Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF_33_-_CMR_Alarm_Upgrade_-_6_June_15.pdf | ||
| CMR_Alarm_Upgrade_-6_June_15_Oslo.doc | DOC document | |
| signed_cover_letter.pdf | ||
| Diagram_of_Required_CMR_Camera_Locations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C
Statement of Work
1.0 BACKGROUND AND PURPOSE
The U.S. American Embassy in Oslo [Embassy] is seeking to augment the existing security system at the Chief of Mission Residence [CMR]. The aim of this project is to increase the effectiveness of physical security and personnel in place along the perimeter of this historic and politically sensitive estate. The Embassy’s Regional Security Office (RSO) would like to install enough pan-tilt-zoom (PTZ) cameras to cover any existing blind-spots along the perimeter.
The CMR was constructed in 1912 and purchased by the US government in 1926. The property is on the Secretary of State’s Register of Culturally Significant Properties. Today, it serves as an important center for diplomatic engagements between the United States and Norway. It is critical that all work done at the CMR must maintain or restore the original design and character of this important historical property. Security hardware should to the best of our ability present a low visibility profile.
2.0 General Requirements
2.1 The Contractor shall provide personnel, material, equipment, and supervision to complete the technical requirements in this Statement of Work. The Contractor shall be responsible for hiring labor, equipment vendors and shall follow security and safety directives as explained by the Embassy.
2.2 The Contractor shall have limited access into the CMR and outside the areas designated for the project except with permission by the Embassy. The Contractor shall address the impact of the consequent disruption and provide for a continuing level of operation of the American Embassy functions caused by the proposed work.
2.3 All systems should be off the shelf items and serviceable with parts and labor for at least 10 years.
2.4 Estimates shall be in English.
2.5 Normal hours for work shall be from 8:00 a.m. to 4:00 p.m., Monday through Friday.
3.0 Scope of work
Installation of no fewer than twelve new pan tilt zoom cameras with low-light and/or infrared capabilities, including positioning the poles and mounting the cameras to provide full coverage of the entire 320 meters of perimeter fence. The contractor will provide all materials including the camera systems and mounting equipment. PTZ cameras should be comparable to the Bosch High Speed Positioning System. Cameras must be able to work in nighttime and low light and should provide the ability to identify intruders from beyond 100 meters. All cameras should be able to integrate with the command system.
The contractor will set-up and install a perimeter security command software system and monitoring station on-site. All hardware should be securely housed in the CMR. Two work stations with full control and monitoring ability should be set up in the guard house and carriage house. This system should be open-architecture and capable of integrating third-party security equipment.
The Contractor shall provide installation of all poles, concrete, buried power and network cables as well as restoration of any grounds and work spaces back to its pre-work condition. All of the equipment should be off the shelf equipment.
See attached diagram for required locations of pan tilt zoom cameras.
4.0 Contract Administration
4.1 The Embassy does not make representations or warranties of whatsoever kind or nature, either expressed or implied, as to the quality, level of completion, accuracy, extent of compliance with the standards, codes and requirements described or referred to in this SOW, or the extent of coordination between or among the documents provided to the Contractor.
4.2 The Embassy’s review, approval, or acceptance of, nor payment for the services required under this contract shall be construed to operate as a waiver of any rights under this contract or any cause of action against the Contractor arising out of the performance of this contract.
4.3 The Embassy has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Embassy may perform quality assurance inspections [QAI] and to confirm the work is being performed according to the Statement of Work.
5.0 Responsibility of the Contractor
5.1 The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.
5.2 The Contractor shall identify a Project Manager who shall be responsible for the overall management of this Contract. The Project Manager will be approved by the Embassy.
5.3 The Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. The Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries to the Embassy Facilities Manager.
6.0 Construction Requirements
6.1 The Contractor shall be responsible for all required materials, equipment and personnel to manage, administer, and supervise the project. All workmanship shall be of good quality and performed in a skillful manner as determined by the Embassy.
6.2 The Contractor shall have limited access to or be admitted into any building on the compound outside the areas designated for the project except with permission by the Embassy. Contractors will be escorted at all times by Embassy staff.
6.3 The Contractor will be permitted to use the area within the compound for operation of his construction equipment and temporary facilities.
7.0 Deliverable Schedule
7.1 The Contractor shall commence work under this contract promptly, execute the work diligently, and achieve final completion and acceptance of this project including final cleanup of the premises within the contract period specified.
7.2 Within 15 days of contract award the contractor will meet with the Embassy facilities Manager to establish a schedule of work to completion.
8.0 Security
8.1 This is a non-classified project. The work to be performed under this contract requires that the Contractor, its employees and sub-contractors submit corporate, financial and personnel information for review by the Embassy to obtain access to the embassy. Information submitted by the Contractor will not be disclosed beyond the Embassy.
-End Statement of Work-