMOVAL/ERECTION

A. Removal of Existing Fence: Remove wires, posts and gates. Roll wire in such a manner that it can be disposed of. Posts which cannot be removed from the ground shall be cut off a minimum of three inches below ground level. Dispose of debris offsite or as approved by the Contracting Officer. The Contractor shall be responsible for the legal disposal of debris and the payment of disposal fees.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT

A. Units: Fence removal will be paid for by the linear foot of complete fence removed and wires removed as measured on the ground next to the fence prior to removal or as measured with GPS.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 20

4.2 BASIS OF PAYMENT

A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:

Juniper Butte Pay Item Pay Unit 07 02827 Barbed Wire Removal (4 Wire) Foot

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 21

WORK DATA SHEET

for

SECTION 02824 - WIRE FENCES AND GATES

Job Title: Fence Construction

Fence type: Barbed Wire – Pipe Structures (3-Wire) Permanent

Type of top wire: Barbed Type of intermediate wire: Barbed Type of bottom wire: Barbed or Barbless

Wire locations/dimensions in inches (spacing):

D: N/A C: 12" (Top) B: 10" (Intermediate) A: 18" (Bottom)

Line post spacing (L): 16 ft 6 inches

Type of Stays: N/A

Stay Spacing: N/A

Length of pipe posts (H1): 7 ft 0 inches

Depth of pipe posts in ground (h1): 3 ft 0 inches

Length of steel line posts (H2): 5 ft 6 inches

Depth of steel line posts in ground (h2): 1 ft 6 inches

Gate Width: 16 ft 6 inches or wide enough to accommodate the road

Gate Wires: 4 Strand Wire locations/dimensions in inches (spacing):

D: 12” Barbed C: 6” Barbed B: 4” Barbed A: 18” Barbless

SPECIAL CONSIDERATIONS

Terrain may make some of the areas inaccessible to any vehicle traffic. Some areas have surface and subsurface rock which may require pipe posts and t-posts to be drilled. Please keep this in consideration for your bid.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 22

WORK DATA SHEET

for

SECTION 02824 - WIRE FENCES AND GATES

Job Title: Fence Construction

Fence type: Net Wire – Pipe Structures Permanent

Type of top wire: Barbed Type of intermediate wire: Barbed Type of bottom wire: Net

Wire locations/dimensions in inches (spacing):

D: N/A C: 2" B: 2" A: Net

Line post spacing (L): 20 ft 0 inches

Type of Stays: N/A

Stay Spacing: N/A

Length of pipe posts (H1): 7 ft 0 inches

Depth of pipe posts in ground (h1): 3 ft 0 inches

Length of steel line posts (H2): 5 ft 6 inches

Depth of steel line posts in ground (h2): 1 ft 6 inches

Gate Width: 16 ft 6 inches or wide enough to accommodate the road

Gate Wires: 4 Strand Wire locations/dimensions in inches (spacing):

D: 12” Barbed C: 6” Barbed B: 4” Barbed A: 18” Barbless

SPECIAL CONSIDERATIONS

Terrain may make some of the areas inaccessible to any vehicle traffic. Some areas have surface and

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 23

WORK DATA SHEET

for

SECTION 02824 - WIRE FENCES AND GATES

Job Title: Fence Construction

Fence type: Barbed Wire – Pipe Structures (4-Wire) Permanent

Type of top wire: Barbed Type of intermediate wires: Barbed Type of bottom wire: Barbed or Barbless

Wire locations/dimensions in inches (spacing):

D: 12" C: 6" B: 4" A: 18"

Line post spacing (L): 16 ft 6 inches

Type of Stays: N/A

Stay Spacing: N/A

Length of pipe posts (H1): 7 ft 0 inches

Depth of pipe posts in ground (h1): 3 ft 0 inches

Length of steel line posts (H2): 5 ft 6 inches

Depth of steel line posts in ground (h2): 1 ft 6 inches

Gate Width: 16 ft 6 inches or wide enough to accommodate the road

Gate Wires: 4 Strand Wire locations/dimensions in inches (spacing):

D: 12” Barbed C: 6” Barbed B: 4” Barbed A: 18” Barbless

SPECIAL CONSIDERATIONS

Terrain may make some of the areas inaccessible to any vehicle traffic. Some areas have surface and

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 24

WORK DATA SHEET

for

SECTION 02824 - WIRE FENCES AND GATES

Job Title: Conner Summit Protection Fence Construction

Fence Construction Type: Barbed Wire 25’ Spacing (3-Wire) w/Easy Fence Panels

Type of top wire: Barbed Type of intermediate wire: Barbed Type of bottom wire: Barbless

Wire locations/dimensions in inches (spacing):

D: N/A C: 12" B: 10" A: 18"

Line post spacing (L): 25 ft 0 inches

Type of Stays: N/A

Stay Spacing: N/A

Length of steel line posts (H2): 5 ft 6 inches

Depth of steel line posts in ground (h2): 1 ft 6 inches

Gate Width: 16 ft 6 inches

4 Wire locations/dimensions in inches (spacing) for Gates:

D: 12” C: 6" B: 4" A: 18"

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 25

WORK DATA SHEET

for

SECTION 02827 - FENCE REMOVAL, RELOCATION

Job Title: Juniper Butte Fence Material Removals

FENCE SPECIFICATIONS

4 Strand Barbed Wire – The existing fence consisted of cedar wood posts every 16.5 feet throughout the fence line. The majority of the posts burned during the fire and the wire is remaining on the ground. The wire is not in good condition, so we are having approximately 10,504 feet of 4 strand barbed wire removed. Wire shall be removed and disposal shall be the responsibility of the contractor. When possible, found metal staples shall be picked up and disposed.

SPECIAL CONSIDERATIONS

Terrain may make some of the areas inaccessible to any vehicle traffic, but most fences are accessible within the project areas.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 26

SECTION D: PACKAGING AND MARKING

Packaging and marking of deliverables shall be IAW the Contractor’s standard commercial practices.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 27

SECTION E: INSPECTION AND ACCEPTANCE

E.1 52.252-2 Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/browse/index/far#

Clause Title Date 52.246-12 Inspection of Construction August 1996 52.246-13 Inspection -- Dismantling, Demolition, or Removal of Improvements August 1996

E.2 Final Inspection and Acceptance

Final completion of the punch list items, submission of all required submittals, and final cleanup of the project site shall be completed before the contract’s required completion date. The Contracting Officer or his/her designated representative will perform final inspection. Acceptance of the work will occur only upon written notice of acceptance by the ordering Contracting Officer or any other Warranted Contracting Officer employed by the Bureau of Land Management (BLM) and performing authorized duties in conjunction with this contract.

https://www.acquisition.gov/browse/index/far#

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 28

SECTION F: DELIVERIES OR PERFORMANCE

F.1 52.252-2 Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/browse/index/far#

Clause Title Date 52.211-13 Time Extensions September 2000 52.211-18 Variation in Estimated Quantity April 1984 52.236-11 Use and Possession Prior to Completion April 1984

F.2 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within five (5) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 50 calendar days after receipt of the notice to proceed. *The time stated for completion shall include final cleanup of the premises.

*The Government recognizes that seasonal climatic conditions may occur that restrict or prohibit normal construction activities. The anticipated length of the seasonal delay for this project is 0 days. This number of days has been included in calculating the stated period of performance. Therefore, the contract period of performance will not be extended due to normal seasonal weather delays.

F.3 52.211-12 Liquidated Damages--Construction (Apr 1984)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $ 1,152.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

F.4 Simultaneous Performance

If a Contractor receives award of more than one contract, simultaneous performance will be required. All work must be completed within the timeframe allowed for each contract.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 29

SECTION G: CONTRACT ADMINISTRATION DATA

G.1 Authorities and Delegations (Sep 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.

The Contractor need not proceed with direction that it considers to have been issued without proper authority.

The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 30

G.2 Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Apr 2013)

Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor.

To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions- Commercial Items included in commercial item contracts. The IPP website address is:

https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

(a) Copy of Company Generated Invoice.

(b) Substantiation Forms are to be submitted with progress payments only.

(c) Release of Claims shall be submitted with the final payment only.

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment.

The Contractor Government Business Point of Contact will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

G.3 Local Internet Payment Platform (IPP) Hotline

To check payment status, contact the Payment Hotline at 877-480-9724 or 303-236-2850. You will need to leave a message with the following information:

1. Company Name

2. Contract Number

3. Invoice Number

4. Invoice Amount

5. A brief description of why you are calling

6. Your contact information

If you do not receive a callback from the Payment Hotline within 72 hours, please contact the Contracting Officer with the day and time you contacted the Payment Hotline.

G.4 Government Point of Contact

Patricia Fort, Contracting Officer pfort@blm.gov Bureau of Land Management 1387 S. Vinnel Way Boise, ID 83709 Telephone: (208) 373-3910 http://www.ipp.gov./ mailto:ippgroup@bos.frb.org mailto:pfort@blm.gov

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 31

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 Work Hours

The performance period established for this contract is based upon all work being conducted during regular working hours between 6:00 am and 6:00 pm, Mountain Daylight Time, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.

In addition to any holidays declared by Executive Orders, the following Federal Legal Holidays are observed:

New Year’s Day Martin Luther King Jr. Day President’s Day Memorial Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day

H.2 Communications

“Time” for communications received after 3:00 pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Mountain time.

H.3 Fire Danger Season

If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

H.4 Drawings

(a) Typical Drawings. Any drawings titled typical are general only and dimensions of each structure will be fixed by the Contracting Officer to adapt the design to existing conditions at the structure location.

(b) Reduced Size Drawings. Any drawings identified as "REDUCED SIZE DRAWINGS" appearing in the solicitation are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective bidders desiring to review a copy of the full size drawings may contact the Contracting Officer identified in the solicitation.

H.5 Preservation of Historical and Archeological Data

(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

(b) If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.

PROJECT DESCRIPTION: TWIN FALLS DISTRICT FENCE REPAIRS 2021 Page 32

(c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.

(d) The Contractor will be responsible for protecting the cultural resources within the effected area from damage.

In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

(e) The Contractor agrees to insert this paragraph in all subcontracts that involve the performance of work on the terrain of the site.

H.6 Safety and Quality Control Plan

Following contract award, the contractor must provide effective quality assurance and safety plans for acceptance by the Government.

H.7 Limitations on Subcontracting Reporting

In accordance with 52.219-14 Limitations on Subcontracting, the prime contractor must perform at least 15% of the cost of the contract, excluding the cost of materials with its own employees and employees of a similarly situated subcontractor. A similarly situated subcontractor is a small business concern subcontractor that is a participant of the same SBA program that qualified the prime contractor as an eligible offeror and awardee of the contract. The contractor is responsible for ensuring compliance with the Limitation on Subcontracting.

At the conclusion of the period of performance and prior to final payment, the contractor shall submit a Limitation on Subcontracting Report directly to the Contracting Officer. The following information is required as part of the report:

1) the total amount paid to the Prime during the performance period broken out by labor and materials 2) list of Similarly Situated Subcontractors and the amounts paid to each during the performance period broken out by labor and materials 3) list of any other subcontractors and the amounts paid to each during the performance period broken out by labor and materials.

If the Contracting Officer review of the report finds that the contractor is not in compliance for the period of performance, the contractor will be notified in writing.