This is a Solicitation, Offer, and Award form (SF 1442) for a firm fixed price construction contract issued by the U.S. Fish and Wildlife Service (FWS), an agency within the Department of Interior. The solicitation number is 140FC326Q0055, issued on September 2, 2026, for garage and shop roof repairs at the Red Bluff Fish and Wildlife Office in Red Bluff, California (10950 Tyler Road, Red Bluff, CA 96080-7762). The contracting officer is Cindy Salazar, and interested parties may contact Jacqueline Gonzalez for site visits. The Request for Information (RFI) period ends September 14, 2026 at 5:00 PM PDT, with responses due September 16, 2026 at 5:00 PM PDT. Quotes should be submitted to Cindy Salazar at cindy_salazar@ios.doi.gov. The contract performance period runs from October 1, 2026 to December 31, 2026, with delivery required by December 31, 2026. The contractor must begin work within 60 calendar days of receiving notice to proceed and complete it within 90 days of award. Offers are valid for 90 days after the due date. A performance and payment bond is required within 10 days of award.
The Statement of Work requires comprehensive roof repair services including removal and installation of four new roof-top attic vents with 24-gauge pre-finished metal flashings, installation of metal Zee flashings, rubber pipe boot flashings for plumbing vents, and complete hip, rake, and ridge flashing replacement with new 24-gauge materials. Work must begin within 30 days of contract execution, occur during regular business hours Monday through Friday from 7:30 AM to 5:00 PM, and exclude federal holidays. The contract is subject to Davis-Bacon wage requirements (Tehama County General Decision Number CA20260007, effective May 18, 2026), and invoices must be submitted electronically through the Invoice Processing Platform (IPP). The contract includes liquidated damages of $400 per day for delays and incorporates standard FAR clauses including small business set-aside requirements (52.219-6), construction wage rate requirements (52.222-6), and environmental compliance provisions. A warranty must be provided for all installed roofing materials.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140FC326Q0055
FWS Constr A/E 3 FWS, Construction A/E Team 3 5275 Leesburg Pike Falls Church VA 22041
0044049980
FC3
Cindy Salazar 5038722832
09/02/2026
09/16/2026
15 90 Statement of Work
This is for a Firm Fixed Price Contract.
See attached:
Statement of Work
Construction Wage Determination Tehama County - General Decision Number: CA20260007 05/18/2026
Bid Schedule
Station Picture
1 81
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
5275 Leesburg Pike Falls Church VA 22041
FC3
Cindy Salazar
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FC326Q0055
Site Visit: Contact Jacqueline Gonzalez
(530-536-0016)
Request for Information (RFI) ends on
9/14/2026, 5:00 PM (PDT)
Response Due Date: 09/16/20206, 5:00 PM (PDT)
Submit quotes to Cindy Salazar via email:
cindy_salazar@ios.doi.gov
Delivery: 12/31/2026
Delivery Location Code: 0011280605
FWS RED BLUFF FISH AND WILDL OFC
10950 TYLER ROAD
RED BLUFF CA 96080-7762 US
Period of Performance: 10/01/2026 to
12/31/2026
00010 Garage and Shop Roof Repairs
Red Bluff Fish & Wildlife Office SOLICITATION NO. 140F0322Q0055 Garage and Shop Roof Repair
Section Title
Part I—The Schedule
A Solicitation/Contract Form
B Prices
C Description/Specifications/Statement of Work
D Packaging and Marking
E Inspection and Acceptance
F Project Delivery
G Contract Administration Data
H Special Contract Requirements
Part II—Contract Clauses
I Contract Clauses
Part III—List of Documents, Exhibits, and Other Attachments
J List of Attachments
Part IV—Representations and Instructions
K Representations, Certifications, and other Statements of Offerors
L Instructions, Conditions, and Notices to Offerors
M Evaluation Factors for Award
NOTE: Be advised that the controlling law regarding certain terms and conditions of this agreement remains unsettled by the Federal judiciary at the time of award and will be enforced only to the extent permitted by law.
Notice will be provided regarding the legal outcomes that impact your agreement.
52.252-2 – CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
As prescribed in 52.107(b), insert the following clause:
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul (FAR clauses begin with 52)
(End of Clause) https://www.acquisition.gov/far-overhaul
SECTION B – PRICES (QUOTE SCHEDULE)
Name of Firm: _______________________________________________________________________
Address: ___________________________________________________________________________
City: __________________________________ State: ___________ Zip Code: __________________
Unique Entity ID (12 Digits assigned by SAM.gov) __________________ CAGE Code: _______________
Name and Title of Firm’s Point of Contact: _________________________________________________
Phone Number: _________________________ Email Address: _________________________
This requirement is for one (1) Firm Fixed Price Construction contract for repair of the roof for garage and shop buildings in Red Bluff, CA.
Item
no. Item Description Quantity
Unit of Measure Unit Price Total
0001 Garage and Shop Roof Repairs 1 LS $ $
TOTAL - Base $
GRAND TOTAL $
(End of Section B)
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
1. Overview
This Statement of Work (SOW) outlines the requirements for repair of the roof for the garage/shop building at the US Fish & Wildlife Office located at 10950 Tyler Road, Red Bluff, CA 96080 Red Bluff, CA.
2. Scope of Work
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to repair the vents and roof of the garage/shop building.
New Roof Vents and Flashing Hip, Rake, and Ridge Replacement Roof Repair: Where Hip Meets Rake
3. Deliverables
New Roof Vents and Flashing o Remove (4) roof-top attic vents and install new fabricated ones out of 24-guage pre-finished metal o Install metal Zee flashings around new vents and all the way to the ridge o Flah all vents with pre-finished metal flashing all the way to the ridge on the new Zee flashings o Install (2) new rubber pipe boot flashings on (2) plumbing roof vents o Clean up and haul away all related debris o
Hip, Rake, and Ridge Replacement o Remove all hip and ridge flashing o Remove all rake flashing o Remove all screws at the bottom of the panels and install new, larger-diameter screws o Install metal Zee flashing on both sides of all the hips and ridges o Install all new 24-guage hip, ridge, and rake flashing (color to match as closely as possible) o Clean up and haul away all related debris
Roof Repair: Where Hip Meets Rake o Remove rake flashing on north end of roof o Remove 1 piece of hip flashing on northwest end of roof o Remove 3’ of roof-to-wall flashing where removed o Install new wider rake flashing so the new rake covers the panel rib 2” away from the edge o Clean up and haul away all related debris
4. Installation Timeline
• The installation process is expected to commence within 30 days of contracting documents being signed
5. Responsibilities
• Supplier Responsibilities:
o Procurement of all necessary equipment as specified.
o Installation and repair of all of the deliverables identified above.
• Client Responsibilities:
o Provide necessary access to the installation sites.
o Ensure availability of power sources and necessary infrastructure as per agreed specifications.
o Coordinate with supplier for any required or permissions.
6. Acceptance Criteria
• The systems will be deemed accepted upon successful testing and demonstration of all specified functionalities.
• Client satisfaction with the repair performance and compliance with outlined requirements.
7. Warranty and Support
• Provide warranty details for all installed and replaced roofing materials.
8. Payment
• Payment will be made upon completion of the work consistent with the terms of the contract and receipt of the invoice.
9. Contractor’s Use of Premises
• Contractor shall conduct their operations during regular business hours for the Station. The site will be accessible Monday through Fr 7:30 AM-5:00 PM. The contractor shall maintain a clean and safe worksite at all times.
• Recognized Holidays:
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day Juneteenth National Independence Day
• Confine materials/supplies within the worksite and space provided. Additional storage areas will be designated by the station representative if needed.
(End of Section C)
SECTION D – PACKAGING AND MARKING
D.1.0 PAYMENT OF POSTAGE FEES
All postage and fees related to submitting information forms, reports, etc., to the CO or the COR shall be paid by the contractor.
D.2.0 MARKING
All information submitted to the Contracting Officer or the Contracting Officer's Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.
(End of Section D)
SECTION E – INSPECTION AND ACCEPTANCE
The following clauses are incorporated by reference:
52.246-12 Inspection of Construction AUG 1996
(End of Section E)
SECTION F – PROJECT DELIVERY
F.1.0 PERIOD OF PERFORMANCE
F.2.0 PROGRESS PLAN
At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.
52.211-13 Time Extensions SEP 2000 52.242-14 Suspension of Work APR 1984
**The following clauses are provided in full text:
52.211-12 – LIQUIDATED DAMAGES – CONSTRUCTION (SEPT 2000) (a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $400 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (End of Clause)
(End of Section F)
SECTION G – CONTRACT ADMINISTRATION DATA
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP) (February 2021)
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP).
“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts.
The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice billed according to contract line items and rates.
2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.
3. If the partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this invoice period.
4. If final payment is billed, the last invoice shall state “FINAL”.
5. Contractor’s Release of Claims shall be submitted with the final invoice.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
(End of Section G) https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1.0 WORK HOURS
See Statement of Work
Contractor’s Use of Premises:
Contractor shall conduct their operations during regular business hours for the Station. The site will be accessible Monday through Fr 7:30 AM-5:00 PM. The contractor shall maintain a clean and safe worksite at all times.
No work will be performed on Saturday, Sunday, or Federal holidays unless authorized by the COR (See SOW for recognized holidays).
H.2.0 ENVIRONMENTAL INTERRUPTION OF WORK
H.2.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration. An allowance has been included in the contract time for environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger. The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions.
H.2.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, are discovered to be present in or adjacent to the project area.
H.3.0 DRAWINGS
H.3.1 Reduced Size Drawings. Drawings appearing in this package may be photographically reduced in size.
Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. The Contractor may request full-size drawings from the COR.
H.4.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
H.4.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data (including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.
H.4.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.
H.4.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in Section I of this contract.
H.4.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.
H.5.0 SUBSTITUTION – PROCESSION OF WORK
Any proposed key personnel, minimum qualifications for incoming or replacement key personnel, subcontractors, processes, procedures or materials included in the quotation are hereby incorporated into the contract. Performance shall be limited to the personnel, qualifications, firms, procedures, and materials that were specifically identified in the RFQ response. The Contractor shall obtain the Contracting Officer’s written consent before making any substitutions or changes. All substitutions or replacements shall comply with the terms and conditions of the contract.
H.6.0 ENVIRONMENTAL IMPACT
All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ); the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.
H.7.0 HAZARDOUS MATERIALS
Any material suspected of being hazardous that is unexpectedly encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.
Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR
1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.
H.8.0 GREEN PROCUREMENT REQUIREMENTS
In the performance of this construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, as applicable:
• U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program.
• . USDA Biobased product listings published at www.biopreferred.gov.
• Energy Star® product listings published at www.energystar.gov/products.
• FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories
Contractor shall comply with all reporting requirements of the following clauses/provisions when applicable (See Clause and Provision sections):
• 52.223-1 Biobased Product Certification
• 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts
• 52.223-4 Recovered Material Certification
• 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items
H.9.0 UNAUTHORIZED PERSONNEL
The contractor shall inform all personnel working under their jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
H.10.0 DAVIS-BACON WAGE RATES APPLICABLE TO TRUCK DRIVERS
29 CFR 5.2(j) limits coverage of construction contractor or subcontractor employees performing as truck drivers under the Davis-Bacon Act (FAR 52.222-6) to only their time spent directly upon the "site of the work" or when hauling between the site of the work and a facility which is dedicated to and located in the proximity of the actual construction location. Other transportation of materials or supplies to or from the site of work by employees of the construction contractor or subcontractor is not “construction” at the site of work and accordingly is not subject to the Davis-Bacon Act.
http://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories http://energy.gov/eere/femp/covered-product-categories
H.11.0 FIRE DANGER SEASON
If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.
(End of Section H) SECTION I – CONTRACT CLAUSES
Clause Title Date 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements JAN 2017 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards JUN 2020 52.204-13 System for Award Management Maintenance (DEVIATION MAR 2026) OCT 2018 52.204-14 Service Contract Reporting Requirments (DEVIATION MAR 2026) OCT 2016 52.204-19 Incorporation By Reference of Representations and Certifications DEC 2014 52.215-8 Order of Precedence-uniform Contract Format APR 2026 52.232-16 Progress Payments APR 2026 52.222-1 Notice to the Government of Labor Disputes Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-12 Contract Termination – Debarment MAY 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations MAY 2014 52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) AUG 2018 52.222-90 Addressing DEI Discrimination by Federal Contractors (DEVIATION MAY 2026) MAY 2026 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (DEVIATION
MAY 2026)
May 2024
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2024 52.223-23 Sustainable Products (DEVIATION MAY 2026) May 2024 52.225-9 Buy American—Construction Materials Apr 2026 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving MAY 2024 52.227-1 Authorization and Consent JUN 2020 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement JUN 2020 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-13 Alternative Payment Protections JUL 2000 52.228-14 Irrevocable Letter of Credit NOV 2014
52.232-5 Payments Under Fixed-Price Construction Contracts MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017
The following clauses are provided in full text:
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (JAN 2025) (DEVIATION MAY 2026)
As prescribed in 9.409 , insert the clause:
(a) Definition. As used in this clause—
Commercially available off-the-shelf (COTS) item
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” in Federal
Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
(b) The Government suspends or debars Contractors to protect the Government's interests. Other than a subcontract for a commercially available off-the-shelf item, the Contractor shall not enter into any subcontract, in excess of the threshold specified in FAR 9.405-2(b) on the date of subcontract award, with a Contractor that is debarred, suspended, or proposed for debarment by any executive agency unless a compelling reason exists to do so.
52.232-33 Payment by Electronic Funds Transfer—System for Award Management OCT 2018 52.232-39 Clause for unenforceability of unauthorized obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors MAR 2023 52.233-1 Disputes APR 2026 52.233-1 Dispuits-Alternate 1 APR 2026 52.233-3 Protest After Award APR 2026 52.233-4 Applicable Law for Breach of Contract Claim APR 2026 52.243-5 Changes and Changed Conditions APR 1984 52.244-6 Subcontracts for Commercial Products and Commercial Services OCT 2025 52.246-21 Warranty of Construction MAR 1994 52.249-10 Default (Fixed-Price Construction) APR 1984 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section40102(4)&num=0&edition=prelim
(c) The Contractor shall require each proposed subcontractor whose subcontract will exceed the threshold specified in FAR 9.405-2(b) on the date of subcontract award, other than a subcontractor providing a commercially available off-the-shelf item, to disclose to the Contractor, in writing, whether as of the time of award of the subcontract, the subcontractor, or its principals, is or is not debarred, suspended, proposed for debarment, or voluntarily excluded by the Federal Government.
(d) A corporate officer or a designee of the Contractor shall notify the Contracting Officer, in writing, before entering into a subcontract with a party (other than a subcontractor providing a commercially available off-the-shelf item) that is debarred, suspended, proposed for debarment, or voluntarily excluded (see FAR 9.404 for information on the System for Award Management (SAM) Exclusions). The notice must include the following:
(1) The name of the subcontractor.
(2) The Contractor’s knowledge of the reasons for the subcontractor being listed with an exclusion in SAM.
(3) The compelling reason(s) for doing business with the subcontractor notwithstanding its being listed with an exclusion in SAM.
(4) The systems and procedures the Contractor has established to ensure that it is fully protecting the
Government's interests when dealing with such subcontractor in view of the specific basis for the party's debarment, suspension, proposed debarment, or voluntary exclusion.
(e) Subcontracts. Unless this is a contract for the acquisition of commercial products or commercial services, the
Contractor shall include the requirements of this clause, including this paragraph (e) (appropriately modified for the identification of the parties), in each subcontract that—
(1) Exceeds the threshold specified in FAR 9.405-2(b) on the date of subcontract award; and
(2) Is not a subcontract for commercially available off-the-shelf items.
(End of clause)
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations (NOV 2015) (DEVIATION MAY 2026)
As prescribed in 9.108-6(b), insert the clause:
(a) Definitions. As used in this clause-
Inverted domestic corporation means a foreign incorporated entity that meets the definition of an inverted domestic corporation under 6 U.S.C. 395(b), applied in accordance with the rules and definitions of 6 U.S.C.
395(c).
Subsidiary means an entity in which more than 50 percent of the entity is owned—
(1) Directly by a parent corporation; or
(2) Through another subsidiary of a parent corporation.
(b) If the contractor reorganizes as an inverted domestic corporation or becomes a subsidiary of an inverted domestic corporation at any time during the period of performance of this contract, applicable law may prohibit the Government from paying for Contractor activities performed after the date when it becomes an inverted domestic corporation or subsidiary. The Government may seek any available remedies in the event the Contractor fails to perform in accordance with the terms and conditions of the contract as a result of Government action under this clause.
(c) Exceptions to this prohibition are located at 9.108-3.
(d) In the event the Contractor becomes either an inverted domestic corporation, or a subsidiary of an inverted domestic corporation during contract performance, the Contractor shall give written notice to the Contracting
Officer within five business days from the date of the inversion event.
(End of clause)
52.213-4 Terms and Conditions—Simplified Acquisitions (Noncommercial) (OCT 2025) (DEVIATION MAR 2026)
As prescribed in 13.204(b), insert the clause:
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights—
(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers.
When an excusable delay occurs, the Contractor shall—
(1) Notify the Contracting Officer in writing as soon as possible;
(2) Remedy the delay as quickly as possible; and
(3) Notify the Contracting Officer when the occurrence is over.
(c) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(d) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. The
Government will send a cure notice to the Contractor, unless the reason for the termination is late delivery. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(e) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(End of clause)
52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) (DEVIATION JAN 2026)
As prescribed in 19.104-3(a), insert the clause:
(a) Definition. Small business concern, as used in this clause—
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.
(2) Affiliates, as used in paragraph (a)(1) of this clause, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) Applicability. This clause applies only to-
(1) Contracts that have been set aside for small business concerns; and
(2) Orders set aside for small business concerns under multiple-award contracts as described in 8.4 and 16.5.
(c) General.
(1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.
(2) Any award resulting from this solicitation will be made to a small business concern.
(End of clause)
Alternate I (MAR 2020) . As prescribed in 19.104-3(a), substitute the following paragraph (c) for paragraph (c) of the basic clause:
(c) General.(1) Offers are solicited only from small business concerns and Federal Prison Industries, Inc. (FPI).
Offers received from concerns that are not small business concerns or FPI shall be considered nonresponsive and will be rejected.
(2) Any award resulting from this solicitation will be made to either a small business concern or FPI.
(End)
52.219-33 Nonmanufacturer Rule (SEP 2021) (DEVIATION JAN 2026)
As prescribed in 19.104-3(e)(1), insert the clause:
(a) Definitions. As used in this clause—
Manufacturer means the concern that transforms raw materials, miscellaneous parts, or components into the end item. Concerns that only minimally alter the item being procured do not qualify as manufacturers of the end item.
Concerns that add substances, parts, or components to an existing end item to modify its performance will not be considered the end item manufacturer, where those identical modifications can be performed by and are available from the manufacturer of the existing end item.
Nonmanufacturer means a concern, including a supplier, that provides an end item it did not manufacture, process, or produce.
(b) Applicability.
(1) This clause does not apply to contracts awarded pursuant to the unrestricted portion of a partial set-aside or to a contractor that is the manufacturer of the product or end item.
(2) This clause applies to—
(i) Contracts that have been awarded pursuant to a set-aside for any of the small business concerns identified in
19.000(a)(3);
(ii) Contracts that have been awarded on a sole-source basis in accordance with sections 19.105, 19.106, 19.107, and 19.108;
(iii) Orders expected to exceed the simplified acquisition threshold and that are set aside for small business under multiple-award contracts, as described in 8.4 and 16.5;
(iv) Orders, regardless of dollar value, that are set aside in accordance with sections 19.105, 19.106, 19.107, and
19.108 under multiple-award contracts as described in 8.4 and 16.5; and
(v) Contracts using the HUBZone price evaluation preference to award to a HUBZone concern unless the
Contractor waived the evaluation preference.
(c) Requirements.
(1) The Contractor shall—
(i) Provide an end item that a small business has manufactured, processed, or produced in the United States or its outlying areas; for kit assemblers who are nonmanufacturers, see paragraph (c)(2) of this clause instead;
(ii) Be primarily engaged in the retail or wholesale trade and normally sell the type of item being supplied; and
(iii) Take ownership or possession of the item(s) with its personnel, equipment, or facilities in a manner consistent with industry practice; for example, providing storage, transportation, or delivery.
(2) When the end item being acquired is a kit of supplies, at least 50 percent of the total cost of the components of the kit shall be manufactured, processed, or produced in the United States or its outlying areas by small business concerns.
(End of clause)
52.222-6 Construction Wage Rate Requirements (AUG 2018) (DEVIATION MAY 2026)
As prescribed in 22.402-4(a)(1), insert the clause:
(a) Definition.—"Site of the work"—
(1) Means—
(i) The primary site of the work. The physical place or places where the construction called for in the contract will remain when work on it is completed; and
(ii) The secondary site of the work, if any. Any other site where a significant portion of the building or work is constructed, provided that such site is-
(A) Located in the United States; and
(B) Established specifically for the performance of the contract or project;
(2) Except as provided in paragraph (3) of this definition, includes any fabrication plants, mobile factories, batch plants, borrow pits, job headquarters, tool yards, etc., provided-
(i) They are dedicated exclusively, or nearly so, to performance of the contract or project; and
(ii) They are adjacent or virtually adjacent to the "primary site of the work" as defined in paragraph (a)(1)(i), or the
"secondary site of the work" as defined in paragraph (a)(1)(ii) of this definition;
(3) Does not include permanent home offices, branch plant establishments, fabrication plants, or tool yards of a
Contractor or subcontractor whose locations and continuance in operation are determined wholly without regard to a particular Federal contract or project. In addition, fabrication plants, batch plants, borrow pits, job headquarters, yards, etc., of a commercial or material supplier which are established by a supplier of materials for the project before opening of bids and not on the Project site, are not included in the "site of the work." Such permanent, previously established facilities are not a part of the "site of the work" even if the operations for a period of time may be dedicated exclusively or nearly so, to the performance of a contract.
(b)
(1) All laborers and mechanics employed or working upon the site of the work will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account (except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act (29 CFR Part
3)), the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made a part hereof, or as may be incorporated for a secondary site of the work, regardless of any contractual relationship which may be alleged to exist between the Contractor and such laborers and mechanics. Any wage determination incorporated for a secondary site of the work must be effective from the first day on which work under the contract was performed at that site and must be incorporated without any adjustment in contract price or estimated cost. Laborers employed by the construction Contractor or construction subcontractor that are transporting portions of the building or work between the secondary site of the work and the primary site of the work must be paid in accordance with the wage determination applicable to the primary site of the work.
(2) Contributions made or costs reasonably anticipated for bona fide fringe benefits under section 1(b)(2) of the
Construction Wage Rate Requirements statute on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of paragraph (e) of this clause; also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs which cover the particular weekly period, are deemed to be constructively made or incurred during such period.
(3) Such laborers and mechanics must be paid not less than the appropriate wage rate and fringe benefits in the wage determination for the classification of work actually performed, without regard to skill, except as provided in the clause entitled Apprentices and Trainees. Laborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein; provided that the employer’s payroll records accurately set forth the time spent in each classification in which work is performed.
(4) The wage determination (including any additional classifications and wage rates conformed under paragraph
(c) of this clause) and the Construction Wage Rate Requirements (Davis-Bacon Act) poster (WH-1321) must be posted at all times by the Contractor and its subcontractors at the primary site of the work and the secondary site of the work, if any, in a prominent and accessible place where it can be easily seen by the workers.
(c)
(1) The Contractor must complete and submit to the Contracting Officer the Standard Form (SF) 1444, Request for
Authorization of Additional Classification and Rate, if any class of laborers or mechanics that is not listed in the wage determination applicable to the contract is to be employed under the contract. Upon receipt of a complete
SF 1444, the Contracting Officer will submit a report to the Administrator, Wage and Hour Division, for approving, modifying, disapproving, or rendering a final determination, of the additional classification and wage rate including any amount designated for fringe benefits.
(2) The wage rate (including fringe benefits, where appropriate) determined pursuant to subparagraph (c) of this clause must be paid to all workers performing work in the classification under this contract from the first day on which work is performed in the classification.
(d) Whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly rate, the Contractor must either pay the benefit as stated in the wage determination or must pay another bona fide fringe benefit or an hourly cash equivalent thereof.
(e) If the Contractor does not make payments to a trustee or other third person, the Contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program; provided, that the Secretary of Labor has found, upon the written request of the Contractor, that the applicable standards of the Construction Wage Rate Requirements statute have been met. The Secretary of Labor may require the Contractor to set aside in a separate account assets for the meeting of obligations under the plan or program.
(End of clause)
52.222-11 Subcontracts (Labor Standards) (MAY 2014) (DEVIATION MAY 2026)
As prescribed in 22.402-4(a)(6), insert the clause:
(a) Definition. "Construction, alteration or repair," as used in this clause, means all types of work done by laborers and mechanics employed by the construction Contractor or construction subcontractor on a particular building or work at the site thereof, including without limitation-
(1) Altering, remodeling, installation (if appropriate) on the site of the work of items fabricated off-site;
(2) Painting and decorating;
(3) Manufacturing or furnishing of materials, articles, supplies, or equipment on the site of the building or work;
(4) Transportation of materials and supplies between the site of the work within the meaning of paragraphs
(a)(1)(i) and (ii) of the "site of the work" as defined in the FAR clause at 52.222-6, Construction Wage Rate
Requirements of this contract, and a facility which is dedicated to the construction of the building or work and is deemed part of the site of the work within the meaning of paragraph (2) of the "site of the work" definition; and
(5) Transportation of portions of the building or work between a secondary site where a significant portion of the building or work is constructed, which is part of the "site of the work" definition in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, and the physical place or places where the building or work will remain (paragraph (a)(1)(i) of the FAR clause at 52.222-6, in the "site of the work" definition).
(b) The Contractor must insert in any subcontracts for construction, alterations and repairs within the United
States the clauses entitled-
(1) Construction Wage Rate Requirements;
(2) Contract Work Hours and Safety Standards-Overtime Compensation (if the clause is included in this contract);
(3) Apprentices and Trainees;
(4) Payrolls and Basic Records;
(5) Compliance with Copeland Act Requirements;
(6) Withholding of Funds;
(7) Subcontracts (Labor Standards);
(8) Contract Termination-Debarment;
(9) Disputes Concerning Labor Standards;
(10) Compliance with Construction Wage Rate Requirements and Related Regulations; and
(11) Certification of Eligibility.
(c) The prime Contractor must be responsible for compliance by any subcontractor or lower tier subcontractor performing construction within the United States with all the contract clauses cited in paragraph (b).
(d)
(1) Within 14 days after award of the contract, the Contractor must deliver to the Contracting Officer a completed Standard Form (SF) 1413, Statement and Acknowledgment, for each subcontract for construction https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_222_6 https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_222_6 https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_222_6 https://www.gsa.gov/forms-library/statement-and-acknowledgment within the United States, including the subcontractor’s signed and dated acknowledgment that the clauses…