This is a Request for Proposal (RFP) issued by the Bureau of Land Management (BLM) Northwest Oregon District for outfitting a single 2024 Ford F150 law enforcement patrol vehicle. The solicitation (No. 140L4325Q0053) seeks a firm fixed-price contract for comprehensive vehicle modification services, with a period of performance from May 19, 2025 to December 31, 2025. The detailed Statement of Work requires extensive vehicle customization, including installing specialized equipment such as infrared and LED lights, front and rear HD bumpers, winches, a cargo deck with drawer, window barriers, a 2000-watt inverter, vehicle alarm, siren systems, external lighting, communication equipment, and various other law enforcement-specific modifications.
The solicitation includes specific evaluation factors for award, which will consider past performance, relevant experience, and price. Offerors must demonstrate experience with similar projects completed within the last five years and provide detailed information about their previous work. The contract is set aside for small businesses, with a size standard of $10 million. Electronic quotations must be submitted via email to specified BLM contacts by the solicitation closing date. The government will award the contract to the responsible firm whose quote is most advantageous, considering price and other factors, with the goal of obtaining a fully outfitted law enforcement vehicle that meets the BLM Northwest Oregon District's operational requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUMIS CHECKED
CODE 18a. PAYMENT WILL BE MADE BY
CODE
FACILITYCODE
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
OFFEROR
LHA
PORTLAND OR 97204
1220 SW 3rd Avenue, 12th Floor
BLM OR STATE OFC PROC MGMT-OR952
0011276580 CODE 16. ADMINISTERED BYCODE
X
X
811198
SIZE STANDARD:
% FOR:SET ASIDE:UNRESTRICTED ORLHA
REQUEST FOR
PROPOSAL
(RFP)
INVITATION
FOR BID (IFB)
10. THIS ACQUISITION ISCODE
REQUEST FOR
QUOTE (RFQ)
14. METHOD OF SOLICITATION
13b. RATING
NORTH AMERICAN INDUSTRY
CLASSIFICATION STANDARD
(NAICS):
SMALL BUSINESS
05/07/2025 1700 PD
04/30/2025
0000000000Carrie Mahlmeister (No collect calls)
INFORMATION CALL:
FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME
4. ORDER NUMBER3. AWARD/ 6. SOLICITATION
140L4325Q0053
5. SOLICITATION NUMBER
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF
1 67 0044011853OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
TELEPHONE NO.
17a. CONTRACTOR/
SALEM OR 97306
1717 FABRY RD SE
BLM-OR NORTHWEST OREGON DISTRICT OF
15. DELIVER TO
PORTLAND OR 97204
1220 SW 3rd Avenue, 12th Floor
9. ISSUED BY
7.
2. CONTRACT NO.
EFFECTIVE DATE
$10
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
ISSUE DATE
DELIVERY FOR FREE ON BOARD
(FOB) DESTINATION UNLESS
BLOCK IS MARKED
11.
SEE SCHEDULEX
12. DISCOUNT TERMS THIS CONTRACT IS A RATED
ORDER UNDER THE DEFENSE
PRIORITIES AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
13a.
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
8(A)
BLM OR-ST OFC PROC MGMT BR(OR952)
WOMEN-OWNED SMALL
BUSINESS (WOSB)
ECONOMICALLY DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
LE PATROL VEHICLE: FORD F150 OUTFITT
Delivery: 12/31/2025 Period of Performance: 05/19/2025 to 12/31/2025
LE PATROL VEHICLE: FORD F150 OUTFITT
00010 LE Patrol Vehicle: Ford F150 Outfitting Product/Service Code: N023 Product/Service Description: INSTALLATION OF
EQUIPMENT- GROUND EFFECT VEHICLES, MOTOR
Continued ...
(Use Reverse and/or Attach Additional Sheets as Necessary)
HEREIN, IS ACCEPTED AS TO ITEMS:
X
XX
DATED
Matthew Duane
. YOUR OFFER ON SOLICITATION (BLOCK 5),
INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER
ARE
ARE
31c. DATE SIGNED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)
ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL
SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3
AND 52.212-5 ARE ATTACHED. ADDENDA
26. TOTAL AWARD AMOUNT (For Government Use Only)
OFFER
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
ARE NOT ATTACHED.
ARE NOT ATTACHED.
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
30b. NAME AND TITLE OF SIGNER (Type or print)
30a. SIGNATURE OF OFFEROR/CONTRACTOR
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
25. ACCOUNTING AND APPROPRIATION DATA
29. AWARD OF CONTRACT: REFERENCE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER
37. CHECK NUMBER
FINALPARTIAL
36. PAYMENT
FINALPARTIAL
35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER33. SHIP NUMBER
COMPLETE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)
42b. RECEIVED AT (Location)
42a. RECEIVED BY (Print)
41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
STANDARD FORM 1449 (REV. 11/2021) BACK
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
VEHICLES, TRAILERS, AND CYCLES
32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
67 2 of
LE Patrol Vehicle: Ford F150 Outfitting SOLICITATION NO. 140L4325Q0042 BLM Northwest Oregon District Page 3 of 67
Combined Synopsis / Solication
This announcement constitutes the only solicitation; quotes are being requested and a separate written solicitation will not be issued.
SECTION B - SERVICES AND PRICES
This requirement is for one(1) Firm Fixed Price Commercial Services Contract for outfitting one 2025 Ford F-150 Law Enforcement Vehicle, BLM Northwest Oregon District.
BASE
Item no. Item Description Quantity Unit of
Measure Unit Price Total
0001 Outfit 2025 Ford F-150 1 EA
GRAND TOTAL $
PERIOD OF PERFORMANCE: See Deliveries or Performance section.
(End of Supplies/Services and Prices/Costs)
BLM Northwest Oregon District Page 4 of 67
SECTION C – STATEMENT OF WORK
1.0 General:
1.1 This purpose of this contract is to outfit a 2024 Ford F150 for law enforcement services.
1.2 Unless otherwise specified below, the contractor shall furnish all necessary management, supervision, labor, equipment, materials, and any other incidental services to perform this work.
1.3 Placement, orientation, or substitution of the equipment requires approval of the BLM.
1.4 The vehicle is currently in the BLM’s possession and is available to be dropped off by BLM to outfitter. 30 miles away restriction
2.0 Government furnished items:
2024 Ford F150
Motorolla 8500 Radio
BLM Law Enforcement Exterior Badging.
3.0 Contractor-furnished items:
Pair of 3x3” Infrared lights installed on front bumper (one on each side)
Pair of 3x3” cube LED lights mounted on front bumper (one on each side).
Fab Fours - Matrix Full Width Front Winch HD Bumper with Brush Guard, or equivalent
30” LED lightbar on front bumper.
Fab Fours- Premium full width rear HD bumper, or equivalent
Warn winch front (10, 000 lbs. cap. mounted into bumper) and rear (10,000 lbs. cap. via hitch receiver).
Front and rear synthetic winch rope.
RDS 50 Gallon, Black Aluminum Toolbox/ transfer fuel tank mounted in front of truck vault (between cab and vault), or equivalent
GPI pump Part Number 137100-05 (for Transfer fuel tank, or equivalent
Miscellaneous pump parts.
Go Rhino RB20 running boards, or equivalent
Setina Cargo Deck w/ Drawer Super Max, PART# TK1338FDT15F150, or equivalent
Setina #6VS SPT Coated Poly Partition, PART# 1K0574FDT15F150WOD, or equivalent
Setina Window Barrier Steel Horizontal, PART# WK0514FDT15F150H, or equivalent
BLM Northwest Oregon District Page 5 of 67
Setina SPT Rear Transport Replacement Seat, PART# QK2381FDT17F250, or equivalent
Setina Door Panel TPO, PART# DK0100FDT21F150, or equivalent
Setina D T-Rail Mount 2 Universal Locks Handcuff Key, PART# GK10342UHK, or equivalent
Center console with locking storage
2000-watt inverter and all wiring and accessories
USB and 12v charging ports.
White/red overhead light for rear cargo area
Main electronics kill switch in console.
Vehicle alarm/ remote start
Soundoff siren controller, or equivalent
Soundoff aftershock siren system, or equivalent
Rear bumper mounted backup lights
External window visors (rain guards)
Rear lighting kill switch (blackout switch)
Rear window tint
Soundoff mPower fascia lights, or equivalent
Coax kits and antennas/connectors.
Miscellaneous install supplies
Valor light bar, or equivalent
Radar unit (front and rear antennas), or equivalent
Weapon release switches and timer (front and rear)
Cell booster with internal and external antennas (not including coax kit)
GPS unit on dash
Truck vault
Dual radios with roof mounted antennas
Siren speaker
External red/blue led lights (including 3rd brake light housing)
Relays, power distribution panels, electronics slide tray.
(End of Statement of Work)
BLM Northwest Oregon District Page 6 of 67
SECTION E – INSPECTION AND ACCEPTANCE
The following clause is incorporated by reference:
Clause Title Date
52.246-1 CONTRACTOR INSPECTION REQUIREMENTS APR 1984
(End of Inspection and Acceptance)
BLM Northwest Oregon District Page 7 of 67
SECTION F – DELIVERIES OR PERFORMANCE
F.1.0 PERIOD OF PERFORMANCE
The contract shall commence from date of award to 12/31/2025.
F.2.0 PROGRESS PLAN
At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.
The following clause is incorporated by reference:
Clause Title Date
52.242-15 STOP WORK ORDER AUG 1989
(End of Deliveries or Performance)
BLM Northwest Oregon District Page 8 of 67
SECTION G – CONTRACT ADMINISTRATION DATA
The following local clauses are provided in full text:
CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (JULY 2010)
(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR42.15.
(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available for Government use in evaluating past performance as part of a source selection action.
(c) We request that you furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.
(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/. The CPARS User Manual, registration for On Line Training for Contractor Representatives, and a practice application may be found at this site.
(e) Within 60 days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official's narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1 - 17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating ''No comment" in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment." Your response is due within 30 calendar days after receipt of the CPAR.
(f) The following guidelines apply concerning your use of the past performance evaluation:
(1) Protect the evaluation as "source selection information." After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.
https://www.cpars.gov/ http://www.cpars.csd.disa.milj/ https://www.cpars.gov/ http://www.cpars.csd.disa.mil/
BLM Northwest Oregon District Page 9 of 67
(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determinations, production readiness reviews, or other similar purposes.
(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30- day review period.
(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of clause)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)
(APR 2013)
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP).
“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Products and Commercial Services included in commercial products and commercial services contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice billed according to contract line items and rates.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contract (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
(End of Contract Administration Data) https://www.ipp.gov/ mailto:ippgroup@bos.frb.org
BLM Northwest Oregon District Page 10 of 67
SECTION H – SPECIAL CONTRACT REQUIREMENTS
1.0 ACCESS
In the event of a site/facility closure, the Contractor shall not perform or make deliveries to the site/facility until it is reopened by the Government, unless otherwise instructed by the Contracting Officer or their designated representative.
2.0 WORK HOURS
Unless otherwise specified in Section C, Specifications, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be done on Saturday, Sunday, or Federal holidays unless authorized by the COR.
3.0 ENVIRONMENTAL INTERRUPTION OF WORK
3.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. An allowance has been included in the contract time for all environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger. The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration.
3.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, or Federal candidate (Category 1 and 2), sensitive or state listed species, identified under BLM Manual 6840, are discovered to be present in or adjacent to the project area.
4.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
4.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data (including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.
4.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.
4.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in the Contract Clauses Section of this contract.
4.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.
5.0 ENVIRONMENTAL IMPACT
All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ);
the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16
BLM Northwest Oregon District Page 11 of 67
U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.
6.0 HAZARDOUS MATERIALS
Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.
Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR
1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.
7.0 GREEN PROCUREMENT REQUIREMENTS
In the performance of this service or construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, if applicable:
• U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.
• USDA Biobased product listings published at www.biopreferred.gov.
• Energy Star® product listings published at www.energystar.gov/products.
• FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories
Contractor shall comply with all reporting requirements stated in the applicable clause(s):
• 52.223-2 Reporting of Biobased Products under Service and Construction Contracts
• 52.223-4 Recovered Material Certification
• 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items
8.0 RESTORATION OF RESOURCES
8.1 Cleanup - The Contractor is responsible for cleaning up all camp and worksites before leaving the area.
Final payment or other alternative deemed feasible may be withheld until the Contractor has complied with this requirement.
8.2 Site and Access Roads – Site and public or private access roads damaged by the Contractor shall be restored to the same condition they were in at the commencement of work, at the expense of the Contractor.
9.0 UNAUTHORIZED PERSONNEL
http://www.epa.gov/cpg/products.htm http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories http://energy.gov/eere/femp/covered-product-categories
BLM Northwest Oregon District Page 12 of 67
The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
10.0 OREGON FARM/FOREST LABOR CONTRACTOR'S LICENSE
If the State of Oregon requires an Oregon Farm/Forest Labor Contractor's License, then the contractor awarded this contract and all first-tier subcontractors shall be required to obtain and maintain, during the term of this contract, such a license. Contractors not having a current license will be required to furnish evidence of having obtained such license within ten (10) days after receipt of written notification of contract award. Failure to obtain, keep and maintain a current license during the term of this contract or the extension thereof shall be a basis for termination for default.
Information on obtaining this license may be obtained from:
Bureau of Labor and Industries Contact: Licensing Unit Wage and Hour Division Telephone: (503) 373-1463 3865 Wolverine St. NE; E-1 Fax: (503) 373-7636 Salem, OR 97305-1268
11.0 FIRE DANGER SEASON
If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR and outlined in the attachment at the end of this section.
The following clause is provided in full text:
SECURITY REQUIREMENTS: FACILITY ACCESS and INFORMATION TECHNOLOGY (August 2016)
(a) All Contractor employees must have an "Enter on Duty" (EOD) approval issued by the Bureau Personnel Security Office (PSO) before they begin performing work on any Bureau contract. The Contractor must ensure that all employees requesting an EOD are citizens of the United States of America, or an alien who has been lawfully admitted for permanent residence or employment (indicated by immigration status) as evidenced by Immigration and Naturalization Service documentation and the employee must have resided in the United States for a minimum of 3 years. The EOD may be issued in advance of a completed Background Investigation and may be rescinded by the PSO at any time. However, all contractors who require network access are required to complete the identity proofing process, and must be able to obtain a successfully adjudicated National Criminal History Check (NCHC) and National Agency Check with Inquiries (NACI) or higher to stay on the contract.
(b) Starting Work - Contractor employees with an approved EOD may begin performing unsupervised work on Bureau contracts. To remain on the contract, the Contractor employees will need a completed favorable Background Investigation.
(c) Rescission of EOD - The PSO may rescind the EOD at any time. This may occur as the result of additional information obtained or the final results of the background investigation.
(d) Background Investigation - Contractor employees who will have unsupervised access to Bureau facilities, access to the Department of the Interior (DOI) information technology (IT) systems or DOI data, or will develop custom applications, must have a favorably adjudicated background investigation from the Office of
BLM Northwest Oregon District Page 13 of 67
Personnel Management (OPM). Existing clearances at the same or higher level are acceptable upon the PSO’s review and approval. If the employee does not already have a complete investigation, they must apply for one. The employee may begin work with an EOD, but must receive a favorable background investigation to continue working on the contract. The background investigation includes obtaining fingerprints through a USAccess Credentialing Center for an FBI criminal history and a credit report. Once the investigation has been scheduled by OPM, the Bureau will receive advance reports. If those reports are favorable, the Bureau PSO will issue the EOD. The type of background investigation required is based on the risk/sensitivity level designation. Citizenship requirements and guidance for determining the appropriate type of background investigation required for the designated risk/sensitivity level are contained in DOI Departmental Manual (DM) Part 441. The DM is available on the Internet at http://elips.doi.gov/app_home/index.cfm?fuseaction=home.
(e) Electronic Questionnaire for Investigations Processing (e-QIP) – The Bureau uses the e-QIP for all background investigations or reinvestigations. To initiate an investigation, the Contractor, in collaboration with the COR, will complete an e-QIP Request Form. This request form is available through the COR. The COR will submit the completed request form to the Bureau PSO. The PSO will enter the information into e-QIP to either establish a new applicant profile or determine if an existing investigation that meets Bureau requirements is on file. The PSO will then contact the applicant to provide additional information and instructions. Generally, the Contractor is required to complete the following forms:
▪ e-QIP application (on-line)
▪ Fair Credit Release
▪ OF-306
▪ Fingerprints via USAccess Credentialing Centers
The Contractor shall complete the required background investigation forms and submit them to the PSO. The PSO shall determine if individuals meet the required background investigation standards and citizenship requirements, and then make a suitability determination. Minimum standards used in suitability determinations are contained in the DOI Departmental Manual Part 441. The Government will pay for any background investigations required for contractor employees. If the Contractor employee’s background investigation is returned as unfavorable, the Government reserves the right to request reimbursement of the actual costs for the investigation from the Contractor.
(f) Reinvestigation - Contractor employees occupying high risk public trust positions must be reinvestigated every 5 years. A reinvestigation may be initiated prior to the normal periodic reinvestigation schedule when an individual’s continued ability to meet the minimum background investigation standards is in question. The electronic fingerprints on file in the USAccess system will be electronically submitted to OPM for the reinvestigation. The PSO shall review the records and documentation and make the suitability determination.
(g) Disputes - In the event of a disagreement between the Contractor and the Government concerning the suitability of a particular employee to perform work under this contract, the Government has the right of final determination. Determinations under this requirement are subject to the Disputes Clause, FAR 52.233-1. Failure of the Contractor to comply with the requirements of this clause could constitute grounds for termination for default.
(h) Physical Security Requirements - DOI Access Cards.
(1) Contractor employees must have a DOI Access Card before being given unsupervised access to a Government facility.
(2) To gain unsupervised access to Government facilities, Contractor employees must present their DOI Access Card for examination by the security guard or electronically authenticate their DOI Access Card, as required. Contractor employees must keep their DOI Access Card in a shielded card holder, and visually display the card at all times while in the facility. Refusal or repeated neglect to display the DOI Access Card may result in limiting Contractor employee’s access to Government facilities or revoking of authorized access.
BLM Northwest Oregon District Page 14 of 67
(3) When a Contractor employee is no longer working under this award, the Contractor is responsible for returning all DOI Access Cards, keys, and other Government property issued to that employee. The Contactor shall coordinate all returns with the COR. The COR is responsible for ensuring the Contractor complies with these requirements. However, failure by the Contractor to comply with these requirements may result in the Contractor’s liability for all costs associated with correcting any resultant breech in building security.
(i) Issuance & Maintenance - DOI Access Cards
(1) Process: To obtain a DOI Access Card the COR will use the online DOIAccess System to initiate the access request. Contractor employees will receive email notificat ions to enroll at a USAccess Credentialing Center with two forms of identification, and after adjudication, a second email notification to pick up and activate their DOI Access Card. The Contractor employee shall schedule an enrollment appointment at a USAccess center at least two weeks prior to the targeted EOD.
(2) Contractor Responsibilities: Contractor employees must complete actions in a timely manner to prepare for on-boarding and access to DOI network resources. The Contractor shall allow their personnel sufficient time to schedule and attend an enrollment appointment at the USAccess center prior to the contract start date. If the Contractor employee’s DOI Access Card becomes lost or stolen, the contractor employee shall notify the COR immediately to request a new DOI Access Card.
(3) COR Responsibilities: The COR (or designated individual) and Contractor shall maintain a listing of all Contractor employees who received a DOI Access Card, the date the card was issued, the date the electronic certificates expire (3 years from issue date), and the date the DOI Access Card expires (5 years from issue date). If the Contractor employee’s DOI Access Card or certificates will expire before the contract is completed, the COR (or designated individual) and Contractor is responsible for ensuring that the Contractor employee visits a USAccess center to update certificates on the existing card or obtain a new DOI Access Card. No later than one week prior to the DOI Access Card’s certificate or card expiration, the COR (or designated individual) shall notify the Contractor that DOI Access Card actions are required. The COR (or designated individual) and the Contractor shall update their listing to reflect the new issue date, certificate expiration date and card expiration date.
(j) Information Technology Security Requirements.
(1) Training – If contractor employees require access to any DOI/IT systems, the Contractor shall ensure its employees complete all Bureau/DOI required IT security training. The Contractor’s employees shall complete this training before being granted access to Bureau/DOI data or being issued network access. The current training requirements are: (i) annual end-user IT Security Awareness, (ii) annual IT Resources Rules of Behavior, and (iii) annual Role-Based Security training for IT professionals. The Contractor shall comply with all Bureau/DOI IT security training requirements in effect during contract performance. The COR will notify the Contractor of all Bureau mandatory IT training. The Contractor shall submit training completion certificates to the COR for all required training. Failure to meet this training requirement may result in removal of the contractor employee from the contract. The Bureau will determine if the contractor can later return to the contract.
(2) Access to Contractor’s Facilities for IT audit purposes - The Contractor shall afford Bureau and the Department of the Interior Office of Inspector General access to the Contractor’s and subcontractors’ facilities, installations, operations, documentation, databases, and personnel used in performance of the contract.
Access shall be provided to the extent required to carry out a program of IT inspection, investigation, and audit that will safeguard against threats and hazards to the integrity, availability, and confidentiality of Government data or to the function of computer systems operated on behalf of the Government and to preserve evidence of computer crime. If the Contractor questions the Government employee’s right to access its facilities, it should contact the CO for resolution.
(3) Contractor Location - Custom software development and outsourced operations shall be located in the United States to the maximum extent practical. If such services are proposed to be performed abroad, BLM Northwest Oregon District Page 15 of 67 the Contractor shall provide an acceptable security plan that addresses the mitigation of problems related to communication, control, and protecting the confidentiality, integrity, and availability of IT systems and information.
(4) Applicable Standards - The Contractor shall follow all applicable Federal, DOI, and Bureau Bulletins, Directives, Guidelines, Manuals, Processing Standards, Memoranda, Policies and Standards; applicable OMB Memoranda; and all current National Institute of Standards & Technology (NIST) Special Publications. To comply with Federal Acquisition Regulation Subpart 39.101(d), contractors shall use the common security configurations available from the NIST website at http://checklists.nist.gov. NIST documents are available on the internet at http://csrc.nist.gov/publications/PubsSPs.html. OMB memoranda are available on the internet at http://www.whitehouse.gov/omb/memoranda/. The Contractor shall request copies of DOI and Bureau documents by contacting the COR.
(5) Incident Reporting - The Contractor shall immediately report computer security incidents affecting Bureau/DOI data and systems in accordance with the Bureau Computer Incident Response policy. The Contractor shall request copies of the Bureau Computer Incident Response policy by contacting the COR.
(6) Assessment and Authorization (A&A) and Continuous Monitoring.– The Contractor shall comply with Bureau policy when developing, upgrading, modifying or supporting applications and/or systems that require A&A and Continuous Monitoring. The Contractor shall request copies of Bureau A&A policy by contacting the COR. The A&A requirement does not apply when the Contractor's employees merely access data or have "read only" access.
(k) Documentation - The Contractor shall document all work performed and ensure that the appropriate Assessment and Authorization (A&A) documents are updated to reflect the work performed and the current state of Bureau systems and networks. The Documentation requirement does not apply when the Contractor's employees merely access data or have "read only" access.
(l) Personnel Changes, Contractor Request - The Contractor shall immediately notify the COR and PSO when an employee is reassigned or leaves the Contractor’s employment and prior to any termination. The Contractor must adhere to the Bureau or Office’s mandatory exit clearance procedure. Once the COR has been notified that a Contractor employee is leaving the contract, the COR will initiate the exit clearance process in the DOIAccess System and forward to the Contractor the necessary instructions and form required to be completed prior to the contractor's employee’s departure. This form must be completed by the Contractor's employee and signed by both the Contractor's employee and the COR and then forwarded to the bureau/office specific program responsible for employee, volunteer, and contractor departures.
(m) Personnel Removal, Government Request - The Government retains the right to direct the Contractor to remove any prime or subcontractor personnel, regardless of prior clearance or background investigation adjudication status, whose actions, while assigned to this contract, clearly conflict with the security interests of the Government. The justification for the Government’s direction to remove Contractor personnel will be documented and provided to the Contractor by the CO.
(n) Subcontract Inclusion - The requirements of this clause must be incorporated into any subcontract if the subcontractor’s employee must have access to Bureau facilities.
(End of clause)
BLM Northwest Oregon District Page 16 of 67
FIRE REQUIREMENTS PROCEDURES OUTLINE [FOR OREGON, Dec 2013]
This outline covers the fire protection requirements of a contractor or private party who performs service or construction contracts on BLM land. In western Oregon, the BLM allows Oregon Forest Law (ORS) and Oregon Administrative Rules (OAR) to apply to these operations on BLM lands rather than develop similar rules applicable only to BLM lands.
1. CLOSED FIRE SEASON
The closed fire season means that fire season has been declared. ORS 477.505 gives the State Forester the authority to establish the fire season. The authority has been delegated to the District Foresters around the state who issue public notices through the newspapers and radio when fire season will be closed for their individual districts.
Closed fire season depends upon the drying of forest fuels, rainfall, and time of year. During the closed fire season, the following requirements must be met:
• Fire tools must be on site;
• Fire extinguisher must be in all vehicles;
• Chainsaws must have a .023-inch mesh screen installed in the exhaust;
• Only unmodified saws are to be used in the forest;
• Approved spark arresters must be on all internal combustion engines;
• Watchman service must be provided for 3 hrs after shutdown of power equipment for the day;
• No smoking is permitted while working or traveling through any operations area in the forest;
• No use of explosives is permitted unless approved by the State Forester's representative;
• Permits to burn are required unless waived by a representative of the State Forester.
• Permits to operate power-driven machinery shall be obtained by the Contractor prior to commencing operations unless waived by a representative of the State Forester (ORS 47.625).
Changes or modifications to the above requirements are possible depending upon changes in State of Oregon law and requirements of the State Districts and Protective Associations.
2. FIRE PRECAUTION LEVELS
There are 4 fire precaution levels that begin with level 1 at the start of the closed fire season and can go through level 4 if conditions warrant. The fire precaution levels restrict certain forest operations as the fire danger increases.
It is the responsibility of the individual operating on forest land to know the precaution level for the day and take the correct fire precautions. There are no precaution levels prior to the closed fire season. Each fire precaution level requires adherence to the restrictions applicable to all lower levels in addition to the limits placed by that level.
Level 1 is the lowest level of fire danger usually occurring early in the season and perhaps again after significant rainfall during the season. All requirements listed above apply. Waivers may be issued by the State Districts or Protective Associations and these MUST be approved by the BLM. Waivers will only be considered if the conditions on the work site are not as severe as predicted. The requirements for fire tools on site, screens installed in saws, and fire extinguishers with saws will not be waived.
Level 2 is the partial hootowl where saws can operate from first light in the morning until 1:00 p.m. in the afternoon.
From 1:00 p.m. until the end of the day saws are to be shut down. Waivers for operating beyond the 1:00 p.m.
shutdown will be evaluated on a site-by-site basis.
Level 3 is the partial shutdown of all forest industrial operations and shuts down contractor operations with few exceptions. Waivers may be issued on a site-by-site basis.
Level 4 is the general shutdown of all contractor operations. Waivers will not be issued. Landowners are permitted entry into their lands.
ORS. 477.066 requires that an operator on forest land take immediate action to control and extinguish a fire on forest land. The contractor shall take this action and notify the BLM and the nearest State of Oregon District office immediately.
OAR. 629-43-030 requires watchmen to be:
BLM Northwest Oregon District Page 17 of 67
• Physically capable and experienced in operating any firefighting equipment on site.
• On duty for 3 hours after the shutdown of the last power-driven equipment for the day.
• Furnished adequate facilities for transportation and communications in order to summon assistance if needed.
• Patrolling and visually inspecting all sites where work was done during the day.
3. FIRE TOOLS REQUIRED DURING CLOSED FIRE SEASON
The operator/contractor shall furnish fire tools to all personnel on site using the following combinations.
NUMBER OF PERSONNEL_______________________________
1- 4 5 6 7 8 9 10 11 12 13 14
KIND OF TOOLS NUMBER OF TOOLS REQUIRED_________________________
Pulaskis 1 1 1 1 1 1 2 2 2 2 2
Shovels 2 2 2 3 3 3 3 4 4 5 5
Hazel hoes 1 2 3 3 4 5 5 5 6 6 6
In addition to the above handtools, the operator/contractor must provide a backpack pump can filled with water located with the tool box in a readily available area.
All shovels are to be size 0 or larger, long handled. All tools shall be sharp and ready for service. Fire extinguishers as follows:
For chainsaws - 8 oz. capacity by weight.
For vehicles - UL rating of at least 4 BC.
4. ADDITIONAL WATER SUPPLY
Contractor shall comply with ORS 477.615 during fire season when inside or within one-eighth of one mile of a state forest protection district and furnish additional water supply and equipment for use in fire suppression in conformity with the rules promulgated by the Oregon State Forester, when directed by the Oregon State Forester in writing. When required, all water supply and equipment components shall be maintained and ready for immediate use.
During fire season when operating a stationary internal combustion engine inside or within one eighth of one mile of a state forest protection district, Contractor shall comply with ORS 477.650 and provide a water supply, with equipment for its use in fire suppression for each engine, in conformity with the rules promulgated by the Oregon State Forester. All water supply and equipment components shall be maintained and ready for immediate use.
(End of Special Contract Requirements)
BLM Northwest Oregon District Page 18 of 67
BLM FIRE PROTECTION REQUIREMENTS [FOR WASHINGTON, Dec 2013]
This outline covers the fire protection requirements of a contractor or private party who performs service or construction contracts on BLM land. In Washington State, the BLM, US Forest Service, Bureau of Indian Affairs, and Washington State Department of Natural Resources all use the same four-level industrial regulation system.
This system, which helps prevent wildfires by regulating work in the woods, is known as the Industrial Fire Precaution Level (IFPL) system.
Information available at: http://www.blm.gov/or/districts/spokane/fire/index.php
For areas outside this link (generally the Columbia Basin) call the local BLM office. Spokane 509-536-1200 Wenatchee 509-665-2100.
1. CLOSED FIRE SEASON
The closed fire season means that fire season has been declared. The BLM works with their neighboring agencies when declaring this issuing public notices through the newspapers and radio when fire season will be closed for their individual districts. Closed fire season depends upon the drying of forest fuels, rainfall, and time of year. During the closed fire season, the following requirements must be met:
a. Fire tools must be on site;
b. Fire extinguisher must be in all vehicles;
c. Chainsaws must have a .023-inch mesh screen installed in the exhaust;
d. Only unmodified saws are to be used in the forest;
e. Approved spark arresters must be on all internal combustion engines;
f. Watchman service must be provided for 3 hrs after shutdown of power equipment for the day;
g. No smoking is permitted while working or traveling through any operations area in the forest;
h. No use of explosives is permitted unless approved by the BLM representative;
i. Permits to burn are required unless waived by a BLM representative.
j. Permits to operate power-driven machinery shall be obtained by the Contractor prior to commencing operations unless waived by a representative of the State Forester.
2. FIRE PRECAUTION LEVELS
There are 4 fire precaution levels that begin with level 1 at the start of the closed fire season and can go through level 4 if conditions warrant. The fire precaution levels restrict certain forest operations as the fire danger increases.
It is the responsibility of the individual operating on forest/range land to know the precaution level for the day and take the correct fire precautions. There are no precaution levels prior to the closed fire season. Each fire precaution level requires adherence to the restrictions applicable to all lower levels in addition to the limits placed by that level.
At any time the local Fire Management Officer, reserves the right to shut down any and all operations regardless of the precaution level.
Level I: Closed Fire Season: Fire equipment and firewatch service is required.
Level II: Partial Hootowl: Limits certain activities between the hours of 8 p.m. and 1 p.m.
Level III: Partial Shutdown: Prohibits some activities altogether and limits other activities between the hours of 8 p.m. and 1 p.m.
http://www.blm.gov/or/districts/spokane/fire/index.php
BLM Northwest Oregon District Page 19 of 67
Level IV: General Shutdown: All operations prohibited.
Example of restrictions:
BLM Northwest Oregon District Page 20 of 67
3. FIRE TOOLS REQUIRED DURING CLOSED FIRE SEASON
The operator/contractor shall furnish fire tools to all personnel on site using the following combinations.
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
1-4 5 6 7 8
KINDS
OF
TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
Pulaskis 1 1 1 1 1 Shovels 2 2 2 3 3 Adz Hoe
1 2 3 3 4
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
NUMBER
OF
PERSONNEL
9 10 11 12 13 14
KINDS
OF
TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
NUMBER
OF TOOLS
Pulaskis 1 2 2 2 2 2 Shovels 3 3 4 4 5 5 Adz Hoe
5 5 5 6 6 6
In addition to the above handtools, the operator/contractor must provide a backpack pump can filled with water located with the tool box in a readily available area.
All shovels are to be size 0 or larger, long handled. All tools shall be sharp and ready for service. Fire extinguishers as follows:
a. For chainsaws - 8 oz. capacity by weight.
b. For vehicles - UL rating of at least 4 BC.
4. FIREWATCH SERVICES
The purpose of the firewatch is to stay after the day's work is over and report any fire starts to the proper authorities.
The firewatch is required to be on duty after the last power-driven equipment used by the operator has been shut down for the day. The firewatch must be on duty a minimum of one hour. During periods of high fire danger, BLM recommends the firewatch be on the operation site more than the mandated one hour.
A firewatch must:
BLM Northwest Oregon District Page 21 of 67
• Visually observe all parts of the operation area on which industrial activity has been in progress.
• Be physically capable of fighting a fire and experienced in operating fire-fighting equipment.
• Have on-site communication (CB radio, cellular or radio phone) to…