SLV_AFD_Concrete_SOW_v2_1.docx

DOCX document 10 MB Posted

Attached to
SLV-CB SHOP FLOOR AND APRON REPAIR
Solicitation number
140R4024Q0064
Issued by

About this file

This document is a Draft Statement of Work for the SLV-CB Shop Floor and Apron Repair project. The Bureau of Reclamation, Alamosa Field Division is seeking concrete repair services for their shop floor and aprons. This is a Sources Sought notice to determine potential sources for information and planning purposes only, and no formal solicitation exists at this time. Responses to this notice must be emailed to Ronda Lucero at rlucero@usbr.gov by 4:00 p.m. (MDT) on Thursday, September 5, 2024. Offerors should not provide a proposal in response to this Sources Sought notice.

View the file

Other files

File Type Posted
140R4024Q0064_-_SOURCES_SOUGHT_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SLV Concrete Work

DESCRIPTION/SPECIFICATIONS

(Concrete Work)

1.0 - Introduction The Bureau of Reclamation, Upper Colorado Region, Albuquerque Area Office, Alamosa Field Division (Reclamation) is looking to repair or replace concrete features that have shifted or heaved. Work on the shop floor Contractor shall furnish and install all equipment, controls, materials, and perform required testing. In addition, the Contractor shall verify selections.

1.1 - Abbreviations, Definitions, and Acronyms The Bureau of Reclamation commonly used definitions are listed below:

AAO -Albuquerque Area Office (BOR)
AFD -Alamosa Field Division
BOR -Bureau of Reclamation
CO -Contracting Officer
COR -Contracting Officer’s Representative
CS -Contracting Specialist
FAR -Federal Acquisition Regulation
MDT -Mountain Daylight Time
MRG -Middle Rio Grande
NIBS -National Institute of Building Sciences
OGR -Onsite Government Representative
RSN -Required Submittal Number
SEMS -Sustainability and Environmental Management System (BOR)
UCB -Upper Colorado Basin (Interior Region 7)

1.2 - North American Industry Classification System (NAICS) The NAICS for this work is 238110.

1.3 - Location and Hours of Operations The Reclamation’s facility is located at 10900 Highway 160 East, Alamosa, Colorado 81101 in Alamosa County at Latitude 37º 28’ 22.3” and Longitude 105º 50’ 32.1”. Alamosa Field Division facility is approximately 1.7 miles northeast of downtown Alamosa, Colorado on US Highway 160. Reclamation’s standard business hours are Monday through Friday from 07:30 AM to 4:00 PM MDT except Federal Holidays. Reclamation is a smoke, drug, and alcohol-free facility.

1.3.1 - Facility Access and Deliveries Contractor shall inform the CO and COR a minimum of 5 working days prior to mobilizing personnel, equipment, and materials/supplies to the project site. In addition, if the Contractor would like to have delivery of materials and/or supplies directed shipped to the project site, the Contractor shall notify Ms. Susan Storm and COR a minimum of 3 working days (seventy-two hours) prior to the delivery of materials/supplies. The Contractor shall communicate with Susan the following:

· Provide a detail list of items to be shipped and arrive at the Alamosa Field Division (AFD)

· Provide the shipping company’s name and related information

· Provide estimated day and time the items are to arrive at AFD

Ms. Susan Storm contract information is as follows:

Susan Storm, Facility Manager Bureau of Reclamation Alamosa Field Division 10900 US Highway 160 Alamosa, Colorado 81101

(719) 589-1810 SStorm@usbr.gov

Contractor shall check and maintain all equipment stored at the AFD shall be protected from weather, humidity, temperature variations, dirt, and dust, and/or other contaminants.

1.4 – Site Visit The Government (Reclamation) plans to hold a site visit (walkthrough of the building HVAC systems) for perspective Offerors TBD. The site visit purpose is to provide a complete understanding of the project objectives and scope.

1.5 - Government Furnished Materials Government shall provide if available design data if requested by the Contractor for the purpose of fulfilling the requirements of these specifications.

2.0 - General

2.1 – Background One slab of the shop floor has shifted to the point of creating hazardous walkway. The slab has a vault with stairs that is designed to function as a mechanic service walkway. This vault has shifted to the point it may affect stability. The outside walkways have deteriorated due to insufficient drainage and water damage. There is also a section that has heaved outside the main door which limits the door from opening fully.

2.2 – Purpose The east foundation slab in the shop has lifted and cracked around the concrete vault/vehicle maintenance pit in the middle of the slab. It appears that freeze-thaw from moisture under the slab is the cause of the lifting. The issue at the shop slab appears to be indicative of a wider drainage issue in the area of the Alamosa shop building. The Alamosa office and shop building area appears to be at a lower elevation than the surrounding land, which causes runoff to flow to and pond at various spots on the property.

2.3 - Scope The slab on the right side of the Alamosa shop building needs to be removed and replaced, an estimated 800-ft2 area and 18-inch-thick slab. The vault in the middle of the slab can either be removed or left in place; either way the open space would be filled and compacted. The vault dimensions are 26.25 ft. long x 3.4 ft. wide x 5.2 ft. deep (464 ft3). To prevent future moisture accumulation that could lead to another damaging freeze-thaw effect, a subsurface drain to draw water away from the shop foundation could be installed. Also recommended is to improve the overall drainage scheme of the paved areas around the shop building. This could include removing the drain at the disused wash bay and paving it over and repaving other areas so that runoff flows away from high traffic areas where it could otherwise freeze over and become a hazard. There are existing drains in the gravel parking lot area that the new drainage scheme can flow to. The heaving area outside the north entrance of the shop will need to be removed and replaced. The perimeter sidewalks will need to be repaired or replaced along with deteriorating sidewalk aprons.

The following Photographs are provided for as reference only.

1. Shop Slab

1a.

Shows vault location in east bay of shop.

The vault dimensions are 26.25 long x 3.4” inches wide x 5.2” deep, (464 ft3).

1b.

Shows settling and damage around vault, separation between edge of vault and the slab.

1c.

Looking from the left slab towards the right slab, showing the separation between the two slabs.

2. Wash Bay

2a.

Water accumulated at the disused wash bay.

3. Walkway near north door of shop

3a.

Shows the cement walkway with heaving near the door to the shop. The shop door will only open to ~45 degrees due to raised area.

Dimensions of area to be replaced are ~8 ft. by 13.5 ft. (110 ft2).

3b.

Shows damaged walkway with heaving near the door to the shop.

4. Perimeter sidewalk

4a.

Shows perimeter walkway with crumbling aprons and damage.

Section of east perimeter sidewalk requiring apron replacement is ~150 ft in length.

4a.

Shows section of perimeter walkway with heaving area near main office building.

Area ~30 ft x 5 ft (150 ft2)

2.4 – Submittals The contractor shall submit the following for Government review and approval:

· Prepare in English.

· Measurement Units: US Customary Units.

· Label with contract number and title including Required Submittal Number (RSN).

· Provide a unique transmittal tracking number for each submittal.

· Required certifications shall be performed by a registered professional.

· Manufacturer’s certifications shall be signed by authorized representative.

· Product data that represents more than one items shall be highlighted to show model, size, features, optional, etc. to be supplied under these specifications.

· Review of submittals:

· Time required: The Government will require a minimum of 21 calendar days to review and/or approve each submittal or resubmittal, unless otherwise specified.

· Excess Time: Should the Government require additional time for review, the Contracting Officer may extend the contract completion date to allow completion of work. Time extension will be to the extent that the excess review time caused delay to contract completion.

· Submit the following for Government review and approval:

· Submittal Types:

· A – Action requiring Government approval

· I – Informational requires Government review and written receipt

· Submit electronic copies for review and approval to Susan Storm at sstorm@usbr.gov.

Submittal Table

RSN
Required Submittal and Description
Due Date or Delivery Time
Type
S1
Project Schedule (Original) and (Revisions) include key elements such as mobilization, demolition, installation, punch list items, and substantial completion
Within 14 days after contract award provide (Original) schedule. Submit (Revised) schedule(s) if any dates change more than 5 working days
A
S2
Submit site specific Contractor’s Safety Plan and Job Hazard Analysis (JHAs)
A minimum of 7 Days prior to mobilization
A
S3
Submit methods and practices for removing and disposal of existing concrete including safety plan for preventing accidental access.
Within 7 days prior to performance of work activities/tasks
A
S4
Submit list of recycled equipment, materials, supplies used per SEMS.
Within 7 days prior to performance of work activities/tasks
I
S5
Submit installation methods, practices, and layout plan for new concrete/structures.
Within 7 days prior to performance of work activities/tasks
A
S6
Submit As-Built drawings for changes in 34” x 22” standard bond paper and AutoCAD electronic formats
A minimum of 21 days prior to sending final payment
A

Reclamation’s Sustainability and Environmental Management System (SEMS) requires that construction contract(s) use recycled materials as defined by EPA’s Green Procurement Program for Recovered Materials. For questions on whether the product counts as "EPA-designated" or what the required recycled content is, refer to product descriptions on EPA's website at https://archive.epa.gov/epawaste/conserve/smm/wastewise/web/html/buyman.html.

3.0 - Reference Standards These standards are part of the specifications:

American Concrete Institute (ACI) 318

ASTM International – ASTM C94, ASTM C150/C150M, ASTM C618, ASTM C989/C989M

International Existing Building Code

Reclamation Safety and Health Standards (RSHS):

· RSHS-2014Section 3 - Contractor Requirements
· RSHS-2014Section 8 - Personal Protective Equipment (PPE)
· RSHS-2014Appendix C - Electrical Grounding

4.0 - General Requirements Contractor and Government personnel shall interact and communicate with professional and respect throughout the contract processes. The Contractor shall use good housekeeping practices and cleanup all work areas at completion of a workday. All discarded materials, debris, and trash shall be contained and removed from the project site at a minimum weekly and disposed of according to local requirements. Contractor shall remove all equipment and materials not required to meet the requirements of this specifications within 48 hours from the construction site.

Contractor is responsible for the security of all equipment and materials on site. In addition, all material shipments, transportation, and storage are the responsibility of the Contractor. Unless arrangements are made with the AFD Manager to provide access for shipments to be delivered.

All design work and equipment selection shall be in accordance with the Department of the Interior's Guiding Principles for Existing Buildings (Appendix 1).

Qualifications: Contractors, subcontractors, manufacturers, and suppliers shall have minimum of three years experience in concrete construction.

The new concrete shall have the following intrinsic characteristics:

· All changes to existing or new wiring, conduits, and connectors shall be according 2015 NEC and be performed by a state licensed electrician.

· All installations shall provide for a neat and acceptable appearance.

· Contactor, Subcontractors, and Reclamation shall participate in project meetings as required to develop, track, and maintain project schedules.

· The Contractor shall consult with Reclamation to address impacts to existing utilities prior to removal and/or construction.

4.1 – East Bay of Shop Building Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site

· Remove original slab and repair or remove vault area.

· Pour new slab.

4.1.1 - Existing Site Conditions The Contractor shall prior to ordering supplies verify the following existing site requirements:

· Government furnished drawings are for “Reference Only” and all plans are approximations.

· Offeror shall document existing features:

· If required, include recommendations requiring changes, upgrades, or other related improvements to support new concrete features.

· Offeror can submit changes and/or modifications to the existing footprint to the Government for review and written approval of such changes/modification.

4.2 – Outdoor Washbay Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site

· Remove original slab and repair or remove filled in drain to prevent water infiltration.

· Grade shall provide for drainage away from the building or to proper drains.

· Pour new slab.

4.3 – Walkway Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site

· Remove original slab.

· Grade shall provide for drainage away from the building or to proper drains.

· Pour new slab.

4.4 – Perimeter Sidewalks Prepare area for concrete accordance with these specifications, standards, and industry best practices. The following is a short, bulleted list of activities:

· Concrete removed shall be recycled or disposed of accordingly to local requirements off site.

· Remove original deteriorated aprons and damaged sections of sidewalk.

· Construct new aprons and repair/replace walkways.

5.0 – As-Built Drawings The following bullets describes the requirements for providing As-Built drawings for this project:

· Drawing shall indicate location of existing piping or electrical service, grade, and drainage.

· Drawing shall indicate location of grade and dimensions of concrete features at each state of work.

· Drawing shall include section and elevation views as required.

· Submit final electronic files for As-Built drawings by approved format such as CD, DVD, or thumb-drive, web base applications.

If required by the Offeror, the Government can supply electronic AutoCAD format template.

6.0 – Security and Safety This section describes the security and safety requirements for this Reclamation facility. The following sub-sections provide additional details for various considerations on this effort.

6.1 - Security The contractor shall not access any sensitive areas without escort from Reclamation personnel.

6.1.1 – Facility Security Agreement The contractor shall sign a Facility Security Agreement which outlines the Contractor’s and the Government’s responsibilities in the following areas:

· Drafting, coordinating Government reviews, finalizing, and maintaining the Facility Security Agreement

· Standard Procedures for accessing sensitive or restrictive areas

· Contractor security supervision

· Contractor’s accountability in training and managing personnel that will be accessing sensitive or restrictive areas

· Accountability of issued Identification

· Emergency protection

· Protection of government resources

6.2 - Safety Contractor and its subcontractors shall comply and incorporate into their safety and health programs/plans the following safety requirements:

· Occupational Safety and Health Administration (OSHA) Part 1926 Construction.

· Reclamation Safety and Health Standards (RSHS) which can be found at the following website: https://www.usbr.gov/ssle/safety/RSHS/rshs.html.

The contractor and its subcontractors (if applicable) shall promptly report all facts regarding accidents, near miss(es), emergencies, and/or mishaps involving Government property damage or injury to Government personnel and to cooperate in any resulting safety investigation.

The contractor shall notify the Contracting Officer’s Representative and Contracting Officer by one of the following methods: in person, by telephone, and/or by email within four (4) hours of all incidents. Reclamation’s personnel will notify Reclamation’s Safety and Health office. The contractor shall immediately secure the incident area and any damaged property. If requested by Reclamation Safety and Health office, the Contractor shall submit all pertinent maintenance and training records for equipment or personnel involved in the safety incident(s). If the Government investigates the safety incident, the contractor and the subcontractors shall cooperate fully and assist the Government personnel with the investigation.

7.0 – Provided to Offeror

7.1 – Point of Contact The following key Government personnel are:

Contract Specialist:Ronda Lucero (UC-871)
Bureau of Reclamation
555 Broadway NE, Suite 100
Albuquerque, NM 87101-2352
Phone No.: (801) 524-3691
Email: rlucero@usbr.gov
Contracting Officer:Mary B. Maestas (ALB-865)
Bureau of Reclamation
555 Broadway NE, Suite 100
Albuquerque, NM 87101-2352
Phone No.: (505) 462-3581
Email: mmaestas@usbr.gov
Contracting Officer’s Representative:Susan Storm, Facility Manager(AFD-400)
Bureau of Reclamation
10900 US HWY 160 E
Alamosa, Colorado 81101
Phone No.: (719) 589-1810
Email: sstorm@usbr.gov
Technical Representative:Frank Espinoza, Maintenance Supervisor (AFD-426)
Bureau of Reclamation
10900 US HWY 160 E
Alamosa, Colorado 81101
Phone No.: (719) 588-7114
Email: despinoza@usbr.gov

7.2 – Government provided Utilities The Government will make available electricity and water for construction activities. The use of water closet(s) will be at the discretion of the AFD Manager. If use of the water closet (bathroom) is not allowed the Contractor shall provide a portable toilet for its employees use.

image2.emf image3.emf image4.emf image5.png image6.png image7.png image8.png image1.png