Sol_12363N26Q4197.pdf

PDF 14 MB Posted

Attached to
Solicitation is Restricted to the NC MATOC Road Maintenance and Construction Holders
Solicitation number
12363N26Q4197
Issued by

About this file

This is a Solicitation, Offer, and Award document (Standard Form 1442) issued by the USDA Forest Service for a road restoration project on National Forest System Road (NFSR) 192 in the Pisgah National Forest, Grandfather Ranger District, Avery County, North Carolina. The solicitation is restricted to North Carolina MATOC (Multiple Award Task Order Contract) Road Maintenance and Construction holders. The project involves hurricane recovery work including road reconstruction, rehabilitation, landslide repairs, culvert replacements, and drainage infrastructure repairs. The estimated contract value is between $500,000 and $1,000,000, with a period of performance from August 18, 2026, to January 26, 2027 (150 days). A mandatory pre-bid site visit is scheduled for July 28, 2026, at 11:00 AM at the top of the road (mile post 6.545). All quotes must be submitted by August 13, 2026, at 10:00 AM Mountain Time to Chad A. Bullock (Contracting Officer) and James Kaminski (APSO) via email following a specific naming convention for attachments.

The project includes detailed specifications and requirements for linear grading (3.030 miles), gate installation and removal, concrete footing repairs, drainage feature installation, and culvert removals and installations with riprap and erosion control measures. Contractors must provide performance and payment bonds for projects over $35,000 and furnish submittals including construction schedule, safety and fire plan, erosion control plan, traffic control plan, dewatering plans, and quality control plan. Work is restricted to 6:00 AM to 6:00 PM Monday through Friday, except federal holidays. The project uses Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14) and incorporates multiple Forest Service Supplemental Specifications (FSSS). The contractor is responsible for all mobilization, labor, materials, equipment, and supervision, with payment processed monthly upon government acceptance of pre-bill submittals. Equipment must arrive washed and free of soil and debris, with government approval required before unloading on site. All equipment must also be certified weed-free and inspected at least ten business days before arrival.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1173757

USDA-FS STEWARDSHIP CONTRACTING BR

1400 INDEPENDENCE AVE SW

MS-1138

WASHINGTON DC 20250-1138

363N

Bid Bond is acceptable for proposals valued at $150,000 and greater.

JAMES KAMINSKI 573-453-8424

07/14/2026

12363N26Q4197 INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Bid Bond is required for proposals over $150,000

Payment and Performance bonds are required for construction projects over $35,000.

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price; include bond payments under 151.01 Mobilization.

NFSR 192 Road Restoration

Pisgah National Forest Grandfather Ranger District

Avery County, NC

Magnitude is Between $500,000 and $1,000,000.

Estimated Period of Performance - August 18, 2026, to January 26, 2027

A site visit will be July 28,2026 11:00 AM

Roseboro Gragg NFSR 192 Reconstruction:

Meet at top of road (EMP 6.545): 35.078264, -81.783528

Continued ...

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

0 0 calendar days and complete it within ________________ ________________ calendar days after receiving

08/13/2026

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

12363N26Q4197 NFSR 192 Road Restoration Page 1 of 99

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

USDA-FS STEWARDSHIP CONTRACTING BR

1400 INDEPENDENCE AVE SW

MS-1138

WASHINGTON DC 20250-1138

363N

CHAD A. BULLOCK

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

12363N26Q4197 NFSR 192 Road Restoration Page 2 of 99

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED

12363N26Q4197

SEE ATTACHED DIRECTIONS WITH MAP

Solicitation is Restricted to the NC MATOC Road

Maintenance and Construction Holders.

ALL QUOTES SHALL BE EMAILED TO:

CHAD.BULLOCK@USDA.GOV;

JAMES.KAMINSKI@USDa.GOV,D__QUOT.k11q89t56age4hh0@u

.box.com on or BEFORE

August 13, 2026, 10:00 AM MOUNTIAN TIME.

Since all documents will be submitted to me electronically. Follow this naming convention for your attachments and keep the subject line the same or just reply all to this email.

26Q4197-NCMATOC-VendorName-Quote and

26Q4197-NCMATOC-VendorName-Technical.

Be sure to fill out all required documentation.

Required to be filled in below:

Company Name:___________________________________

POC Name:_______________________________________

Phone number:___________________________________

Email:__________________________________________

BPA/IDIQ/MATOC Contract #_______________________

UEI SAM #______________________________________

Contractual POC: Chad A.T. Bullock Contracting

Officer, chad.bullock@usda.gov 385-368-5300

Contractual Technical: James Kaminski APSO, 573-453-8424

Delivery: 01/26/2027

Delivery Location Code: 4550

USDA FS

NATIONAL FOREST IN NORTH CAROLINA

160A ZILLICOA ST

ASHEVILLE NC 28801-9999 US

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

12363N26Q4197 NFSR 192 Road Restoration Page 3 of 99

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED

12363N26Q4197

Mark For:

USDA-FS STEWARDSHIP CONTRACTING BR

1400 INDEPENDENCE AVE SW

MS-1138

WASHINGTON DC 20250-1138

Period of Performance: 08/18/2026 to 01/26/2027

0001 Roads repairs for Hurricane Recovery including but not limited to road reconstruction, rehabilitation, landslide repairs , culvert replacements and drainage infrastructure replacements and repairs.

Product/Service Code: Y1LB

Product/Service Description: CONSTRUCTION OF

HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice

Processing Platform (IPP), https://www.ipp.gov.

If the contractor lacks an IPP account, USDA will automatically initiate the enrollment process with Treasury using the contractor's SAM.gov

Accounts Receivable POC as the IPP account holder. Once the enrollment process is complete, the IPP account holder will receive notification and can being invoicing. More information about

IPP can be found at: https://www.ipp.gov

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

12363N26Q4197 NFSR 192 Road Restoration Page 4 of 99

ITEM NO. DESCRIPTION PAY UNIT AMOUNT

UNIT

COST

TOTAL COST

PER ITEM

15101 Mobilization LUMP SUM ALL

15201 Construction survey and staking, method 1, tolerance B

LUMP SUM ALL

15713 Soil erosion and pollution control LUMP SUM ALL

20301A Removal of gate, disposal method A LUMP SUM ALL

20301B Removal of culvert, disposal method A, compaction method 6

LUMP SUM ALL

20411 Unclassified borrow excavation - Pit Run

(Commercial Source)

CUBIC YARD* 4055

20420 Drainage Excavation, type outlet ditch, tolerance class B, compaction method 2

FOOT 60

20421A Drainage Excavation, type 1 rolling dip, tolerance class B, compaction method 2

EACH 9

20421B Drainage Excavation, type hard dip, tolerance class B, compaction method 2

EACH 1

20426 Drainage Excavation, type deep culvert excavation beyond 5' depth

LUMP SUM ALL

21201 Linear Grading, compaction method 2 MILE 3.030

25101A Placed riprap, class 2, (NCDOT Class 1), acceptance method A

CUBIC YARD* 118

25101B Placed riprap, class 3, (NCDOT Class 2), acceptance method A

CUBIC YARD* 40

25101C Placed riprap, class 4, (NCDOT Class 3), acceptance method A

CUBIC YARD* 100

30103 Aggregate base, grading B, (NCDOT 57), compaction method B

CUBIC YARD* 400

30115 Aggregate surface course, grading F, (NCDOT

ABC), compaction method B

CUBIC YARD* 2640

30315 Roadway reconditioning, compaction method 2 MILE 3.515

50203 Grout, non-shrink ASTM C1107, minimum compression strength of 5000psi/3days

CUBIC YARD* 10

55207 Repair Concrete, non shrink grout patching compound

FOOT 3

60201A 24 inch pipe culvert, aluminized corrugated metal, gage 14, compaction method 6

FOOT 718

60201B 36 inch pipe culvert, aluminized corrugated metal, gage 14, compaction method 6

FOOT 554

60708 Cleaning culverts in place EACH 1

61902 Gate, 14' steel (brown paint) EACH 2

62501 Turf establishment, seeding, mulching, fertilization

SQUARE YARD 17750

62901 Rolled erosion control product, type 3.B SQUARE YARD 83

63501 Temporary traffic control LUMP SUM ALL

TOTAL

SCHEDULE OF ITEMS

* DENOTES CONTRACT QUANTITY

12363N26Q4197 NFSR 192 Road Restoration Page 5 of 99

12363N26Q4197 NFSR 192 Road Restoration Page 6 of 99

MattieAcuna-Rourk Text Box

BMP 0.00

35.031806, -81.803278

MattieAcuna-Rourk Text Box

EMP 6.545

35.078264, -81.783528

MattieAcuna-Rourk Text Box Road Blown Out-Must Accessed from Either Side

DRAWN

DESIGNER

STAMPS, LOGOS, AND SEALS

PROJECT NAME

DRAWING TITLE

CHECKED

ARCHIVE NO.DATE

PROJECT NO.

DRAWING SHEET NO.

DATENO.

REVISION / ISSUE

OFSHEET

United States Department of Agriculture Forest Service

5/1 2/2

6 0 9:

M

AT

TI

EA

CU

NA

-R

OU

RK

C :\U

SE

RS

\M

AT

TI

ER

OU

RK

\B

OX

\02 . R

N

FS

NC

\P

RO

J\G

RF

\A

CT

IV

E\

-R

OA

DS

EN

G\

\N

FS

R_

7_

MA

PL

E

SA

LL

Y

RE

PA

IR

S\

2_

DE

SI

GN

\2_

DW

GS

\D

ET

AI

LS

_R

EC

OV

ER

.D

W G;

(R08)

SOUTHERN REGION

NFSR 187

REPAIRS

PISGAH NATIONAL

FOREST

GRANDFATHER RANGER DISTRICT

VICINITY MAP

05/2026

M. ACUNA-ROURK

M. ACUNA-ROURK V-01

2 42

12363N26Q4197 NFSR 192 Road Restoration Page 7 of 99

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

AutoCAD SHX Text E

NATIONAL FORESTS IN NORTH CAROLINA

PISGAH NATIONAL FOREST

GRANDFATHER RANGER DISTRICT

AVERY COUNTY

STATEMENT OF WORK

NFSR 192 ROAD RESTORATION

12363N26Q4197 NFSR 192 Road Restoration Page 8 of 99

Contents Project General Information

1.0 Scope of Work

2.0 Background

3.0 Project Location

4.0 Pre-Bid Site Visit

5.0 Request for Quotations (RFQ) Submittal Requirements

Contractor Requirements

6.0 Technical Requirements / Tasks and Information

6.1 Technical Specifications

6.2 Project Plans

6.3 Operational Hours

6.4 Period of Performance

6.5 Submittals

6.6 Construction Schedule

6.7 Contractor’s Key Personnel

6.8 Government Furnished

6.9 Construction Staging

6.10 Pre-Construction Meeting

6.11 Payment Provisions

6.12 Quality Control

6.13 Personal Protective Equipment (PPE)

6.14 Basic First Aid

6.15 Safety

6.16 Landscape Preservation

6.17 Loss, Damage, or Destruction

6.18 Control of Noxious Weeds

6.19 Temporary Facilities

6.20 Construction Tolerances

6.21 Final Cleanup

Attachments

12363N26Q4197 NFSR 192 Road Restoration Page 9 of 99

Project

NFSR 192 ROAD RESTORATION

General Information

1.0 Scope of Work

This project is intended to restore NFSR 192 – Roseboro Gragg Road which sustained damage during Tropical Storm Fred in 2021 and during Hurricane Helene in September 2024. Restoration work includes linear grading of lower road section, roadway reconditioning of upper road section, aggregate placement, culvert replacements/culvert installations, riprap installation, drainage excavation of hard dips/rolling dips/outlet ditches, removal and installation of gates, and repair concrete and grouting of existing AOP foundation structures.

The contractor shall be responsible for furnishing all mobilization, labor, materials, tools, supervision, personnel, equipment and other incidentals necessary to perform all work and meet the requirements outlined in the supporting contract documents.

2.0 Background

Roseboro Gragg Road (NFSR 192) is a partially open/partially closed system road on the National Forest in North Carolina (NFsNC) on the Grandfather Ranger District of the Pisgah National Forest. It is approximately 6.545 miles in total length with the upper section being a Maintenance Level 3 with aggregate surfacing and the lower section being Maintenance Level 2. The transition from Level 2 to Level 3 occurs on top of Yancey Ridge at the crossroads of NFSR 4062 and NFSR 4053.

3.0 Project Location

The project is located on NFSR 192 – Roseboro Gragg Road in the Grandfather Ranger District of the Pisgah National Forest. FROM THE INTERSECTION OF HIGHWAY 105 (N. LINVILLE AVE.) AND US-221 IN LINVILLE, NC, HEAD SOUTH ON NC-1545 FOR 0.3 MILES AND THEN TURN LEFT ONTO ROSEBORO ROAD FOR 6.8 MILES. THIS TAKES YOU TO THE BEGINNING OF THE PROJECT. THERE ARE WEIGHT RESTRICTED BRIDGES NORTH AND SOUTH OF THE BEGINNING (SOUTH

END) OF NFSR 192 (OLD HOUSE GAP ROAD).

Beginning Latitude/Longitude (MP 0.00): 36.031806 °, - 81.803278 ° Ending Latitude/Longitude (MP 6.545): 36.078264 °, - 81.783528 °

Forest maps are available from the Grandfather Ranger District Office located at 109 Lawing Dr., Nebo, NC 28761 or online at https://www.fs.usda.gov/nfsnc. Directions and vicinity map are provided in the project plans (Attachment 4).

4.0 Pre-Bid Site Visit

A non-mandatory pre-bid site visit will be scheduled at the time of solicitation to facilitate the Offeror’s understanding of the work. The Contractor is urged and expected to inspect the site where work is to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award. Contact the Contracting Officer (CO) to indicate if you will be attending the site visit at least 24 hours before the scheduled visit. If no offerors intend to attend the site visit, it will be canceled. Formal questions about the project will be accepted up to 7 business days after the scheduled visit and must be directed to the CO. Responses will be provided to all potential offerors within 3 business days after.

5.0 Request for Quotations (RFQ) Submittal Requirements

Contractor’s submittals will be evaluated using the Highest Technically Rated with Fair and Reasonable Pricing method.

Contractors shall complete the Schedule of Items (SOI).

Contractor Requirements

6.0 Technical Requirements / Tasks and Information

This project shall consist of the following tasks to be addressed over the course of the contract: (This list is not all-inclusive to the work outlined in the plans, worklist, and specifications. It is the contractor’s responsibility to read and

12363N26Q4197 NFSR 192 Road Restoration Page 10 of 99 https://www.fs.usda.gov/nfsnc interpret the plans, worklist, and specifications and perform all work required to complete the project. Some of these tasks may be performed simultaneously.)

Linear Grading Work (3.030 Miles)

Gate Installation (2) and Removal

Concrete Footing Repair of Existing AOP and Grouting to repair AOP foundation scour

Installation of Drainage Features: Hard Dips, Rolling Dips, and Outlet Ditches.

Culvert Removals and Installations:

• Culvert diameters, lengths, skew, and inlet/outlet protection is outlined in the worklist and plans.

• Dewatering will only be required at culvert installation sites with live water flow. Contractor is required to submit a dewatering plan. Water flows at culverts vary and may require alternate dewatering plans. Dewatering is incidental to all 60201 and 60202 items-no additional payment will be made.

• Any necessary excavation activities associated with culvert installation as well as hauling of culverts to each site are incidental to all 60201 and 60202 items, and no additional payment will be made.

• Place and compact material over new culverts in 6-inch layers. Culverts must have a minimum of 1ft of cover.

• Culverts with a length of >40ft will be one piece. Culverts with lengths >40 will require band with neoprene gasket.

• Riprap for inlet and outlet protection is to be machine-placed and installed with the type as specified in the plans, culvert schedule, and worklist.

Roadway Reconditioning and Aggregate Placement:

• Roadway Reconditioning includes roadbed, road shoulder, turnouts, and ditch reconditioning. It also includes cleaning of inlet and outlet and providing a 25ft transition in grade in the ditch line leading up to the inlet.

o Material removed from culverts is NOT to be placed on culvert head or on cut slope, but to be placed or cast off the fill slope to depth of not more than 4-inches.

• Roadway Reconditioning is not to be performed until all culverts have been installed and approved by the COR.

Any reconditioning performed prior to COR approval of all culvert installations will need to be reperformed.

• Completion of all roadway reconditioning sub-items listed above is required for COR approval and payment. COR approval of roadbed and ditch reconditioning is required prior to aggregate placement.

• If there is a need for stockpiling of aggregate, it will be in a location approved by the COR and placement of aggregate will be performed in a timely manner, so stockpile is not left for extended periods of time.

• Aggregate is to be placed as soon as possible after approval of reconditioning to limit any changes to the road.

• Compact aggregate as specified in the plans, FP-14, and FSSS. Compaction of aggregate is to be completed as aggregate is applied and spread or within one week (7 days) of application.

• Contractor will provide an organized compilation of aggregate and riprap tickets with tonnage amounts with each invoice.

Turf Establishment and Erosion Control:

• Any silt fence installed for erosion control is to be removed before the end of the project.

• Seeding and installation of rolled erosion control is to be completed within 15 days of soil excavation/disturbance.

6.1 Technical Specifications

This project makes use of Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP- 14). FP-14 is included by reference only and can be found on the internet at the following website:

https://highways.dot.gov/federal-lands/specs/fp-24.

12363N26Q4197 NFSR 192 Road Restoration Page 11 of 99 https://highways.dot.gov/federal-lands/specs/fp-24

In addition to FP-14 specifications, the U.S. Forest Service has Supplemental Specifications (FSSS) that include additions and revisions to FP-14. The following FSSS are a part of this solicitation and any resulting contract and are included in Attachments:

FSSS NO. DESCRIPTION

PREFACE

101 TERMS, FORMAT, AND DEFINITIONS

102 BID, AWARD, AND EXECUTION OF CONTRACT

103 SCOPE OF WORK

104 CONTROL OF WORK

105 CONTROL OF MATERIAL

106 ACCEPTANCE OF WORK

107 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

108 PROSECUTION AND PROGRESS

109 MEASUREMENT AND PAYMENT

152 CONSTRUCTION SURVEY AND STAKING

155 SCHEDULES FOR CONSTRUCTION CONTRACTS

157 SOIL EROSION AND SEDIMENT CONTROL

203 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

204 EXCAVATION AND EMBANKMENT

209 STRUCTURE EXCAVATION AND BACKFILL

301 UNTREATED AGGREGATE COURSES

303 ROAD RECONDITIONING

625 TURF ESTABLISHMENT

703 AGGREGATE

704 SOIL

705 ROCK

6.2 Project Plans

• NFSR 192 ROAD RESTORATION

The following plans are associated with this project (Please refer to Attachments):

SHEET NO. DESCRIPTION

1 TITLE SHEET

2 PROJECT MAP

3 SCHEDULE OF ITEMS/CONSTRUCTION NOTES

4 GENERAL NOTES

5 TEMPORARY TRAFFIC SIGNS

6 NFSR 192 WORKLIST

7 NFSR 192 WORKLIST

8 NFSR 192 WORKLIST

9 NFSR 192 WORKLIST

10 TYPICAL OUTSLOPE ROADWAY SECTIONS

11 TYPICAL INSLOPE ROADWAY SECTIONS

12 TYPICAL CROWNED ROADWAY SECTIONS

13 LINEAR GRADING SECTION DETAILS

14 RECONDITIONING SECTION DETAILS

15 TYPICAL CLEARING LIMITS & SEEDING NOTES

16 DITCHING AND RIPRAP DETAILS

17 HARD DIP DETAILS

18 ROLLING DIP DETAILS

19 SOIL EROSION DETAILS

20 14’ STEEL GATE DETAILS

12363N26Q4197 NFSR 192 Road Restoration Page 12 of 99

21 CULVERT INSTALLATION DETAILS

22 CULVERT DETAILS

23 CULVERT SCHEDULE AND NOTES

24 CULVERT BAND DETAILS

25 CULVERT BAND DETAILS

26 STAKING DETAILS

6.3 Operational Hours

The contractor is responsible for performing work between the hours of 6 a.m. to 6 p.m. Eastern Daylight Time, Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Work outside of these hours or circumstances must be approved in writing by the CO in advance. The contractor shall always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this Statement of Work when the Government facility is not closed for the above reasons.

• Federal Holidays

1. New Year’s Day – January 1st

2. Martin Luther King Junior’s Birthday – Third Monday in January

3. President’s Day – Third Monday in February

4. Memorial Day – Last Monday in May

5. Juneteenth – June 19th

6. Independence Day – July 4th

7. Labor Day – First Monday in September

8. Columbus Day – Second Monday in October

9. Veteran’s Day – November 11th

10. Thanksgiving Day – Fourth Thursday in November

11. Christmas Day – December 25th

6.4 Period of Performance

The project period of performance is 150 days from the date of issuance of the Notice to Proceed by the CO. By submitting a response to this Request for Quotations (RFQ), the offeror is affirming their capability to accomplish the work stated within this Statement of Work and associated attachments within this stated period. If the Offeror believes the work included in this Statement of Work cannot be accomplished within this period of performance, they should submit a statement explaining to the CO their reasons and justifications for a different period of performance and identify what that performance period would be as it relates to their proposal.

6.5 Submittals

The Contractor is responsible for and shall submit, at a minimum, all submittal items listed below as well as within the plans, FP-14 Specifications, and FSSS.

• Construction Schedule

• Safety and Fire Plan

• Erosion Control Plan

• Temporary Traffic Control Plan

• Dewatering Plan(s) if necessary

• Hazardous Spill Plan

• Quality Control Plan

• Utility Locate Confirmation

• Materials Submittals o Aggregate base and surface course o Riprap (Class 2,3,4) o Grout and Repair Concrete o Turf Establishment-Seed Mix

12363N26Q4197 NFSR 192 Road Restoration Page 13 of 99 o Wattles, Silt Fence, and any other erosion control expected o Corrugated Metal Pipe, CMP Bands & Gaskets o Gate: Paint, Pipe details, and concrete.

6.6 Construction Schedule

A detailed construction schedule shall be prepared by the contractor and furnished to the Contracting Officer’s Representative (COR) within 10 business days after the notice to proceed is issued, which incorporates the tasks and phases of the project. The schedule shall be by individual tasks, show the critical path, early start dates, late start dates and the task duration.

6.7 Contractor’s Key Personnel

The awarded contractor shall identify their key personnel assigned to the project and provide written delegated authority citing their role(s), responsibilities, and authorities. Roles such as Project Manager, Superintendent, Inspector, Quality Control Personnel, Site Safety Manager, and subcontractors/skilled personnel necessary to perform contract requirements and expectations, should be clarified to the CO. All project work shall be directly supervised by the prime contractor at all times, and a designated representative shall be present for all work operations.

6.8 Government Furnished

The Government will provide review of all submittals in a timely manner. The CO, Contracting Officer’s Representative (COR) and Government Technical Monitor (GTM) will be the Contractor’s points of contact for anything related to this project.

6.9 Construction Staging

Upon concurrence from the Contracting Officer or Contracting Officer’s Representative, certain areas on the Forest may be used on a case-by-case basis for storage of equipment and/or materials during active construction and/or maintenance periods. The Contractor shall be responsible for protection of items stored on Government property and shall ensure adequate safety measures are maintained at such sites.

6.10 Pre-Construction Meeting

A. Government will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Contracting Officer (CO)

2. Contracting Officer’s Representative (COR)

3. Contractor and Subcontractors

4. Inspector

C. Agenda:

1. Execution of Government-Contractor Agreement.

2. Distribution and discussion of Contract Documents.

3. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

4. Designation of personnel representing the parties to Contract, Contractor, and Government.

5. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

6. Questions and answers related to the contract and/or the project requirements.

6.11 Payment Provisions

The government will make progress payments monthly when properly invoiced. Progress payments will not be processed until the government has reviewed and accepted the contractor’s pre-bill submittals.

6.12 Quality Control

The contractor shall provide and maintain a quality control system that will ensure all services, supplies, technical accuracy, completeness, and construction work required under this contract conforms to the contract requirements. This includes all the sampling, inspection, and testing required to complete all tasks. The contractor shall revise/correct any errors or

12363N26Q4197 NFSR 192 Road Restoration Page 14 of 99 deficiencies that occur during the project duration that are a direct result of contractor negligence at no cost to the government.

Prior to submission of any documents required by this contract, the contractor’s Quality Control individual shall review and ensure the submittals are accurate and in compliance with the contract.

6.13 Personal Protective Equipment (PPE)

The contractor will train all employees in the safe operation and use of equipment that is to be used in the performance of this contract. Personal protective equipment, including personal protective equipment for eyes, face, head, hands, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.

Defective or damaged personal protective equipment shall not be used. The contractor shall ensure that each employee wears foot protection that provides adequate traction, ankle support, and enclosed toe area.

The contractor shall provide, at no cost to the employee, and ensure that each employee who works in an area where there is potential for head injury from falling objects or flying objects, wears a hard hat that meets the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.

The contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.

The contractor shall provide, at no cost to the employee, hearing protection where there is potential for hearing loss due to high intensity noise.

6.14 Basic First Aid

Basic first aid supplies shall be maintained, available and under the charge of the person using motorized equipment.

The supplies shall include supplies that are commonly found in a standard First Aid Kit, such as the type found for camping use or carried in motor vehicle.

6.15 Safety

Before work commences the Contractor shall present a Safety Plan that addresses the hazards associated with the requirements of the project and per OSHA standards.

6.16 Landscape Preservation

The Contractor shall confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits.

Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

Operations shall be scheduled and conducted to minimize erosion of soil and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (streams, creeks, etc.).

Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or wastewater from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

12363N26Q4197 NFSR 192 Road Restoration Page 15 of 99

6.17 Loss, Damage, or Destruction

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment. All claims arising under this clause will be submitted to the Contracting Officer.

6.18 Control of Noxious Weeds

To prevent the introduction and control the spread of seeds of noxious weeds onto and around National Forest land, the Contractor shall ensure all equipment moved onto National Forest land is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. The contractor shall notify the CO and Contracting Officer’s Representative (COR) a minimum of ten (10) business days in advance of equipment arrival. Government inspection is required before any unloading of equipment. The Contractor shall certify their compliance with this requirement in writing. All contractor’s vehicles and equipment inspections shall be done prior to entrance into the National Forest.

6.19 Temporary Facilities

Any temporary facilities needed during project construction (portable toilets, tanks, storage containments, etc.) shall be stored at designated locations approved by the Contracting Officer’s Representative. After the conclusion of the project, all temporary facilities and components shall be completely removed.

6.20 Construction Tolerances

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

6.21 Final Cleanup

Before final acceptance of the project, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, equipment, tools, and all parts of the work area shall be left in a neat and presentable condition.

Attachments Schedule of Items Engineering Drawings/Plans FSSS (FS Supplemental Specifications)

12363N26Q4197 NFSR 192 Road Restoration Page 16 of 99

PROJECT LOCATION

VICINITY MAP

TRAVEL DIRECTIONS:

INDEX OF SHEETS

SHEET SHEET TITLE

G-01

TITLE SHEET

G-02

PROJECT MAP

G-03 SCHEDULE OF ITEMS / CONSTRUCTION NOTES

G-04 GENERAL NOTES

G-05 TEMPORARY TRAFFIC SIGNS

C-01 - C-04 NFSR 192 WORKLISTS

D-01 - D-03 TYPICAL ROADWAY SECTIONS

D-04 LINEAR GRADING SECTIONS

D-05 RECONDITIONING SECTIONS

D-06 CLEARING LIMITS AND SEEDING NOTES

D-07 DITCHING AND RIP RAP DETAILS

D-08 HARD DIP DETAILS

D-09 ROLLING DIP DETAILS

D-10 SOIL EROSION DETAILS

D-11 14' STEEL GATE DETAILS

D-12 CULVERT INSTALLATION DETAILS

D-13

CULVERT DETAILS

D-14 CULVERT SCHEDULE AND NOTES

D-15 - D-16 CULVERT BAND DETAILS

D-17 STAKING DETAILS

United States Department of Agriculture

Forest Service

(R8) SOUTHERN REGION

NATIONAL FORESTS IN NORTH CAROLINA

AVERY COUNTY, NORTH CAROLINA

GRANDFATHER RANGER DISTRICT

NFSR 192 ROAD RESTORATION

SHEET 1 of 26

FROM THE INTERSECTION OF HIGHWAY 105 (N. LINVILLE AVE.) AND

US-221 IN LINVILLE, NC, HEAD SOUTH ON NC-1545 FOR 0.3 MILES AND

THEN TURN LEFT ONTO ROSEBORO ROAD FOR 6.8 MILES. THIS

TAKES YOU TO THE BEGINNING OF THE PROJECT. THERE ARE

WEIGHT RESTRICTED BRIDGES NORTH AND SOUTH OF THE

BEGINNING (SOUTH END) OF NFSR 192 (OLD HOUSE GAP ROAD).

BEGINNING AND END OF PROJECT:

LATITUDE: BEGINNING: 36°01'54.50"N END: 36°04'41.75"N

LONGITUDE: BEGINNING: 81°48'11.80"W END: 81°47'00.70"W

NATIONAL FOREST

SYSTEM ROAD 192

END OF PROJECT

NFSR 192

NATIONAL FOREST

SYSTEM ROAD 192

BEGINNIN OF PROJECT

RECOMMENDED BY:

APPROVED:

FOREST SUPERVISOR

DATE

TRANSPORTATION PROGRAM MANAGER DATE

PUBLIC SERVICES STAFF OFFICER

DATE

DISTRICT RANGER

DATE

CIVIL ENGINEER DATE

12363N26Q4197 NFSR 192 Road Restoration Page 17 of 99

CHECKED

DATE

PROJECT NO.

DWG SHEET NO.

United States Department of Agriculture Forest Service

NFSR 192 ROAD

RESTORATION

NATIONAL FORESTS IN

NORTH CAROLINA

GRANDFATHER RANGER

DISTRICT

PROJECT MAP

6/17/2025

E. CROMELL

E. CROMELL

G. RASKELL

ARCHIVE NO.

ARCHIVE_NUMBER

DRAWING TITLE

G-02

SHEET 2 OF 26

(R8)

SOUTHERN REGION

NFSR 192

ROAD RESTORATION

EXISTING GATE

ACCESS FOR THIS PROJECT IS FROM THE NORTH END - WHICH IS THE END

OF THE PROJECT STATIONING. ROSEBORO ROAD HAS WEIGHT

RESTRICTED BRIDGES NORTH AND SOUTH OF THE BEGINNING OF THE

PROJECT NEAR THE SOUTH END OF NFSR 192 (OLD HOUSE GAP ROAD).

LATITUDE: BEGINNING: 36°01'54.50"N END: 36°04'41.75"N

LONGITUDE: BEGINNING: 81°48'11.80"W END: 81°47'00.70"W

ANDREWS CREEK AOP CROSSING

@ NFSR 192 LOCATION:

LATITUDE: 36°04'09.85"N

LONGITUDE: 81°48'41.50"W

NFSR 192

END OF PROJECT

MP 6.545

ANDREWS CREEK

AOP CROSSING

ROAD IS WASHED OUT

NOT PASSABLE

MP 3.480

NFSR 192

BEGINNING

OF PROJECT

MP 0.000

NOTE:

ACCESS FOR HEAVY CONSTRUCTION EQUIPMENT SHALL BE FROM THE END

OF THE PROJECT WORKING SOUTH ON NFSR 192 AS THIS IS THE BEST

ROUTE FOR LOW BOY, TRACTOR-TRAILER AND DUMP TRUCKS.

HEAD EAST ON US-221 THEN SOUTH ON PILOT RIDGE ROAD THEN WEST ON

EDGEMONT ROAD TO NFSR 192 (END OF PROJECT).

PILOT RIDGE ROAD HAS STEEP GRADES AND TIGHT RADIUS CORNERS. A

CHASE VEHICLE MAY BE NECESSARY FOR LOW BOY HAUL.

ROSEBORO

ROAD

WEIGHT

RESTRICTED

BRIDGE

APPROXIMATE

LOCATION WEIGHT

RESTRICTED

BRIDGE

NARROW

ROAD WITH

WEIGHT

RESTRICTED

BRIDGE

US-221

BLUE RIDGE PARKWAY

SECTIONS MAY BE CLOSED

PILOT

RIDGE RD

EDGEMONT

ROAD

SEE WORKLIST

PAGE C-01

SEE WORKLIST

PAGE C-02

SEE WORKLIST

PAGE C-03

NARROW ROAD

WITH NARROW

BRIDGES

12363N26Q4197 NFSR 192 Road Restoration Page 18 of 99

AutoCAD SHX Text

PROJECT NAME

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

CHECKED

DATE

PROJECT NO.

DWG SHEET NO.

United States Department of Agriculture Forest Service

NFSR 192 ROAD

RESTORATION

NATIONAL FORESTS IN

NORTH CAROLINA

GRANDFATHER RANGER

DISTRICT

SCHEDULE OF ITEMS &

CONSTRUCTION NOTES

6/17/2025

E. CROMELL

E. CROMELL

G. RASKELL

ARCHIVE NO.

ARCHIVE_NUMBER

DRAWING TITLE

G-03

SHEET 3 OF 26

(R8)

SOUTHERN REGION

CONSTRUCTION NOTES

SLASH DISPOSAL

SLASH AND DEBRIS DISPOSAL: TREATMENT OF SLASH AND WOODY DEBRIS SHALL BE BY METHOD B, SCATTER

CONSTRUCTION SLASH IN DESIGNATED AREAS WITHOUT DAMAGING TREES. SLASH SHALL NOT BE DISPOSED

OF (1) WITHIN ANY DEFINED STREAM CHANNEL OR (2) WITHIN ANY MARKED BOUNDARIES OF A PROTECTED

STREAM. EQUIPMENT SHALL NOT BE OPERATED WITHIN ANY STREAM CHANNEL EXCEPT AS ESSENTIAL IN

CONSTRUCTION OF ROADS.

EXCAVATION

CONSTRUCTION TOLERANCES: ALL DITCHES AND DRAINAGE DIPS SHALL BE CONSTRUCTED TO FLOW IN THE

DIRECTION SHOWN ON THE DRAWINGS OR DESIGNATED ON THE GROUND. TOLERANCE CLASS (A).

SEEDING & MULCHING

SEEDING AND MULCHING SHALL BE COMPLETED ON ALL REQUIRED AREAS OF INDIVIDUAL ROADS WITHIN 15

DAYS AFTER COMPLETION OF EXCAVATION.

BORROW

USE ONLY SUITABLE ROADWAY EXCAVATION IN EMBANKMENT CONSTRUCTION FOR THIS PROJECT. DO NOT

BORROW FROM OUTSIDE THE CONSTRUCTION LIMITS. UNSUITABLE MATERIAL SHALL BE HAULED TO AN AREA

DESIGNATED BY THE USFS.

CULVERTS

DITCH BLOCKS AND INLET/OUTLET LEAD OUT DITCHES ARE CONSIDERED INDIRECT TO CULVERT LINEAL FOOT

COSTS AND SHALL BE INCLUDED IN THE COST PER FOOT. LOCATIONS FOR DITCH BLOCKS AND LEAD OUTS

SHALL BE STAKED ON THE GROUND. BEDDING AND BACKFILL SHALL BE CONSIDERED INDIRECT TO CULVERT

LINEAL FOOT COSTS AND SHALL BE INCLUDED IN THE COST PER FOOT. 2 CUBIC YARDS OF CLASS 2 RIP RAP

SHALL BE PLACED AT THE OUTLET OF THE CULVERT BELOW THE INVERT TO PREVENT SCOUR. THIS RIP RAP

SHALL BE INDIRECT TO THE COST PER FOOT OF CULVERT INSTALLATION. THERE MAY BE MORE RIP RAP

CALLED FOR ON PLANS AND SHALL BE PAID FOR SEPARATELY UNDER SECTION 251. GEOTEXTILE FABRIC

SHALL BE PLACED BELOW ALL RIP RAP AND INCIDENTAL TO CULVERT AND/OR RIP RAP UNIT COSTS.

1. THIS DESIGN USES THE "STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROAD AND BRIDGES ON FEDERAL

HIGHWAY PROJECTS, (FP-14)" AND ATTACHED FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS (FSSS).

2. AGGREGATE SHALL BE FROM A CERTIFIED WEED FREE COMMERCIAL SOURCE. PROVIDE CO WRITTEN NOTIFICATION OF

PROPOSED MATERIAL SOURCE 30 DAYS PRIOR TO USE, AS REQUIRED IN FSSS 105.02(c).

3. USFS CLASS F AGGREGATE SURFACING MAY BE SUBSTITUTED WITH NCDOT ABC SURFACING. USFS CLASS B

AGGREGATE BASE MAY BE SUBSTITUTED WITH NCDOT 57 AND USFS CLASS 2 RIP RAP MAY BE SUBSTITUTED WITH

NCDOT CLASS 1 RIP RAP, USFS CLASS 3 MAY BE SUBSTITUTED WITH NCDOT CLASS 2 RIP RAP, USFS CLASS 4 MAY BE

SUBSTITUTED FOR NCDOT CLASS 3.

4. USFS WATER DRAFTING GUIDELINES: AT A MINIMUM, ANY WATER WITHDRAWAL IN ACTIVE STREAMS WITH FISH PRESENT

SHALL HAVE SCREENED INTAKES WITH A MAXIMUM SCREEN OPENING OF 3/32 INCH, MAXIMUM INTAKE VELOCITY OF 0.4

FEET PER SECOND AND WILL NOT REDUCE STREAM FLOW BY MORE THAN 10% BY VISUAL MEASURE. WATER

WITHDRAWAL FROM ANY OTHER SOURCE SHALL BE APPROVED IN WRITING, PRIOR TO USE, BY THE CO.

5. PRIOR TO DIGGING, CALL "DIG SAFELY NORTH CAROLINA" 811. LOCATING AND PROTECTION OF ALL UTILITIES (PUBLIC &

PRIVATE) IS THE RESPONSIBILITY OF THE CONTRACTOR.

6. CONTRACTING OFFICERS APPROVAL IS NEEDED WITH A MINIMUM OF 72 HRS NOTICE PRIOR TO THE PLACEMENT OF THE

FOLLOWING ITEMS: BEDDING OR LEVELING COURSE OF ANY STRUCTURE AND ASPHALT CONCRETE.

7. REMOVE ALL CONSTRUCTION RELATED REFUSE FROM GOVERNMENT LAND PRIOR TO FINAL ACCEPTANCE.

8. REPAIR ANY DAMAGE TO THE EXISTING ROAD SYSTEM DUE TO CONTRACTOR'S OPERATIONS, INSIDE THE PROJECT

BOUNDARY. THERE IS AGGREGATE SURFACING WITHIN THIS CONTRACT TO PROVIDE "CONSTRUCTION MAINTENANCE".

THIS WORK SHALL BE AT THE CONTRACTOR'S EXPENSE AND SHALL BE COMPLETED PRIOR TO FINAL ACCEPTANCE.

9. CONFINE CONSTRUCTION EQUIPMENT TO THE ROADWAY, STAGING AREAS OR DESIGNATED WASTE DISPOSAL SITES, UNLESS OTHERWISE SHOWN ON THE PLANS OR APPROVED BY THE CO.

10. STORING OF ALL EQUIPMENT ON GOVERNMENT LANDS WILL BE AT THE CONTRACTOR'S RISK AND AT A LOCATION

APPROVED BY THE CO.

11. DEPTHS OF SOIL AND AGGREGATE ARE GIVEN AS FINAL COMPACTED DEPTHS.

12. CONSTRUCTION TOLERANCE IS 'F' UNLESS OTHERWISE NOTED ON THE DRAWINGS.

13. DESIGNATED WASTE AREA LOCATIONS SHALL BE APPROVED BY THE CO. CO WILL FLAG THE DISPOSAL AREAS PRIOR TO

PLACEMENT OF MATERIAL. SMOOTH, SHAPE, AND COMPACT TO DRAIN WITH CONSTRUCTION EQUIPMENT.

14. THE SUBMITTED TRAFFIC CONTROL PLAN SHALL INCLUDE METHODS TO WARN PUBLIC TRAFFIC OF ROAD WORK

ACTIVITIES. ALL CONSTRUCTION SIGNS SHALL MEET CURRENT MUTCD REQUIREMENTS.

15. SALVAGE AND STOCKPILE EXISTING AGGREGATE DURING EXCAVATION AND USE AS INITIAL BACKFILL AND BEDDING

MATERIAL.

16. FOREST SERVICE BRIDGES: USE OF ROADS BY COMMERCIAL USERS WITH LOADS EXCEEDING NORTH CAROLINA STATE

LEGAL LOADING FOR A STP (SINGLE TRIP PERMIT) AND THAT WILL CROSS BRIDGES UNDER FOREST SERVICE

JURISDICTION SHALL APPLY FOR A BRIDGE OVERLOAD USE PERMIT (FSM 7736. 05). PROCESSING APPLICATIONS FOR

BRIDGE OVERLOAD PERMITS MAY TAKE (30) DAYS OR LONGER. CONTACT THE CO FOR THE BRIDGE OVERLOAD PERMIT

FORM.

17. WATER LEVEL IS SUBJECT TO CHANGE. THE CONTRACTOR IS RESPONSIBLE FOR MAKING THE DETERMINATION OF

EXPECTED WATER LEVELS THAT WILL EXIST DURING RECONSTRUCTION/RECONDITIONING. CONTRACTOR SHALL BE

RESPONSIBLE FOR DIVERSION OF WATER DURING CONSTRUCTION AS REQUIRED.

18. THE CONTRACTOR SHALL PERFORM ALL WORK BETWEEN THE HOURS OF 6:00 AM AND 6:00 PM MONDAY THROUGH

FRIDAY. NO WORK SHALL BE PERFORMED ON WEEKENDS OR FEDERAL HOLIDAYS WITHOUT PRIOR APPROVAL FROM THE

CO.

ABBREVIATIONS:

POB - POINT OF BEGINNING NFSR - NATIONAL FOREST SYSTEM ROAD CO - CONTRACTING OFFICER

POE - POINT OF END USFS - UNITED STATES FOREST SERVICE

FSSS - FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS*INDICATES CONTRACT QUANTITIES

12363N26Q4197 NFSR 192 Road Restoration Page 19 of 99

AutoCAD SHX Text

PROJECT NAME

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

AutoCAD SHX Text E

CONTRACTOR RESPONSIBLE FOR ANY UTILITY LINE LOCATES AND ANY DAMAGED DONE TO UTILITY LINES DURING EARTHWORK

CHECKED

DATE

PROJECT NO.

DWG SHEET NO.

United States Department of Agriculture Forest Service

NFSR 192 ROAD

RESTORATION

NATIONAL FORESTS IN

NORTH CAROLINA

GRANDFATHER RANGER

DISTRICT

GENERAL NOTES

6/17/2025

E. CROMELL

E. CROMELL

G. RASKELL

ARCHIVE NO.

ARCHIVE_NUMBER

DRAWING TITLE

G-04

SHEET 4 OF 26

(R8)

SOUTHERN REGION

GENERAL NOTES

1. THE CONTRACTOR SHALL SUBMIT A DETAILED CONSTRUCTION SCHEDULE TO THE CO FOR APPROVAL PRIOR TO THE START OF WORK.

2. ALL WORK SHALL BE IN COMPLIANCE WITH THE BEST MANAGEMENT PRACTICES DESCRIBED IN THE NATIONAL BEST MANAGEMENT PRACTICES FOR WATER QUALITY MANAGEMENT ON NATIONAL FOREST SYSTEM LANDS, DATED

APRIL 2012.

3. PUBLIC SAFETY, TRAFFIC CONTROL, AND DUST CONTROL SHALL BE PROVIDED BY CONTRACTOR IN ACCORDANCE WITH STATE AND COUNTY REQUIREMENTS. CONTRACTOR SHALL SUBMIT A TRAFFIC CONTROL PLAN.

4. THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE CO OF ANY DISCREPANCIES ENCOUNTERED BETWEEN FIELD CONDITIONS AND THESE PLANS OR ERRORS IDENTIFIED IN THE CONTRACT.

5. THE CONTRACTOR SHALL KEEP DETAILED RECORDS AND AS-BUILTS SHOWING ALL MODIFICATIONS MADE TO THESE PLANS. THESE RECORDS AND AS-BUILTS SHALL BE PROVIDED TO THE CO UPON PROJECT COMPLETION.

6. THE CONTRACTOR IS RESPONSIBLE FOR THE PROTECTION OF ALL EXISTING MONUMENTS AND OTHER SURVEY MARKERS. ANY MARKERS DESTROYED DURING CONSTRUCTION SHALL BE REPLACED AT THE CONTRACTOR'S

EXPENSE.

7. STAGING AREAS FOR EQUIPMENT STORAGE OR MATERIAL STOCKPILES WILL BE ALLOWED ONLY IN AREAS APPROVED BY THE CO.

8. THE CONTRACTOR IS RESPONSIBLE FOR WATER, ELECTRICITY, AND RESTROOMS.

9. ALL EQUIPMENT WILL ARRIVE ON SITE WASHED AND FREE OF ALL VISIBLE SOIL, DEBRIS, AND ORGANIC MATTER. ALL EQUIPMENT WILL BE APPROVED BY THE CO PRIOR TO UNLOADING ON THE PROJECT SITE.

10. THE CONTRACTOR IS RESPONSIBLE FOR MATCHING EXISTING IMPROVEMENTS AND THE SURROUNDING LANDSCAPE WITH SMOOTH TRANSITIONS. THE CONTRACTOR SHALL AVOID CREATING ANY ABRUPT OR APPARENT

CHANGES IN GRADES OR CROSS SLOPES, TO THE SATISFACTION OF THE CO. THE COSTS OF ANY BACKFILL OR EXCAVATION REQUIRED FOR SUCH TRANSITIONS ARE INDIRECT TO OTHER ITEMS.

11. THE GOVERNMENT MAY DESIGNATE BORROW SITES AS NEEDED.

12. ANY DISTURBANCE MADE OUTSIDE OF ROADWAY CORRIDORS, SUCH AS BORROW SITES AND STAGING AREAS, SHALL BE RESTORED. AT A MINIMUM, COMPACTED AREAS SHALL BE DE-COMPACTED TO A 12" DEPTH, SHAPED TO

DRAIN, AND SEEDED AND MULCHED.

13. WATER SOURCES SHALL BE DESIGNATED BY THE CO. WATER SOURCES SHALL COMPLY WITH SECTION 891. WHEN DRAFTING FROM WATER SOURCES, USE SCREENED DEVICES FOR WATER DRAFTING PUMPS. USE PUMPS

WITH LOW ENTRY VELOCITY TO MINIMIZE REMOVAL OF AQUATIC SPECIES, INCLUDING JUVENILE FISH, AMPHIBIAN EGG MASSES, AND TADPOLES FROM AQUATIC HABITATS. WATER FOR DUST CONTROL AND COMPACTION OF

AGGREGATE BASE OR SURFACING IS INCIDENTAL TO THOSE PAY ITEMS.

14. SEED, MULCH AND FERTILIZE DISTURBED AREAS OUTSIDE OF THE ROADWAY. SEE THE SEED MIX, FERTILIZER, MULCH AND TIMING RESTRICTIONS ON THIS PAGE.

15. ANY WATER NEEDED TO ADJUST MOISTURE FOR AGGREGATE SHALL BE INCLUDED IN THE UNIT PRICE AND IS INDIRECT TO THE UNIT COST OF THE AGGREGATE.

(FSSS) 704.02 Bedding Material.

(a) Maximum particle size

3 in (75 millimeters) or half the corrugation depth, whichever is smaller

(FSSS) 704.03 Backfill Material.

Delete the subsection and replace with the following:

704.03 Backfill Material.

Furnish granular material or fine compactible soil free of excess moisture, muck, frozen lumps, roots, sod, and other deleterious material.

(FP-14) 703.05 Subbase, Base, and Surface Course Aggregate

(a) General. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:

(1) Los Angeles abrasion, AASHTO T 96 50 percent max.

(2) Soundness of aggregate using sodium sulfate, 12 percent loss max.

AASHTO T 104 (5 cycles)

(3) Durability index (coarse), AASHTO T 210 35 min.

(4) Durability index (fine), AASHTO T 210 35 min.

(5) Fractured faces, ASTM D5821 50 percent min.

(6) Without organic matter and lumps or balls of clay.

(b) Subbase or base aggregate. In addition to Subsection 703.05(a), conform to the following:

(1) Gradation Table 703-2

(2) Liquid limit, AASHTO T 89 25 max.

(b)

Material passing No. 200 (75-µm)sieve, 10.0 percent max.

AASHTO T 27 and AASHTO T 11

Table 705-1

Gradation Requirements for Riprap(1)

Class % of Rock

Equal or Smaller by Count, DX

Range of Intermediate Dimensions,(2) inches (millimeters)

Range of Rock Mass,(3) pounds (kilograms)

100 9

15 (230– 380) 59 – 270 (27

120)

85 7 – 11 (180– 280) 28 – 110 (13 – 50)

50 5

8 (130– 200) 10 – 42 (5

19)

15 3

6 (80 – 150) 2 – 18 (1

8)

100 15

21 (380– 530) 270 – 750 (120

340)

85 11

15 (280– 380) 110 – 270 (50

120)

50 8

11 (200 – 280) 42 – 110 (19

50)

15 6

8 (130– 200) 10 – 42 (6

19)

100 21

27 (530– 690) 750 – 1600 (340

730)

85 15

19 (380– 480) 270 – 560 (120

250)

50 11

14 (280– 360) 110 – 220 (50

100)

15 8

10 (200– 250) 42 – 81 (19

37)

100 27

33 (690– 840) 1600 – 2900 (730

1300)

85 19

23 (480– 580) 560 – 990 (250

450)

50 14

17 (360– 430) 220 – 400 (100

180)

15 9

12 (230– 300) 59 – 140 (27

64)

(1) Gradation includes spalls and rock fragments to provide a stable, dense mass.

(2) The intermediate dimension is the longest straight- line distance across the rock that is perpendicular to the rock’s longest axis on the rock face with the largest projection plane.

(3) Rock mass is based on a specific gravity of 2.65 and 85 percent of the cubic volume as calculated using the intermediate dimension.

12363N26Q4197 NFSR 192 Road Restoration Page 20 of 99

PROJECT NAME

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

W20-7AW20-1

TRUCKS

30" X 30" 30" X 30" 30" X 30"

W21-3

36" X 36"

W20-7B

30" X 30"

TEMPORARY TRAFFIC…