SOFIA Mirror Coater Relocation - Statement of Work.pdf
PDF 828 KB Posted
- Solicitation number
- 80ARC023R001
About this file
This statement of work outlines the requirements for planning and executing the relocation of a mirror coater and associated ground support equipment from Armstrong Flight Research Center to Ames Research Center. The scope includes dismantling, packaging, transporting, and unloading the mirror coater and ground support equipment. Key requirements include developing a relocation plan, preparing equipment for disassembly, dismantling and packing subassemblies, providing rigging for transport, transporting all items to Ames Research Center, and unloading at the specified location. The period of performance must be completed by March 2024. Administrative requirements specify work hours, personnel lists, a project schedule, activity hazard analyses, equipment lists, safety lockout/tagout procedures, and crane operation plans.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOFIA Mirror Coating System Description and Components.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
23 October 2023
STATEMENT OF WORK
Stratospheric Observatory for Infrared Astronomy (SOFIA) Mirror Coater Move from
AFRC to ARC
Contents
1. Objective
2. Project Summary
3. Scope and Specifications
4. Period of Performance
Appendix A Administrative Requirements
A.1 Work Hours
A.2 Personnel List
A.3 Project Schedule Requirements
A.4 Project Implementation Review Meeting
A.5 Activity Hazard Analysis
A.6 Moving Equipment List
Appendix B Safety Lockout/Tagout Procedures
B.1 Tag Placement
B.2 Tag Removal
Appendix C Crane Operations
C.1 Crane Operations Plans/Documents
C.2 Crane Safety Checklist for Facility Lifts:
1. Objective The objective of this contract is to plan and execute the move of the Stratospheric Observatory for Infrared Astronomy (SOFIA) Mirror Coater and Ground Support Equipment from the current site in building 703 at the Armstrong Flight Research Center (AFRC) in Palmdale, CA, to Ames Research Center (ARC), Moffett Field, CA. The contract will include dismantling, packaging, transportation, and unloading. Reassembly, installation, activation, and performance testing is not included in this contract. The unloading and storage location at ARC is not yet determined, but will be communicated at least 30 days prior to the move.
must be performed to ensure that any structures, particularly the welded structures within the chamber, are safe or can be braced appropriately for shipment.
j) The contractor shall develop a Relocation Plan to be reviewed prior to the Project Implementation Review. This document shall include the results of the assessment of stability of the mechanical structures for transport, the method proposed to ensure that the electrical connections can be made appropriately during the re-assembly, the plan for bracing, packing and crating the major assembly or sub-assemblies; the plan for dis-assembly and re-assembly, handling of major elements, a critical lift plan (if necessary), and identification and mitigation strategies for risks.
k) The contractor shall prepare all portions of the Mirror Coater System for disassembly.
This includes making safe all pressure lines, pumps, and any other sub-assembly which requires preparation for dismantling and shipment.
l) The contractor shall dismantle and pack for safe transport all sub-assemblies and ground support equipment. The contractor shall protect all components from any contamination in packing or transport that would impair the ability of the Mirror Coater to pump down to the designed vacuum pressures.
m) The contractor shall provide rigging appropriate to transport all large assemblies to ARC.
n) The contractor shall transport all elements of the Mirror Coater System and its ground support equipment to ARC in Moffett Field, CA.
o) The contractor shall unload the Mirror Coater System at ARC at the NASA-specified location. This location shall be provided to the contractor at least 30 days prior to arrival.
p) The entrance door to the AFRC room has approximately 1” of clearance beyond the
Mirror Coater upper lip, which is the largest full diameter part of the vessel, yet not the widest protuberance. The Contractor shall submit a Lift Plan detailing the method by which the Contractor will bring the vessel through this doorway. The Lift Plan is subject to Government approval.
q) The Contractor shall develop the procedure and means by which the Mirror Coater is removed, transported, and unloaded and shall provide the Government with the assessments, and analyses that are used to demonstrate that a safe method of disassembly and manipulation is planned.
r) Equipment in the Mirror Coating Facility (MCF) that uses fluids in their operation are the Leybold mechanical pump and Roots blower assembly, the CVI cryopumps, the Meissner cryo traps and the gaseous Argon delivery system for the glow discharge cleaning sequence. For disassembly, the Contractor shall properly handle components with fluids, which are the Leybold mechanical pump and Roots blower assembly and the CVI cryopumps.
s) The fluid used in the mechanical pumping system is an inorganic synthetic material, one of whose trade names is Fomblin. Under normal conditions, this fluid is non-hazardous to personnel. However, for the protection of the equipment, the Contractor shall insure that the pumps remain in an upright position (as currently installed) during the MCF disassembly, and shipment. This is to avoid fluid migrating to areas that could possibly damage the pumps upon restarting. After removal, the Contractor shall seal the system components to prevent contamination during the move.
t) The two CVI cryopumps and their compressors, as well as the interconnecting braided lines, contain helium at pressures of over 200 psi. Because of the high pressures involved and the specialized nature of cryopumping equipment, both personnel and equipment hazards are present and this equipment shall only be disassembled by those familiar with this type of equipment. After removal, the Contractor shall seal the system components to prevent contamination during the move.
u) The Meissner cryo trap delivery system uses LN2 from portable tanks that is only connected during coating chamber operation, and therefore presents no hazard during disassembly, shipment or re-assembly; however, the Contractor shall seal the system components to prevent contamination during the move.
v) The gaseous Argon delivery system uses a high pressure cylinder that is only connected during coating chamber operation, and therefore presents no hazard, however, the Contractor shall seal the system components to prevent contamination during the move.
w) The Contractor shall provide the Relocation Plan and the completed wiring list information to the Government for review and approval before any disconnections are made. These wire lists, photos and other documents shall be available completely via electronic format. No handwritten documents shall be used.
x) The Contractor shall disconnect AFRC facility electrical equipment and remove all wiring back to the closest breaker panel.
y) The Contractor shall provide clean up at the AFRC facility, patching any penetrations in walls created by the dismantling or extraction of the mirror coater. Any patches made to walls shall preserve the integrity of the firewalls.
z) At the AFRC facility, the contractor shall grind down all protrusions in the floor from existing tie down bolts, patch the floor with a durable material (such as epoxy), and ensure a smooth surface. The Contractor shall protect the facilities in which work is occurring for this project and restore the facility to the original condition in accordance with FAR 52.236-9 and Section I should any damage be done.
aa) The Contractor shall document existing MCF component orientation for parts mounted on the coating chamber and auxiliary equipment so that the removed components can be re-assembled in the exact orientation as they were before removal for shipping. This shall be accomplished by both photographic and physical documentation of the components before removal from the existing system. In addition, a number of components, such as the cryopumps, must be shipped in preferred orientations. The Contractor shall evaluate each component to be moved and document intended handling and packaging means.
How these components are shipped shall be photographed and documented.
bb) The contractor must deliver a Lift Plan for both loading and unloading per Appendix C.
cc) The Contractor shall use air-ride suspension vehicles for transport or identify any Mirror
Coating System equipment that is to be truck-transported by means other than an air-ride suspension equipped truck, along with justification for the appropriateness of alternative means.
4. Period of Performance Site visits may begin after award and are expected to occur in December 2023 or January 2024.
The Mirror Coater move shall be completed no later than March 2024.
Appendix A Administrative Requirements
A.1 Work Hours
All work under this contract shall be performed during normal duty hours for each facility.
Normal duty hours at ARC are from 7:00 a.m. to 5:00 p.m. Normal duty hours at the AFRC are from 7:00 a.m. to 5:00 p.m. Weekends and Government holidays are restricted for work.
Additional days during Thanksgiving, Christmas, and New Years may also be restricted. This will be discussed further at contract award.
A.2 Personnel List
The Contractor shall furnish a list of contact personnel of the Contractor and subcontractors at the Contract Initiation Meeting including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
The Contractor shall submit for approval at least 10 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project for each site (NASA/ARC and NASA/AFRC-B703. Furnish for each person:
a. Full Name
b. Date and place of birth
c. Citizenship
d. Company
e. Driver's License Number and State of Issue
f. Last 6 digits of Social Security number
g. Green card for legal permanent residents (if applicable)
The request for personnel passes shall be accompanied with the following certification:
"I hereby certify that all personnel on this list are either born U.S. citizens, naturalized U.S.
citizens with the naturalization number shown, or legal aliens with the alien registration number indicated."
Signature/Firm Name
A.3 Project Schedule Requirements
The Contractor shall provide a Project Schedule that includes lines identifying the significant and definable features of the technical tasks of the project to an appropriate level of detail. The Contractor shall include the following items in the Project Schedule:
b) Activity Hazard Analysis
c) Analysis of welded structures stability for transport
d) Certifications of Rigging Equipment and Operators
e) Signed Code of Safe Practices
f) Pre-Lift Safety Checklist
g) Moving Equipment List (see A.6)
h) Logistics and Site Requirements
i) Project Schedule (any revisions)
A.5 Activity Hazard Analysis
Prior to beginning each Definable Feature of Work (DFOW), an activity hazard analysis shall be prepared by the Contractor performing the work. A DFOW is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform. Work will not proceed on that phase until the activity hazard analysis has been accepted by NASA and discussed with all engaged in the activity, including the Contractor, subcontractors, and government on-site representatives.
The Activity Hazard Analysis shall:
a) Define the activity to be performed and identify the sequence of work,
b) Define the specific hazards anticipated with the activity,
c) Define the control measures to be implemented to eliminate or reduce each hazard to an acceptable level,
d) Identify the equipment to be used,
e) Identify the inspection requirements for that equipment and activity, and
f) List the training requirements for the workers.
A.6 Moving Equipment List
Prior to the start of work, the Contractor shall submit a moving equipment list showing the locations and dimensions of moving equipment (including equipment and material storage area (onsite and offsite), and access and move routes, avenues of ingress/egress to the move sites).
The Contractor shall indicate if the use of a supplemental or other staging area is desired. The Contractor shall show locations of safety fences, site trailers, equipment/truck entrances, and trash dumpsters.
Appendix B Safety Lockout/Tagout Procedures Contractor shall ensure that each employee is familiar with and complies with these procedures.
Specific Lockout/Tagout requirements are as follows:
a) The tags shall be the same for both lockout and tagout, and shall only be used once. The information on the tag shall be printed legibly.
b) For lockout the information shall include - name of person controlling the lock, the date the lock was put in place, telephone number of the person controlling the lock, name of the Project Inspector monitoring the work, name of the company serving as prime contractor for the work, and the name of the company for which the lock control person is employed.
c) For tagout, the above information is required plus an explanation of why a lock could not be used, and what additional safety precautions were used.
The above information shall be documented, and the record made available for inspection. Upon completion of the Lockout/Tagout Operation the documents shall be stored at the jobsite.
NASA will, at the Contractor's request, apply lockout/tagout tags and take other actions that, because of experience and knowledge, are known to be necessary to make the particular equipment safe to work on.
No person, regardless of position or authority, shall operate any switch, valve, or equipment that has an official lockout/tagout tag attached to it, nor shall such tag be removed except as provided in this section.
No person shall work on any equipment that requires a lockout/tagout tag unless he, his immediate supervisor, project leader, or a subordinate has in his possession the stubs of the required lockout/tagout tags.
When work is to be performed on electrical circuits, the contractor shall only allow qualified personnel to perform work on electrical circuits.
A supervisor who is required to enter an area protected by a lockout/tagout tag will be considered a member of the protected group provided he notifies the holder of the tag stub each time he enters and departs from the protected area.
Identification markings on building light and power distribution circuits shall not be relied on for established safe work conditions.
Before clearance will be given on any equipment other than electrical (generally referred to as mechanical apparatus), the apparatus, valves, or systems shall be secured in a passive condition with the appropriate vents, pins, and locks.
Pressurized or vacuum systems shall be vented to relieve differential pressure completely.
Vent valves shall be tagged open during the course of the work.
Where dangerous gas or fluid systems are involved, or in areas where the environment may be oxygen deficient, system or areas shall be purged, ventilated, or otherwise made safe prior to entry.
B.1 Tag Placement
Lockout/tagout tags shall be completed in accordance with the regulations printed on the back thereof and attached to any device which, if operated, could cause an unsafe condition to exist.
If more than one group is to work on any circuit or equipment, the employee in charge of each group shall have a separate set of lockout/tagout tags completed and properly attached.
When it is required that certain equipment be tagged, the Government will review the characteristics of the various systems involved that affect the safety of the operations and the work to be done; take the necessary actions, including voltage and pressure checks, grounding, and venting, to make the system and equipment safe to work on; and apply such lockout/tagout tags to those switches, valves, vents, or other mechanical devices needed to preserve the safety provided. This operation is referred to as "Providing Safety Clearance."
B.2 Tag Removal
When any individual or group has completed its part of the work and is clear of the circuits or equipment, the supervisor, project leader, or individual for whom the equipment was tagged shall turn in his signed lockout/tagout tag stub to NASA. That group's or individual's lockout/tagout tags on equipment may then be removed on authorization by NASA.
Appendix C Crane Operations Cranes shall not be operated without written permission from the cognizant NASA Safety Specialist.
Crane operations must be approved by cognizant NASA Safety Specialist before crane setup begins.
The contractor shall comply with AFRC Lifting Operations, Devices, and Equipment requirements listed in AFOP-8719.9-002
C.1 Crane Operations Plans/Documents
The contractor shall prepare the following plans/documents:
a) Description of Work
1. List the work to be accomplished during the lifting operation
b) Center Impact Analysis,
1. List the affects this activity will have on Center occupants and Center operations, i.e.
evacuate portions of a building, close a fire lane, require special secure access, close a building exit/entrance, etc.
c) Activity Hazard Analysis
1. Per Appendix A
d) Lift Plan
1. The exact size and weight of the load.
2. The maximum load limits for the entire range of the lift.
3. Height of the lift.
4. The lift geometry and sequence of actions.
5. The load radius.
6. The boom length and angle, for the entire range of the lift.
7. Ground conditions and outrigger and mats requirements.
8. A drawing showing the location of the crane and the "from" and "to" pick points, including adjacent buildings, utilities, and other obstructions or hazards.
9. Rigging procedures and rigging hardware.
10. Proof of qualification for the crane operator
11. Environmental conditions under which lift operations are to be stopped.
12. Communication and coordination requirements.
e) The Contractor shall make Personnel Assignments and clearly list by name who will be the Lift Director, Crane Operator, Signalman, Rigger, and Tag Line Persons.
f) The Contractor shall also complete the Crane Safety Checklist prior to commencing lifting operations.
g) The Contractor shall perform a practice pick without the load to verify estimated boom angle(s) required to pick, rotate, and set the load.
C.2 Crane Safety Checklist for Facility Lifts:
a) Crane certifications and documents have been checked and are current, including:
1. Current physician's certificate.
2. Insurance.
3. Pre-lift Safety Meeting minutes.
b) Operator certifications have been checked and are current.
c) Ancillary lifting equipment certifications (slings, chokers, etc.) are current.
d) Boom angle needed to reach both pick point and set points have been checked and capacity of the crane (AT THOSE BOOM ANGLES) is sufficient to lift the intended load.
e) Capacity of the crane at the horizontal angles required for the pick, rotation, and set have been checked against crane manual and capacity is sufficient for the intended load. (Note:
Some cranes, especially crawler cranes that don't have outriggers, DO NOT have the same capacity to the side that they do to the front.)
f) There is sufficient room for crane counterweights to miss all obstructions when the crane rotates horizontally.
g) Clip on crane hook has sufficient spring tension.
h) All people in area are wearing hard hats and safety shoes.
i) Person who is signaling crane operator has been designated and everyone understands who that person is for this operation.
j) Lift Supervisor has been designated and everyone understands who that person is for this operation.
k) Personnel handling tag lines have been designated and they understand that they are not allowed under the load.
l) Ground where outriggers are set has sufficient capacity to resist "punching shear" force which is generated from load and expected geometric configuration of crane.
m) Check for overhead electrical lines within boom radius + 20 feet. Brief the Chief, Facilities Engineering & Asset Management Office on proposed mitigation procedures.
n) Check for underground vaults, tanks, or utilities near the crane location that might collapse or shift causing the crane to shift or sink while under load.
o) Ensure the lifting/hazardous zone is delineated clearly to public (use cones, caution tape, fencing, or other.)