Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040534791

BLM NM-STATE OFC-SANTA FE(NM916)

301 DINOSAUR TRAIL

SANTA FE NM 87508

LXA

Sarah Valencia svalencia@blm.gov

Sarah Valencia 5057618950

107/09/2021

140L4021Q0009

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Bureau of Land Management - New Mexico State Office

Roswell Field Office Pecos District Fence Construction

See the enclosed statement of work, terms, conditions and provisions.

Pre-bid site visit scheduled for Monday July 19, 2021. Meet at the Roswell Field

Office: 2909 W 2nd Street Roswell, NM 88201 at 8:00am. Interested contractors shall be prepared with a high clearance 4X4 vehicle, lunch and water.

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

60 90 calendar days and complete it within ________________ ________________ calendar days after receiving

08/09/2021

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Sarah Valencia

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 81

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140L4021Q0009

Delivery: 08/03/2020

Delivery Location Code: 0004276456

BLM-NM ROSWELL FIELD OFFICE

2909 WEST 2ND STREET

ROSWELL NM 88201-2019 US

00010 CFO Siegrest Draw Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00020 CFO Cawley Draw Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00030 CFO Stinking Draw Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00040 CFO Johnny Joy Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00050 CFO Box Canyon Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

4 81

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140L4021Q0009

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00060 RFO SEMid CC Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00070 RFO Draper RD Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00080 RFO NW CC Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00090 RFO E CC Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

FOB: Destination

00100 RFO Brown Lake Fence 1 EA

Product/Service Code: F099

Product/Service Description: NATURAL

RESOURCES/CONSERVATION- OTHER

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

5 81

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140L4021Q0009

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Table of Contents

Schedule of Items ………………………………………………………………………………………….. 5

Description/Specifications/Statement of Work ……………………………………………………………. 6

Work Data Sheet………………………………………………………………………………………... 11

Inspection and Acceptance…………………………………………………………………………………. 12

Contract Clauses……………………………………………………………………………………………. 13

List of Attachments………………………………………………………………………………………… 25

Wage Determinations…………………………………………………………………………………… 26

Standard Specifications for Metallic-Coated Carbon Barbed Wire…………………………………….. 35

Legend…………………………………………………………………………………………………... 39

Three Brace Corner Panel………………………………………………………………………………. 40

Angel Iron Corner Detail………………………………………………………………………………... 41

Angle Iron Corner Detail Obtuse Corners………………………………………………………………. 43

Angel Iron Drainage Crossing…………………………………………………………………………... 44

Angel Iron End Panel…………………………………………………………………………………… 45

Angel Iron Fence Post ASTM Spec…………………………………………………………………….. 46

Angel Iron Stress Panel…………………………………………………………………………………. 50

Angel Iron Wire Gate…………………………………………………………………………………… 51

2018 CFO Box Canyon South Fence…………………………………………………………………… 52

2021 CFO Box Canyon Seigrest Draw…………………………………………………………………. 53

2021 CFO 6 Passes Cawley Draw………………………………………………………………………. 54

2021 CFO North Johnny Joy Fence…………………………………………………………………….. 55

2021 CFO South Johnny Joy Fence…………………………………………………………………….. 56

2021 Stinking Draw II Fence…………………………………………………………………………… 57

2021 PDO Fence Construction Overall…………………………………………………………………. 58

2021 Pecos Fence Construction Binder………………………………………………………………… 59

2021 RFO Brown Lake 3 Passes………………………………………………………………………... 72

2021 RFO Draper Rd Chimney Canyon………………………………………………………………... 73

2021 RFO SE Middle Chimney Canyon………………………………………………………………... 74

2021 RFO NW Chimney Canyon 75

Instructions, Conditions and Notices to Offerors and Respondents………………………………………... 76

Basis for Award…………………………………………………………………………………………….. 77

Evaluation Factors for Award……………………………………………………………………………… 78

Schedule of Items

Pay Item Description Quantity* Unit Unit Price Total

1 Fence Removal 51885 LF

2 Barbed Wire Fence (4 Strand) 62795 LF

3 Angle Iron Corner Panel (CP) 10 EA

4 Angle Iron Corner Panel 3 brace (3BCP) 4 EA

5 Angle Iron End Panel (EP) 36 EA

6 Angle Iron Stress Panel (SP) 44 EA

7 Barbed Wire Gate - 4 Wire (WG) 21 EA

8 Single Angle Metal Post (SMP) 5 EA

9 Mob/Demob 1 LS

10 Bonding 1 LS

11 Taxes 1 LS

Total $

LF = Linear Foot, EA = Each and LS = Lump Sum

All quantities are estimates

Description/Specifications/Statement of Work

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Task Order Documents.

2. Geotechnical data.

3. Specification formats and conventions.

1.2 WORK COVERED BY TASK ORDER

A. Project Identification: Pecos District Fence Construction

1. Project Location: Work identified in this contract will be located in Chaves, Eddy, and Lincoln

Counties in the state of New Mexico.

B. The Work consists of the following:

1. Furnishing all labor, equipment, supplies, and materials required to, remove ~10 miles of fence, construct approximately ~12 miles of four-strand barbed wire fences, and build bid items in accordance with the Specifications, Drawings, Maps, and Work Data Sheets. Vehicle traffic along fence lines is allowed within 15 feet of each side of the fence. No scalping of soil along fence line is allowed, however, brush may be removed with equipment. Contractor is responsible for complete removal and recycle of the old fence wire and twisted wire stays from the public lands.

Contractor may broker their own agreement with the allottee to place old fence materials on the allottee private land instead of taking them to local dumps. Clearing of fence lines is minimal and does not have a line item, all trees and brush that require cutting shall be cut at ground level and carried 10 to 15 feet of the fence lines and lain down. All equipment shall be washed of soil and vegetative material before mobilization to the construction site. Additionally, all equipment shall be washed clean of all soil and vegetative material between construction locations. This washing and cleaning process is required to prevent the spread of noxious and invasive weeds. The period of performance on this contract is 90 calendar days after the Notice to Proceed (NTP) is issued by the

Contracting Officer. The contractor shall provide a written work schedule at the prework meeting, and update it monthly, or as requested by the Contracting Officer Representative (COR). The contractor shall provide a written safety and fire plan acceptable to the Contracting Officer prior to construction.

Personal Protective Equipment (PPE) such as hardhats, work gloves, and traffic safety vests shall be used according to OSHA and other safety regulations.

GEOTECHNICAL DATA

C. Geotechnical Data: No Geotechnical Information Maps are included in this contract. Determination of actual subsurface soil conditions at the project site shall be Contractor's responsibility.

D. END OF SECTION 01100

SECTION 02000 - WIRE FENCES AND GATES

PART 2 - GENERAL

2.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

Division 01 Specification Sections, apply to this Section.

2.2 SUMMARY

A. Section Includes:

1. Metallic-coated-steel, welded-wire fences.

2. Wire gates.

B. Product Data: For each type of product.

PART 3 - PRODUCTS

3.1 MATERIALS

A. Barbed Wire: A strand of two 12-1/2 gauge galvanized wires twisted together with 2-point barbs of 14 gauge wire spaced 4” apart. Wire and barbs shall be zinc-coated steel, with a zinc coating of at least 0.28 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb-force. The barbed wire shall conform to ASTM A 121.

B. Barbless Wire: A strand of two 12-1/2 gauge, galvanized wires twisted together. Wire shall be zinc coated steel wire of at least 0.28 oz per square foot of coated surface area. The minimum breaking strength of each wire shall be 950 lb-force. The barbless wire shall conform to ASTM A 121

C. Wire Fence Stays: 36” twisted wire fence stays manufactured from smooth galvanized 9-1/2 gauge

(minimum) wire. ASTM A 121.

D. Steel Angle Iron Upright Post: Uprights shall consist of angles with a nominal size 2 ½” by 2 ½” by ¼” weighing approximately 4.10 lb/ft prior to fabrication. Total length shall be 7’ per post. Uprights shall be furnished with the necessary holes and galvanized hardware for the required assembly (See section 2.

MATERIALS F. Fasteners). All posts shall be cleaned of all loose scale prior to finishing, and painted solid green (Federal Standard 595B with one or more coats of weather resistant, air drying or baking paint or enamel. The steel posts shall be in conformance with ASTM, "Specification for Steel Fence Posts and

Assemblies, Hot Wrought," ASTM A36/A36M.

E. Steel Angle Iron Brace Post: Braces shall be factory new and consist of angles nominal size 2” by 2” by

¼” weighing approximately 3.19 lb/ft prior to fabrication. Total length shall be 7’ per post. Braces shall be furnished with the necessary holes and galvanized hardware for the required assembly (See section 2.

MATERIALS F. Fasteners). All posts shall be cleaned of all loose scale prior to finishing, and painted solid green (Federal Standard 595B with one or more coats of weather resistant, air drying or baking paint or enamel. The steel posts shall be in conformance with ASTM, "Specification for Steel Fence Posts and

Assemblies, Hot Wrought," ASTM A36/A36M.

F. Fasteners: 0.50” Nuts, and 0.50 by 1.5” bolts required. All bolts and nuts shall be new and conform to grade 5 ASME B 18 2 1, ASME B 18 2 2, and ASME B 18 21 1 respectively.

G. Steel Fence SPEC Posts: All t-posts shall be factory new 5’6”, or 7’0” for the Sand Dune fence, steel fence posts, 8” silver painted top with the remainder being green “T” bar type, with a welded or riveted anchor plate. Furnish with clip type wire fasteners (punched tabs for fastening wires are not acceptable). Steel posts shall be manufactured from wrought, rail, or new billet steel, and shall have a minimum weight of

1.33 lb/linear ft. The anchor plates shall weigh a minimum of 0.67 pounds +5 percent, and be a minimum of 18 square inches in area. The steel fence posts shall conform to ASTM A 702. SPEC t-post.

H. Steeples/Staples: New bright-finish or galvanized 9 gauge with slash-cut points 1-1/2” long designed for outdoor use and shall conform to ASTM F1667.

I. Wooden gate posts: Juniper (Cedar) wood posts 48” length and 3” minimum diameter. Acceptable Wood

Gate Posts: A slight bend in one plane is acceptable. Basis for Rejection: Posts are not acceptable when sweep causes a straight line joining the center of the top to the center of the butt to fall outside the body of the post, or at a point 2 inches or more from the center of the post. Posts that are charred, twisted, rotted, or excessively bent are not acceptable. Seasoning checks are not acceptable.

J. Sacked concrete: 80 lbs. sacks ASTM C 404.

PART 4 - EXECUTION

4.1 EXAMINATION

A. Examine areas and conditions for site clearing, construction layout, and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

4.2 PREPARATION

A. Prior to fence construction activities, the Contractor shall attend a site meeting with the COR to discuss extents of ground disturbance on site. Contractor shall stake locations of fence lines, gates, and terminal posts. Do not exceed intervals of 1320 feet or line of sight between stakes. The Contractor shall be responsible for ensuring adequate access to the site to facilitate earthwork, hauling of materials, and proper fence construction. Extents of allowable ground disturbance will be indicated by BLM personnel prior to commencing earthwork activities. Indicate locations of utilities, underground structures, benchmarks, and property monuments. Contractor is solely responsible for OneCall process and utility locates and protection of existing utility resources. No construction will be allowed on site until the

OneCall process is complete and the Contracting Officer’s Representative (COR) has an email verifying the OneCall process is complete.

4.3 FENCE INSTALLATION

A. Install fences according to contract maps and drawings.

B. Post Excavation for brace panels: Drill or hand-excavate holes for posts in firm, undisturbed soil. Excavate holes to a diameter of not less than 10” and a depth of not less than 39”, with 3” of concrete below the bottom of the post. Angle iron posts may be drilled to a diameter of approximately 3” excavated into solid rock to a depth of 36” and then the rock and debris packed back into the excavation hole with concrete. Angle iron posts and braces may not be cut less than the 7’ prescribed amount. All above ground portions of brace posts shall be no more than 48” with 36” below ground. Concrete for braces must be poured at least equal with existing soil surface. All brace angle iron posts shall be constructed with a 16” by 16” by 16” cube of concrete. All brace bolts and nuts shall be tightened with a mechanical advantage such as wrenches or socket and driver. Pipe and wood braces are not allowed.

C. Post Setting: Set posts plumb and at indicated spacing and depth into firm, undisturbed soil, see 4.3 B.

1. Verify that structure posts are set plumb, aligned, and at correct height and spacing, and hold in position during setting with mechanical devices while setting in concrete.

D. Line posts (t-posts)

1. Mechanically Driven Posts (t-posts): Drive into soil to a depth of 18”. Protect post top to prevent distortion. Twisted or bent t-posts are not acceptable. Where conditions prohibit the mechanical driving of t-posts, it shall be permissible to drill a hole 18” deep and 1 ½” to 3” in diameter to receive the t-post without spade. In this instance the post hole must be securely packed with cutting material that was excavated by drilling. In situations where the prescribed wire height is greater than 4” from lengths designated in the work data sheet, due to topography between t-posts, a

“Deadman” shall be used to maintain proper wire height and to prevent t-posts from being pulled out and suspended in midair and be installed at no additional cost. A “Deadman” is properly constructed when a rock of 50 lbs. or greater is hung from the four strands of barbed and barbless wire or t-posts driven in at a 45 degree angle greater than 24” depth and the four strands of barbed and barbless wire are attached to the t-post used as a “Deadman”. “Deadmen” are not bid items and should be included in the cost per foot of fence. In hill top or sand dune top situations where the prescribed wire height is not maintained, an additional t-post must be installed at no additional cost. Additional hill and dune top t-posts are not bid items and should be included in the cost per foot of fence.

2. Space line posts uniformly at 16’-6” on center. Curved t-post lines between braces are not acceptable. Additionally, t-posts more than 12” out of straight line between braces will not be accepted and must be placed back into a straight line..

E. Wire

1. Wire: Stretch wire tightly and securely attach to steel posts with standard wire clips after the concrete has properly cured over 24 hours. Wire is correctly stretched when it is springy to the touch and does not sag more than 2” from a straight line between clips on t-posts, stay thread area, or braces wire wraps. Minimum wire tension per double wire strand is 150 pounds. Clips are properly installed when both ends wrap a minimum of one (1) time around each strand of wire at the t-post. Terminate wire at each end panel, corner post, stress panel, or single metal posts. Wrap wire around the post two times and tie off by wrapping around the incoming wire a minimum of four times. Kinked wire is not acceptable and must be spliced. Wire may be spliced with the terminal ends wrapped around the opposing strand a minimum of four times. Breakaways for drainage crossing shall be constructed from a single strand of 12-1/2 gauge galvanized wire per strand of barbed or barbless wire.

4.4 GATE INSTALLATION

A. Install gates according to contract drawings. The default gate width is always 16.5’. Juniper wood posts, 3” minimum diameter, shall be placed at each end of the wire gate and the wire shall be attached to the stays in the same manner as terminating wire at an angle iron upright post and shall be galvanized steel steepled. Operating gate side posts loop fasteners shall be constructed of barbless wire. A wire gate shall have a minimum of two twisted wire stays between the two juniper wood posts at either end. The wire loop used to hold the gate to provide articulation and access shall be held firmly in place by galvanized wire.

4.5 ADJUSTING

A. Gates: Adjust gates to operate smoothly, free of binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Confirm that gate has enough tension to operate accurately and securely without forcing or binding. Gates that cannot be closed and fastened without mechanical advantage or any one strand sag beyond 6”, shall be rejected for payment.

PART 5 - MEASUREMENT AND PAYMENT

5.1 METHOD OF MEASUREMENT

A. Units: The work described in this section will be paid by the foot for each type of fence as measured along the ground surface next to the completed fence using Global Positioning Systems (GPS) and Geographic information System (GIS), including distance across gate openings. If a discrepancy of more than 10% is suspected between the as built fence distances and the amounts listed on the maps, the contractor and

COR may measure the distance by chain steel, measuring tape, or hip (string) chain. The quantities of end panels, stress panels, corner panels, and gates will be paid for by the actual number of each item constructed and shall include cost for material and labor of required amount of concrete. Note: Gates do not include adjacent end panels, corner panels, or single metal posts. These are separate items.

B. BASIS OF PAYMENT

1. Payment: Prices and payment will be full compensation for all the work described in this section.

Payment will be made under:

Pay Item installed Description Pay Unit

1 Fence Removal Linear Foot

2 Barbed Wire Fence (4 strand) Linear Foot

3 Angle Iron Corner Panel Each

4 Angle Iron 3 Brace Corner Panel Each

5 Angle Iron End Panel Each

6 Angle Iron Stress Panel Each

7 Barbed Wire Gate (4 Wire) Each

8 Single Angle Iron Metal Post Each

WORK DATA SHEET

WIRE FENCES AND GATES

ALL FENCES

Fence type: 4-Twisted Strand Wire Fence

Type of top wire: Barbed Wire

Type of intermediate wires: Barbed Wire

Type of bottom wire: Barbless Wire

Wire locations/dimensions in inches (spacing):

D: 12"

C: 8"

B: 6"

A: 16"

Total fence wire height: 42”

Line post (t-post) spacing (L): 16’6”

Type of Stays: 36” twisted wire stays

Stay spacing (l): 16’6”

Brace Panels (corner, stress, and end panels): see drawings.

Length of wire gate wood posts (H1): 3” minimum diameter juniper species 48” tall

Length of steel posts (H2): 5’6”

Depth of steel posts in ground (h2): 1’6”

All gates: 16’6” (Unless otherwise noted on maps or drawings.)

Inspection and Acceptance

CLAUSES INCORPORATED BY REFERENCE

52.246-12 Inspection of Construction Deliveries or Performance AUG 1996

52.242-14 Suspension of Work APR 1984

CLAUSES INCORPORATED BY FULL TEXT

DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements & Internet Payment

Platform (IPP) (August 2013)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice

Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable

Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions -

Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the

IPP invoice: Copy of Original Invoice, Certification or Progress Payments Under Fixed-Price Construction

Contracts and/or DI-137 Release of Claims

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The

Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP

Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the

Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause) https://www.ipp.gov/

Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)

52.204-7 System for Award Management (Oct 2018)

52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Jun

2020)

52.215-2 Audit and Records--Negotiation (Jun 2020)

52.215-8 Order of Precedence--Uniform Contract Format (Oct 1997)

52.215-11 Price Reduction for Defective Cost or Pricing Data--Modifications (Jun 2020)

52.215-13 Subcontractor Cost or Pricing Data--Modifications (Jun 2020)

52.222-3 Convict Labor (Jun 2003)

52.222-6 Davis Bacon Act (Aug 2018)

52.222-7 Withholding of Funds (May 2014)

52.222-8 Payrolls and Basic Records (Aug 2018)

52.222-9 Apprentices and Trainees (Jul 2005)

52.222-10 Compliance with Copeland Act Requirements (Feb 1988)

52.222-11 Subcontracts (Labor Standards) (May 2014)

52.222-12 Contract Termination-Debarment (May 2014)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (May 2014)

52.222-14 Disputes Concerning Labor Standards (Feb 1988)

52.222-15 Certification of Eligibility (May 2014)

52.222-21 Prohibition of Segregated Facilities (Apr 2015)

52.222-26 Equal Opportunity (Sep 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015)

52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020)

52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)

52.225-13 Restrictions on Certain Foreign Purchases (Jun 2008)

52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises (Jun 2000)

52.227-1 Authorization and Consent (Jun 2020)

52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)

52.228-2 Additional Bond Security (Oct 1997)

52.228-5 Insurance - Work on A Government Installation (Jan 1997)

52.232-5 Payments under Fixed-Price Construction Contracts (May 2014)

52.232-23 Assignment of Claims (May 2014)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.232-33 Payment by Electronic Funds Transfer—System for Award Management (Oct 2018)

52.233-1 Disputes (May 2014)

52.233-3 Protest After Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-2 Differing Site Conditions (Apr 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984)

52.236-5 Material and Workmanship (Apr 1984)

52.236-6 Superintendence by the Contractor (Apr 1984)

52.236-7 Permits and Responsibilities (Nov 1991)

52.236-8 Other Contracts (Apr 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984)

52.236-10 Operations and Storage Areas (Apr 1984)

52.236-11 Use and Possession Prior to Completion (Apr 1984)

52.236-12 Cleaning Up (Apr 1984)

52.236-13 Accident Prevention (Nov 1991)

52.236-14 Availability and Use of Utility Services (Apr 1984)

52.236-15 Schedules for Construction Contracts (Apr 1984)

52.236-17 Layout of Work (Apr 1984)

52.236-21 Specifications and Drawings for Construction (Feb 1997)

52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) - Alternate I (Apr 1984)

52.236-26 Preconstruction Conference (Feb 1995)

52.243-4 Changes (Jun 2007)

52.243-5 Changes and Changed Conditions (Apr 1984)

52.244-6 Subcontracts for Commercial Items (Aug 2020)

52.246-21 Warranty of Construction (Mar 1994)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Apr 1984)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

52.253-1 Computer Generated Forms (Jan 1991)

1452.203-70 Restrictions on Endorsement-Department of Interior (Jul 1996)

1452.204-70 Release of Claims-Department of Interior (Jul 1996)

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days after acknowledgement of the notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

TERMS AND CONDITIONS-SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL ITEMS) (FEB 2021)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) (Section 1634 of Pub. L. 115-91).

(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(AUG 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).

(iv) 52.222-3, Convict Labor (JUN 2003) (E.O.11755).

(v) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

(vi) 52.222-26, Equal Opportunity (Sept 2016) (E.O.11246).

https://www.acquisition.gov/far/part-52#FAR_52_203_19 https://www.acquisition.gov/far/part-52#FAR_52_204_23 https://www.acquisition.gov/far/part-52#FAR_52_204_25 https://www.acquisition.gov/far/part-52#FAR_52_222_3 https://www.acquisition.gov/far/part-52#FAR_52_222_21 https://www.acquisition.gov/far/part-52#FAR_52_222_26

(vii) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

(viii) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C.3553).

(ix) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub.L.108-77, 108-78 (19 U.S.C. 3805 note)).

(2) Listed below are additional clauses that apply:

(i) 52.232-1, Payments (APR 1984).

(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).

(iii) 52.232-11, Extras (APR 1984).

(iv) 52.232-25, Prompt Payment (JAN 2017).

(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).

(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013).

(vii) 52.233-1, Disputes (MAY 2014).

(viii) 52.244-6, Subcontracts for Commercial Items (NOV 2020).

(ix) 52.253-1, Computer Generated Forms (JAN 1991).

(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020)(Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at or above the threshold specified in FAR 4.1403(a) on the date of award of this contract).

(ii) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (JAN 2020) (E.O. 13126) (Applies to contracts for supplies exceeding the micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract).

(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment., Contracts for Materials, Supplies, Articles, and

Equipment (JUN 2020) (41 U.S.C.chapter 65) (Applies to supply contracts over the threshold specified in FAR 22.602 on the date of award of this contract, in the United States, Puerto Rico, or the U.S. Virgin Islands).

(iv) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).

(v) 52.222-36, Equal Employment for Workers with Disabilities (JUN 2020) (29 U.S.C. 793) (Applies to contracts over the threshold specified in FAR 22.1408(a) on the date of award of this contract, unless the work is to be performed outside the United States by employees recruited outside the United States). (For purposes of this clause, "United States" includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)

(vi) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).

(vii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).

(viii) https://www.acquisition.gov/far/part-52#FAR_52_225_13 https://www.acquisition.gov/far/part-52#FAR_52_233_3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_233_4 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_232_1 https://www.acquisition.gov/far/part-52#FAR_52_232_8 https://www.acquisition.gov/far/part-52#FAR_52_232_11 https://www.acquisition.gov/far/part-52#FAR_52_232_25 https://www.acquisition.gov/far/part-52#FAR_52_232_39 https://www.acquisition.gov/far/part-52#FAR_52_232_40 https://www.acquisition.gov/far/part-52#FAR_52_233_1 https://www.acquisition.gov/far/part-52#FAR_52_244_6 https://www.acquisition.gov/far/part-52#FAR_52_253_1 https://www.acquisition.gov/far/part-52#FAR_52_204_10 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/part-4#FAR_4_1403 https://www.acquisition.gov/far/part-52#FAR_52_222_19 https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-52#FAR_52_222_20 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_222_35 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-22#FAR_22_1303 https://www.acquisition.gov/far/part-52#FAR_52_222_36 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-22#FAR_22_1408 https://www.acquisition.gov/far/part-52#FAR_52_222_37 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-22#FAR_22_1303 https://www.acquisition.gov/far/part-52#FAR_52_222_41 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-chapter67-front&num=0&edition=prelim

(A) 52.222-50, Combating Trafficking in Persons (OCT 2020)(22 U.S.C. chapter 78 and E.O. 13627) (Applies to all solicitations and contracts).

(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).

(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (NOV 2020) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).

(x) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2017) (E.O. 13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))

(xi) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2011) (E.O. 13423) (Applies to services performed on Federal facilities).

(xii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O.

13693)(applies to contracts for products as prescribed at FAR 23.804(a)(1)).

(xiii) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (JUN 2016) (E.O.

13693) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).

(xiv) 52.223-15, Energy Efficiency in Energy-Consuming Products (MAY 2020) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR® Program or Federal Energy Management Program (FEMP)) will be-

(A) Delivered;

(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;

(C) Furnished by the Contractor for use by the Government; or

(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance).

(xv) 52.223-20, Aerosols (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).

(xvi) 52.223-21, Foams (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent; or contracts for construction of buildings or facilities.

(xvii) 52.225-1, Buy American-Supplies (JAN 2021) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract, and the acquisition-

(A) Is set aside for small business concerns; or

(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).

(xviii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations., Promoting Excess Food Donation to Nonprofit

Organizations (JUN 2020) (42 U.S.C. 1792) (Applies to contracts greater than the threshold specified in FAR 26.404 on the date of award of this contract, that provide for the provision, the service, or the sale of food in the United States).

(xix) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (OCT 2013)(Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) as its source of EFT information).

(xx) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (JUL 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information).

https://www.acquisition.gov/far/part-52#FAR_52_222_50 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_222_55 https://www.acquisition.gov/far/part-52#FAR_52_222_6 https://www.acquisition.gov/far/part-52#FAR_52_222_41 https://www.acquisition.gov/far/part-52#FAR_52_222_62 https://www.acquisition.gov/far/part-52#FAR_52_222_6 https://www.acquisition.gov/far/part-52#FAR_52_222_41 https://www.acquisition.gov/far/part-52#FAR_52_223_5 https://www.acquisition.gov/far/part-52#FAR_52_223_11 https://www.acquisition.gov/far/part-23#FAR_23_804 https://www.acquisition.gov/far/part-52#FAR_52_223_12 https://www.acquisition.gov/far/part-52#FAR_52_223_15 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-23#FAR_23_204 https://www.acquisition.gov/far/part-52#FAR_52_223_20 https://www.acquisition.gov/far/part-52#FAR_52_223_21 https://www.acquisition.gov/far/part-52#FAR_52_225_1 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-19#FAR_19_502_2 https://www.acquisition.gov/far/part-52#FAR_52_226_6 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-26#FAR_26_404 https://www.acquisition.gov/far/part-52#FAR_52_232_33 https://www.acquisition.gov/far/part-52#FAR_52_232_34

(xxi) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. App. 1241) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d)).

(2) Listed below are additional clauses that may apply:

(i) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (JUN 2016) (Applies to contracts when the contractor or a subcontractor at any tier may have Federal contract information residing in or transiting through its information system.

(ii) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020) (Applies to contracts over the threshold specified in FAR 9.405-2(b) on the date of award of this contract).

(iii) 52.211-17, Delivery of Excess Quantities (Sept 1989) (Applies to fixed-price supplies).

(iv) 52.247-29, F.o.b. Origin (FEB 2006) (Applies to supplies if delivery is f.o.b. origin).

(v) 52.247-34, F.o.b. Destination (NOV 1991) (Applies to supplies if delivery is f.o.b. destination).

(c) FAR 52.252-2, Clauses Incorporated by Reference (Feb 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition,gov

(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract.

The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its post acceptance rights-

(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the

Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.

(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the

Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

https://www.acquisition.gov/far/part-52#FAR_52_247_64 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-47#FAR_47_504 https://www.acquisition.gov/far/part-52#FAR_52_204_21 https://www.acquisition.gov/far/part-52#FAR_52_209_6 https://www.acquisition.gov/far/part-9#FAR_9_405_2 https://www.acquisition.gov/far/part-52#FAR_52_211_17 https://www.acquisition.gov/far/part-52#FAR_52_247_29 https://www.acquisition.gov/far/part-52#FAR_52_247_34 http://www.acquisition,gov/

52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work (May 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b) (1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

(End of provision)

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999)

(a) The offeror’s attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor’s aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for Minority Participation for Each Trade Goals for Female Participation for Each Trade

7.5% 6.9%

These goals are applicable to all the Contractor’s construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical…

This is the start of the file's text. The full file is on GovTribe.