SLR RAS Specs Compiled.pdf
PDF 7 MB Posted
- Solicitation number
- 909197325722
- Issued by
- San Diego County, California
About this file
The document is a comprehensive technical specification prepared by the City of Oceanside, California, for the San Luis Rey Water Reclamation Facility RAS (Return Activated Sludge) Pipe Replacement Project. The project involves replacing approximately 130 linear feet of existing steel piping, including 18-inch, 12-inch, 10-inch, and 8-inch pipes, with associated steel wyes and reconnections. The work encompasses field welding, coating, scaffolding installation, crane or alternative lift system operation, valve and appurtenance installation, removal and replacement of conflicting process pipe, and site restoration. The project is located at the San Luis Rey Reclamation Facility at 3950 N River Rd, Oceanside, CA 92058, with a targeted completion date of April 1, 2025.
The technical specifications outline detailed requirements for pipe materials, installation methods, testing, and quality control, with a total project approach emphasizing minimal disruption to existing facility operations. The contract includes specific constraints, such as limiting return activated sludge pump shutdowns to no more than two hours, with up to four of eight pumps allowed to remain in service during construction. The project will be competitively bid, with contractors required to submit comprehensive documentation including detailed sequencing plans, bypass pumping strategies, and safety protocols. While specific budget details are not explicitly stated, the specifications suggest a complex infrastructure upgrade with multiple technical and operational considerations, requiring specialized expertise in municipal water reclamation facility pipe replacement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
FOR THE CONSTRUCTION OF
SAN LUIS REY WATER RECLAMATION FACILITY
RAS PIPE REPLACEMENT PROJECT
909197325722
April 1, 2025
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
SECTION
NUMBER TITLE
CITY OF OCEANSIDE TOC - 1
SLRWRF RAS PIPE REPLACEMENT SPECIFICATION TABLE OF CONTENTS
DIVISION 1 GENERAL REQUIREMENTS
01001 Standard Drawings, Standard Specifications and Approved Materials List 01010 Summary of Work 01025 Measurement and Payment 01039 Coordination and Meetings 01048 Special Construction Conditions & Procedures 01090 Reference Standards 01300 Record Drawings and Submittals 01310 Construction Progress Schedules 01370 Schedule of Values 01380 Pre-Construction Video Recording and Photographs 01400 Quality Control 01500 Construction Facilities and Temporary Controls 01545 Protection of Work and Property 01600 Materials and Equipment 01630 Product Options and Substitutions 01700 Project Closeout 01710 Clean-Up
DIVISION 2 SITEWORK
02960 Temporary Bypass Pumping
DIVISION 9 FINISHES
09800 Painting and Coating
DIVISION 15 MECHANICAL
15000 General Piping Systems and Appurtenances 15061 Steel Piping 15100 Valves – General 15101 Valve and Gate Operators
15103 Plug Valves 15292 Polyvinyl Chloride (PVC) Pressure Pipe
SECTION 01001 – STANDARD DRAWINGS, STANDARD SPECIFICATIONS
AND APPROVED MATERIALS LIST
CITY OF OCEANSIDE 01001 - 1
SLRWRF RAS PIPE REPLACEMENT STANDARD DRAWINGS, STANDARD SPECIFICATIONS
PART 1 – GENERAL
1.1 STANDARD SPECIFICATIONS AND STANDARD DRAWINGS
A. Standard Specifications, Standard Drawings, Procedures, and Approved Materials Lists shall be as described in these specifications and the City of Oceanside Engineers Design and Processing Manual (Engineers Manual) and the City of Oceanside Water Utilities Department Water, Sewer, and Recycled Water Design and Construction Manual (Water Utilities Manual). Where the Engineers Manual and the Water Utilities Manual reference the same item, material, procedure, or specification, the Water Utilities Manual shall take precedence.
B. The Water Utilities Manual can be found at https://www.ci.oceanside.ca.us/government/water-utilities/administration/design-and-construction-manual
C. The Engineers Manual can be found at:
https://www.ci.oceanside.ca.us/government/development-services/engineering/engineering-manuals/engineering-design-manual
1.2 REFERENCE STANDARDS
A. Standards listed as “Reference Standards” in the various sections of these contract documents are hereby incorporated into this specification by reference.
B. Reference documents shall include all revisions, amendments, supplements or addenda issued on or before the date of advertising for bids.
C. The City of Oceanside Standard Specifications and Standard Drawings are incorporated into these contract documents by their reference herein and will be enforced unless superseded by the project specifications or specific details of the contract documents.
1.3 APPROVED MATERIALS LIST
A. All the material used on this project, shall be in accordance with items listed in these specifications or as indicated in the Engineers Manual and Water Utilities Manual.
The use of the following materials shall refer to the Water Utilities Manual: Fire Hydrants; Blow-off Valves; Air Release Valves; Pipe, Fitting, Valve, and Nut and Bolt Material and Protection; Hydraulic Valves; Water Services to House and Commercial Connections; Service Saddles; Ductile Iron Pipe Water Mains; Polyvinyl Chloride Pipe Water Mains; Bedding and Backfill; Valves under 14”; Butterfly Valves; Standard Vault; Vault Lids; Valve Box, Cover, and Can; Valve Stem Extension; Ductile Iron Fittings; Flanges; and Flange Gaskets. Where materials
SECTION 01001 – STANDARD DRAWINGS, STANDARD SPECIFICATIONS
CITY OF OCEANSIDE 01001 - 2
SLRWRF RAS PIPE REPLACEMENT STANDARD DRAWINGS, STANDARD SPECIFICATIONS
AND APPROVED MATERIALS LIST
specified in the Engineers Manual conflict with materials specified in the Water Utilities Manual, the Water Utilities Manual shall take precedence.
B. Materials not listed in these specifications must be submitted for the AGENCY’S approval and must be accepted for use on this project prior to contract award.
PART 2 – MATERIALS (NOT USED)
PART 3 – EXECUTION (NOT USED)
**END OF SECTION**
SECTION 01010 – SUMMARY OF WORK
CITY OF OCEANSIDE 01010 - 1
SLRWRF RAS PIPE REPLACEMENT SUMMARY OF WORK
1.1 WORK OF THIS SECTION
A. The work to be performed under this Contract shall consist of furnishing all tools, equipment, materials, supplies, and manufactured articles and furnishing all labor, transportation and services, including fuel, power, water, and essential communications, and performing all work, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The work shall be complete, and all work, materials, and services not expressly indicated or called for in the Contract Documents which may be necessary for the complete and proper construction of the work in good faith shall be provided by the CONTRACTOR as though originally so indicated, at no increase in cost to the AGENCY.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. The work under this contract includes, but is not necessarily limited to:
1. Obtaining and complying with all required permits.
2. Preparation of a Storm Water Pollution Control Plan for soil disturbance under 1 acre and furnishing, installation, and maintenance of temporary storm water pollution prevention measures in accordance with the Contract Documents.
3. Field verification of all pipe material and dimensions prior to ordering products and materials.
4. Furnish and install all scaffolding as needed in accordance with the rules, orders and regulations of CAL-OSHA/OSHA.
5. Installation of Wastewater Bypass per the requirements of Specification 02960 and the Contract Documents.
6. Coordination with the AGENCY for shutdown of existing process piping as detailed in this specification.
7. Provide crane and/or boom truck or winching system as needed for steel pipe removal and install per rules, orders and regulations of CAL-OSHA/OSHA. Provide lift plan prepared by qualified person.
8. Remove existing abandoned water pipe, and temporarily remove and replace existing PVC water pipe as needed for construction.
9. Protect in place existing air process pipe, or remove and reinstall per contract drawings.
10. Install tee/valve assembly structural support per plans.
11. Remove approximately 130 feet of existing steel pipe and install approximately: 20 linear feet of 18-inch pipe with two 8-inch wyes; 60 feet of 12-inch pipe with two 8-inch wyes; 20 feet of 10-inch pipe with one 8-inch wye, and; 20 feet of 8-inch pipe with one 8-inch wye.
Replace all Victaulic fittings at new pipe joints and at existing pipe and wye connections. Install new 12-inch tees and plug valves. Install bend fittings and reducers as required.
CITY OF OCEANSIDE 01010 - 2
12. Completion of connections to existing system.
13. Pre- and post-construction photography of work sites.
14. Restoration of all impacted sites to original condition.
15. Preparation of final project redlines.
1.3 PROJECT LOCATION
A. The project is located in the City of Oceanside at the San Luis Rey
Reclamation Facility, 3950 N River Rd, Oceanside, CA 92058.
1.4 CONTRACTOR’S USE OF THE PROJECT SITE
A. The CONTRACTOR’s use of the project site shall be limited to its construction operations. On-site storage of materials, on-site fabrication facilities, and field offices located within public right-of-way require approval from the AGENCY.
B. The CONTRACTOR shall install signs, barricades and lights necessary to ensure public safety and safety of AGENCY’s operators and personnel.
Provide plates across ditches to enable safe access of AGENCY’s personnel to facilities or the public across excavations within public right-of-way that cannot be backfilled at the end of the day. Traffic control during hours of construction work shall be in accordance with the AGENCY approved traffic control plans included in this bid package.
1.5 AGENCY’S USE OF THE PROJECT SITE
A. CONTRACTOR shall comply with Section 7.14 of the General Provisions.
B. The AGENCY may utilize all or part of the existing site during the entire period of construction. The Contractor shall cooperate and coordinate with the AGENCY and the AGENCY REPRESENTATIVE to facilitate the AGENCY’S operations and to minimize interference with the CONTRACTOR’S operations at the same time. In any event, the AGENCY shall be allowed access to the project site during the period of construction.
1.6 WORK BY OTHERS
A. Interference with work on utilities: The CONTRACTOR shall cooperate fully with all utility forces of the AGENCY or forces of other public or private agencies engaged in the relocation, altering, or otherwise rearranging of utilities which interfere with the progress of work by others, and shall schedule the work so as to minimize interference with said relocation, altering, or other rearranging of facilities.
1.7 PIPELINE SHUTDOWNS AND COORDINATION WITH THE AGENCY
See Section 01043
CITY OF OCEANSIDE 01010 - 3
1.8 WORK SEQUENCE AND CONSTRAINTS
A. The CONTRACTOR shall prepare a Sequence of Work and Outage Plan for the AGENCY’S review and approval, within 10 days of issuance of Notice to Proceed. The Sequence of Work shall comply with the requirements in Section 01043 and shall include, at minimum, the following:
1. Contractor to submit pipeline replacement plan to the AGENCY for approval. The replacement plan shall include detailed sequencing and phasing of all pipe replacements, and include the following consideration:
The existing return activated sludge (RAS) pumps that discharge to the steel main replacement cannot be shut down for longer than two hours. Up to four of the 8 pumps may be in service at once. All pipe replacement work must be phased to incorporate this restriction.
2. Contractor to submit wastewater bypass pumping plan for AGENCY approval per the contract document requirements
3. Contractor to build all scaffolding and temporary supports as required for pipe access. Contractor to take measurements of existing 18-inch, 12-inch, 10-inch, and 8-inch pipe for total length, outside diameter, horizonal bend dimensions, and all wye fitting dimensions.
Contractor to submit dimensions to AGENCY for review prior to ordering steel pipe and materials.
4. Contractor to coordinate with Agency for shutdown of RAS pumps and draining of RAS pipe per the approved pipeline replacement plan.
5. Contractor to install tee and valve assembly near STA 85+00 and resume operation of pumps 5 through 8.
6. Contractor to perform all work between STA 2+00 and the new tee and valve assembly near STA 85+00.
7. Contractor to place pipe into normal service operations and confirm functionality of system with pumps 1 through 4 running.
8. Contractor to install, test, and operate wastewater bypass system with pumps 5 through 8 isolated.
9. Contractor to perform all work between STA 0+00 and the new tee and valve assembly near STA 85+00.
10. Contractor to replace and/or reinstall all removed process piping as required in contract drawings. Demobilize and restore site to previous conditions.
SECTION 01025 – MEASUREMENT AND PAYMENT
CITY OF OCEANSIDE 01025-1
SLRWRF RAS PIPE REPLACEMENT MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 DESCRIPTION
Measurement and payment for bid items listed in the proposal shall be based upon use of a lump sum or unit price method. Extra work or changes in the work shall be accomplished as provided in the General Provisions.
1.2 RELATED WORK SPECIFIED ELSEWHERE
A. The Work of the following Sections applies to the Work of this Section. Work of other Sections of the Specification, not referenced below, shall also apply to the extent required for proper performance of this Work.
1. General Conditions
2. Section 01010, Summary of Work
3. Section 01300, Submittals
1.3 PAYMENT
A. Payment for Unit Price Items
Payment for a unit price bid item shall be based upon the amount shown in the Bid Schedule multiplied by the total quantity measurement of the item and shall be full compensation for furnishing all labor, transportation, materials, equipment, tools, appurtenances and incidentals required for construction of the item complete in place in accordance with the Plans and Specifications.
B. Payment for Lump Sum Items
Payment for lump sum bid items shall be based upon the amount shown in the Bid Schedule and shall be full compensation for furnishing all labor, transportation, materials, equipment, tools, appurtenances and incidentals required for construction of the unit complete in place in accordance with the Plans and Specifications. Progress Payment will be based upon measurement of work completed as described in Section 2.6 of this specification. Contractor to provide Schedule of Values sufficient to determine progress of lump sum bid items.
C. Work Not Listed in the Bid Schedule
Costs for related work and appurtenances which are required and/or implied by the General Provisions, Technical Specifications, Special Technical Provisions and Plans and are not listed as a separate bid item but are necessary to complete the project shall be included in the appropriate bid item or items within the proposal.
CITY OF OCEANSIDE 01025-2
SLRWRF RAS PIPE REPLACEMENT MEASUREMENT AND PAYMENT
1.4 MEASUREMENT AND PAYMENT OF BID ITEMS
A. Bid Item A1: Mobilization and Demobilization
1. Description of Work: Mobilization includes (1) Processing and obtaining all permits. All permit fees will be borne by the CONTACTOR; (2) Obtaining insurance and bonds necessary for performing the work; (3) Furnishing all labor, equipment, material and supplies for the execution of the work but which are not to be incorporated in the various items of work; (4) Construction of temporary yards, development of disposal areas, recycling implementation and other construction facilities; (5) Obtaining temporary construction water meters; (6) Maintaining and submitting project record drawings Demobilization includes: (1) Removal of all temporary facilities, equipment, material and supplies from the site. (2) Clean up and removal of all construction debris. (3) Contract closeout.
2. Payment: The lump sum payment for Mobilization, Bonding, and
Insurance shall not exceed 6% of the total bid amount and shall be made in two (2) separate payment requests. The first shall be made with the first payment request, and the second shall be made with the last and final request after 100% of the work is completed. Mobilization shall constitute up to 4% of the total bid amount and demobilization shall constitute up to the remaining 2% of the total bid amount.
Payments for mobilization and demobilization shall be made as shown in the Bid Schedule and no additional payment shall be made thereafter.
B. Bid Item A2: Water Pollution Control
1. Description of Work: The CONTRACTOR shall be responsible for preparing a Water Pollution Control Plan/Storm Water Pollution Prevention plan and implementing, maintaining and operating temporary storm water pollution prevention measures through construction, in accordance with State Regional Water Quality Control Board (SRWQCB) and City of Oceanside requirements and the Contract Documents. No filing of a NOI or SWPPP to the SRWQCB is required for this project.
2. Payment: The payment for work under this bid item shall be based on a lump sum price and shall include all labor materials, equipment, and other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated for in the lump sum price and no additional compensation shall be made
C. Bid Item A3: Pre-construction Video and Photographs
1. Description of Work: This work includes furnishing all labor, material, tools and equipment, and performing all work required for preconstruction video and photographs and all other work necessary to
CITY OF OCEANSIDE 01025-3
complete this item of work as described in the Contract Documents.
a lump sum price and shall include all labor, materials, equipment, and other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated
D. Bid Item A4: Scaffolding Erection Plan and Installation
1. Description of Work: The CONTRACTOR shall be responsible for all scaffolding (or equivalent method) and temporary construction support safety measures as needed by the CONTRACTOR for the protection of life and limb in construction operations and shall be in conformance with OSHA and CAL-OSHA, complete, all in accordance with the Contract Documents. CONTRACTOR shall submit scaffolding plan with general layout, location and size for AGENCY approval.
CONTRACTOR is responsible to have plan review and approved by registered structural engineer. The bid item shall also include obtaining any required permit from the State Division of Industrial Safety.
other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated
E. Bid Item A5: Crane/Boom Truck Lift Plan, Equipment and Operation
1. Description of Work: The CONTRACTOR shall be responsible for preparing and implementing a crane (or alternative method) lift plan as needed by the CONTRACTOR for construction operations and shall be in conformance with OSHA and CAL-OSHA, complete, all in accordance with the Contract Documents. CONTRACTOR shall submit lift plan with general layout, location, size, detailed sequence of events, and all design calculations for lift angle, length, load weight, etc. for AGENCY acceptance of conformance. CONTRACTOR is responsible to have plan prepared and reviewed by qualified person. The bid item shall also include obtaining any required permit from the State Division of Industrial Safety.
other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated
F. Bid Item A6: Furnish and Install RAS Bypass
CITY OF OCEANSIDE 01025-4
1. Description of Work: This work consists of temporarily bypassing the return activated sludge pipe per the contract document requirements to maintain the system during construction. The contractor shall be responsible for providing all necessary materials, installing and securing temporary piping, testing for leaks, maintaining the system during construction, and restoring original connections upon project completion, including repairing any damage caused during the process.
This work also includes preparation of a bypass plan for AGENCY approval.
other incidentals required. All work shall be considered as compensated for in the lump sum price and no additional compensation shall be made thereafter.
G. Bid Item A7: Remove and Reinstall Air Pipe
1. Description of Work: This work consists of removing and replacing all steel air pipe per the contract drawings; all steel pipe welding; third party certified steel pipe welding inspection; repairing linings and coatings; and all incidental work, in accordance with the Contract Documents.
other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated
H. Bid Item A8: Remove and Replace Steel Pipe
1. Description of Work: This work consists of coordination with AGENCY staff; shutting down and draining steel pipe; removal and disposal of existing steel pipe and PVC pipe in conflict per the contract documents;
protection in place or removal and replacement of existing PVC pipe to remain; removal and replacement of existing fittings and specials;
removal and replacement of steel wye fittings; removal and replacement of steel strap pipe supports; installation of new steel pipe per the contract document requirements; repair of coatings and linings as required; removal and replacement of steel walkways; and all incidental work, in accordance with the Contract Documents.
other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated
CITY OF OCEANSIDE 01025-5
I. Bid Item A9: Furnish and Install Valve Assembly STA 0+85
1. Description of Work: This work includes all labor, supervision, materials, and equipment purchased, installed and utilized for furnishing and installing the valve assembly per the contract drawings, complete and in place in full compliance with the Contract Documents.
This assembly includes the 12-inch steel tee, two 12-inch plug valves, and blind flange. This work also includes the valve assembly structural support installation.
other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated
J. Bid Item A10: Furnish and Install Valve Assembly STA 0+00
1. Description of Work: This work includes all labor, supervision, materials, and equipment purchased, installed and utilized for furnishing and installing the valve assembly per the contract drawings, complete and in place in full compliance with the Contract Documents.
This assembly includes the 12-inch steel tee, one 12-inch plug valve, and blind flange, and 12-inch steel pipe spools. This work also includes the valve assembly pipe support installation.
other incidentals required, as shown on the approved plans or called for in the specifications. All work shall be considered as compensated
PART 2 - MATERIALS
2.1 GENERAL (MEASUREMENT)
Measurement for unit price quantities shall be based upon the appropriate bid item in the proposal. The actual quantity of measurement shall be as constructed by the CONTRACTOR in place in conformance with the Plans and Specifications.
2.2 LINEAR MEASUREMENTS
Pipeline and related facility measurements shall be made horizontally along the centerline of the pipeline and related facilities through tees, bends, valves, fittings, and as shown on the Plans for its limits or as otherwise specified in the Special Technical Provisions. Manholes and vaults shall be measured vertically from the lowest to the highest elevations and as shown on the Plans or as otherwise specified in the Special
CITY OF OCEANSIDE 01025-6
Technical Provisions.
2.3 AREA MEASUREMENTS
Measurement for bid items involving area units shall be based upon the surface area measured in acres, square yards, square feet, or as indicated in the bid item.
2.4 VOLUME MEASUREMENTS
Measurement for bid items involving volume units shall be based upon the volume measured in cubic yards, tons, or as indicated in the bid item.
2.5 UNIT MEASUREMENTS
Measurement for bid items involving units of the item shall be based upon the number of units counted as indicated in the bid item.
2.6 LUMP SUM MEASUREMENT
All lump sum items section will be broken out as described in the CONTRACTOR'S Schedule of Values, as approved by the AGENCY.
PART 3 - EXECUTION
3.1 GENERAL
A. This section covers methods of measurement and payment for items of work under this Contract. The total Bid Price shall cover all work required by the Contract Documents. All costs in connection with the proper and successful completion of the work, including furnishing all materials, equipment, supplies, and appurtenances; providing all construction plant, equipment, and tools; and performing all necessary labor and supervision to fully complete the work, shall be included in the unit and lump sum prices bid. All work not specifically set forth as a pay item in the Bid Form shall be considered a subsidiary obligation of CONTRACTOR and all costs in connection therewith shall be included in the prices bid.
3.2 ESTIMATED QUANTITIES
A. All estimated quantities stipulated in the Bid Form or other Contract Documents are approximate and are to be used only (a) as a basis for estimation the probable cost of the work and (b) for the purpose of comparing the bids submitted for the work. The actual amounts of work done and materials furnished under unit price items may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work done and materials furnished.
CONTRACTOR agrees that he will make no claim for damages, anticipated profits, or otherwise on account of any difference between the amounts of work actually performed and materials actually furnished and the estimated amounts therefor.
SECTION 01039 – COORDINATION AND MEETINGS
CITY OF OCEANSIDE 01039 - 1
SLRWRF RAS PIPE REPLACEMENT COORDINATION AND MEETINGS
A. This section specifies the methods and requirements of coordination and meetings required for project coordination. This includes coordination with AGENCY, Federal, State and Local authorities, utilities, neighboring property owners, special events, and other contractors.
A. Section 01043 – Coordination with AGENCY’S Operations
B. Section 01047 – Connections to Existing Facilities
C. Section 01060 – Permits & Other Regulatory Requirements
D. Section 01048 – Special Construction Conditions and Procedures
1.3 COORDINATION AND PROJECT CONDITIONS
A. CONTRACTOR shall coordinate scheduling, submittals, and work of the various sections of the Project to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later. CONTRACTOR shall be required to coordinate with AGENCY through project management software platform as specified by AGENCY during the pre-construction meeting.
1.4 PRECONSTRUCTION MEETING
A. AGENCY will schedule a Preconstruction meeting after Notice of Award and before the Notice to Proceed, per Section 4, Notice of Award.
B. Attendance Required:
AGENCY: Project Manager, Design Engineer, Construction Manager, and Inspector
CONTRACTOR: Superintendent, Foreman, and Representatives from Subcontractors
C. The AGENCY will distribute an agenda including, but not limited to the following items:
1. Distribution of Contract Documents.
2. Designation of personnel representing the parties in Contract.
3. Submission of list of Subcontractors.
4. Review of proposed Critical Path Method (CPM) Construction Schedule, Schedule of Values, and delivery dates.
5. Procedures for inspection of work.
CITY OF OCEANSIDE 01039 - 2
SLRWRF RAS PIPE REPLACEMENT COORDINATION AND MEETINGS
6. Procedures and processing for:
a. Substitutions
b. Submittals
c. RFI’s
d. PCO’s
e. Field decisions
7. Payment requests.
8. Change Orders.
9. Procedures for testing.
10. Procedures for maintaining record documents.
11. SWPPP/NPDES General Permit for Storm Water Discharges Associated with Construction Activity
12. Traffic Control Permit
13. Property Owner Notification / Community Outreach
14. Contract closeout procedures.
D. AGENCY shall record minutes and distribute copies within five working days after meeting to participants and those affected by decisions made.
1.5 PROGRESS MEETINGS
A. AGENCY shall schedule and administer meetings throughout progress of the work at the discretion of the City Inspector.
B. AGENCY will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.
C. Attendance Required:
AGENCY: Inspector.
CONTRACTOR: Job superintendent, major Subcontractors and suppliers, and as appropriate to agenda topics for each meeting.
D. The scheduled progress meetings will include, but is not limited to the following agenda items:
1. Review minutes of previous meetings.
2. Review of work progress.
3. Field observations, problems, and decisions.
4. Identification of problems which impede planned progress.
5. Review of submittals schedule and status of submittals.
6. Review of RFI’s.
7. Review of PCO’s
8. Review of off-site fabrication and delivery schedules.
9. Maintenance of progress schedule.
10. Corrective measures.
11. Planned progress during succeeding work period.
12. Coordination of projected progress.
13. Maintenance of quality and work standards.
14. Effect of proposed changes on progress schedule and coordination.
CITY OF OCEANSIDE 01039 - 3
SLRWRF RAS PIPE REPLACEMENT COORDINATION AND MEETINGS
15. Other business relating to work.
E. AGENCY will record minutes and distribute copies within two working days after meeting to participants and those affected by decisions made.
F. Formal progress meeting shall include all items of typical progress meetings, and the following in addition:
1. Review of Record Drawings (Red Lines)
2. Schedule (2 copies)
1.6 COORDINATION WITH CITY OF OCEANSIDE
A. Contact City of Oceanside Water Utilities Department 72 hours before start of construction at the following location:
CITY OF OCEANSIDE
Water Utilities Department 300 North Coast Highway Oceanside, CA 92054
Mr. Neil Irani (Project Manager) 760-435-5831
B. Do not begin work until CONTRACTOR’s schedule, permits, bonds, certificates of insurance and business license have been reviewed and approved by the
AGENCY.
C. Coordinate with City of Oceanside Water Utilities Department regarding shutdowns or connections to existing facilities.
1.7 COORDINATION WITH UTILITIES
A. Protect existing underground utilities. The CONTRACTOR shall coordinate with all utilities affected by the project to mark-out their locations for potholing and notify utilities of progress during construction so utility field personnel are available when required.
B. Support or relocation of existing Utility Company facilities to accommodate
CONTRACTOR’s means and methods of conducting the work shall be coordinated directly with the Utility Company. All costs associated with support or relocation shall be borne by the CONTRACTOR.
C. Utility companies including but not limited to SDG&E, SBC, AT&T and Cox
Communications may maintain energized aerial electrical power lines in the immediate vicinity of work. Do not consider these lines to be insulated.
Construction personnel working near these lines are exposed to an extreme hazard from electric shock. CONTRACTORs, their employees and construction personnel working on this project must be warned of the danger and instructed to take adequate protective measures, including maintaining a minimum 10 feet clearance between lines and construction equipment and personnel (See OSHA
CITY OF OCEANSIDE 01039 - 4
SLRWRF RAS PIPE REPLACEMENT COORDINATION AND MEETINGS
requirements). As an additional safety precaution, call electric utility company to arrange, if possible, to have these lines de-energized or relocated when work reaches their immediate vicinity. Cost of such temporary arrangements shall be borne by CONTRACTOR.
D. CONTRACTOR shall coordinate with the local utilities to arrange for standby when working within five (5) feet horizontally of any high pressure gas line aligned within the project limits.
E. All demolition, removal or abandonment of existing facilities or portions there of shall be coordinated and performed by the CONTRACTOR. All costs associated with abandonment, removal or demolition shall be borne by the CONTRACTOR.
1.8 COORDINATION WITH PROPERTY OWNERS
A. Coordinate construction with property owners adjacent to the project limits, especially with regard to any limitations with access to their property.
SECTION 01048 - SPECIAL CONSTRUCTION CONDITIONS AND PROCEDURES
CITY OF OCEANSIDE 01048 - 1
SLRWRF RAS PIPE REPLACEMENT SPECIAL CONSTRUCTION
CONDITIONS AND PROCEDURES
1.1 SCOPE
This section covers special construction conditions and procedures associated with this construction project.
A. Section 01545 - Protection of Work and Property.
C. Section 02960 - Temporary Wastewater Bypass Pumping
1.3 NORMAL WORK SCHEDULE
A. The CONTRACTOR shall conduct all work within the working hours and days as defined in the General Provisions.
B. Exceptions to this work schedule are indicated per paragraph 1.18 (B) or as approved in writing by the AGENCY per paragraph 1.4 (A) below.
1.4 SATURDAY, SUNDAY, HOLIDAY AND NIGHT WORK
A. Except as noted above, no Work shall be done outside of defined working hours, nor on Saturdays, Sundays or City observed legal holidays, except such work as is necessary for the proper care and protection of the work already performed, or except in case of emergency, and in any case only with the written notice of the
B. Saturday operations require a permit secured from the City of Oceanside
Engineering Department by noon on the proceeding Thursday.
1.5 COMPLIANCE WITH STATE SAFETY CODES
A. All necessary machinery guards, railings, and other protective devices shall be provided as specified and/or required by the State of California Division of Industrial Safety and the Occupational Safety and Health Administration. It is assumed that all fabricators, electrical and machinery manufactures, and other equipment suppliers are conversant with such regulations and they shall be responsible for the industrial safety aspects of such equipment. All equipment shall comply with all rules and regulations of the Safety Orders of the State of California Division of industrial Safety and all local building. plumbing, and electrical codes and ordinances. Safety guards shall be easily removed to permit inspection, removal and repair of the moving parts.
CITY OF OCEANSIDE 01048 - 2
CONDITIONS AND PROCEDURES
1.6 RESPONSIBILITY FOR JOB SITE CONDITIONS
A. The CONTRACTOR agrees to assume sole and complete responsibility for job site conditions during the course of construction of this project, including safety of all persons and property; that this requirement shall apply continuously and not be limited to normal working hours; and that the CONTRACTOR shall defend, indemnify and hold the AGENCY and the design consultant harmless from any and all liability except for that arising from the sole negligence of the AGENCY. It is the CONTRACTOR’S sole responsibility to protect the safety of employees, residents, and the public from construction-related conditions or activities.
B. The CONTRACTOR shall be solely responsible for monitoring the work site on a
24-hour basis to prevent vandalism and graffiti. The CONTRACTOR, at no additional expense to the AGENCY, will replace all damaged new work.
1.7 CONSTRUCTION TESTING
A. The AGENCY shall furnish all materials testing and special inspections (other than steel welding inspection) required by the AGENCY.
B. The CONTRACTOR shall pay for the services of a third-party welding inspector for all steel welding operations. CONTRACTOR to submit welding inspector’s certification for AGENCY approval.
C. When any work is determined to be unsatisfactory, faulty or defective, or does not conform to the requirements of the Contract Documents, the costs incurred by the AGENCY for additional tests or inspections shall be reimbursed by the CONTRACTOR. Said costs shall be paid by the AGENCY and deducted from progress payments to the CONTRACTOR.
1.8 WATER/SANITATION AVAILABILITY
A. The CONTRACTOR shall be responsible for providing sanitation facilities for its employees and shall fully comply with the rules and regulations of the State Board of Health and/or other bodies having jurisdiction.
B. The CONTRACTOR shall, at all times, provide for its employees an abundant supply of safe drinking water and shall give orders against the use of, for drinking purposes, any water in the vicinity of the work known to be unsafe.
C. The CONTRACTOR shall provide suitable and conveniently located temporary toilets for use by his forces. They shall be left at the site until final inspection has been made.
D.
1.9 DOCUMENTATION OF EXISTING CONDITIONS PRIOR TO CONSTRUCTION
A. The CONTRACTOR shall perform video and photo recording surveys of existing facilities along the pipeline alignment and appurtenance locations to provide a record of preconstruction and postconstruction conditions in accordance with Specification 01380.
CITY OF OCEANSIDE 01048 - 3
CONDITIONS AND PROCEDURES
1.10 CLOSED CIRCUIT TELEVISION (CCTV) INSPECTIONS OF EXISTING SEWER
A. NOT USED
1.11 CONTRACTOR WORK AREA
A. The use of the project area will not be available beyond the limits of the project site as identified on the drawings. The CONTRACTOR must operate entirely within the limits of the project site. No equipment or materials may be parked or stock piled outside the project site or CONTRACTOR staging areas. The CONTRACTOR is responsible for locating and securing legal storage and staging areas. No staging in the right-of-way will be allowed. The CONTRACTOR must provide a storage and staging plan to the AGENCY, if requested, including written permission from legal owner of property stating they are allowing the CONTRACTOR to use their property.
B. It shall be understood that responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the CONTRACTOR and that no claim shall be made against the AGENCY or his authorized representatives by reason of any act. It shall be further understood that should any occasion arise necessitating access to the sites occupied by stored material or equipment, the AGENCY shall direct the CONTRACTOR owning or responsible for the stored materials and equipment to immediately move the same. No materials or equipment may be placed upon the property of the AGENCY other than the designated areas on the Drawings unless the AGENCY has agreed to the location proposed by the CONTRACTOR to be used for storage.
C. Where work is to be performed on private property, all necessary safeguards required by local, state, and federal regulations shall be supplied and deployed by the CONTRACTOR to protect residents and the public at all times.
PART 2 - PRODUCTS (NOT USED)
** END OF SECTION **
SECTION 01090 – REFERENCE STANDARDS
CITY OF OCEANSIDE 01090 - 1
SLRWRF RAS PIPE REPLACEMENT REFERENCE STANDARDS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Applicable Publications: Whenever in these specifications references are made to published specifications, codes, standards, or other requirements, it shall be understood that wherever no date is specified, only the latest specifications, standards, or requirements of the respective issuing agencies which have been published as of the date that the Project is advertised for bids shall apply; except to the extent that said standards or requirements may be in conflict with applicable laws, ordinances, or governing codes. No requirements set forth herein or shown on the drawings shall be waived because of any provision of, or omission from, said standards or requirements.
When a reference standard is specified, comply with requirements and recommendations stated in that standard, except when they are modified by the Contract Documents, or when applicable laws, ordinances, rules, regulations or codes establish stricter standards. The latest provisions of applicable standards shall apply to the work.
B. Reference standards include, but are not necessarily limited to, the following:
1. American Association of State Highway and Transportation Officials
(AASHTO)
2. American Concrete Institute (ACI)
3. American Institute of Steel Construction (AISC)
4. American Iron and Steel Institute (AISI)
5. American National Standards Institute (ANSI)
6. American Society of Mechanical Engineers (ASME)
7. American Society for Testing and Materials (ASTM)
8. American Water Works Association (AWWA)
9. American Welding Society (AWS)
10. Concrete Reinforcing Steel Institute (CRSI)
11. Institute of Electrical and Electronics Engineers (IEEE)
12. National Electrical Manufacturer's Association (NEMA)
13. National Fire Protection Association (NFPA)
14. Occupational Safety and Health Administration (OSHA)
15. Prestressed Concrete Institute (PCI)
16. Standard Specifications for Public Works Construction (SSPWC or
Greenbook)
17. State of California, Department of Transportation Standard Specifications
(Caltrans)
18. All other applicable standards listed in the Specifications, and the standards of utility service companies, where applicable.
19. National Association of Corrosion Engineers (NACE)
20. Society of Protective Coatings (SSPC)
A. Section 01300 – Record Drawings and Submittals
CITY OF OCEANSIDE 01090 - 2
B. Section 01630 – Product Options and Substitutions
1.3 REFERENCE SPECIFICATIONS, CODES, AND STANDARDS
A. Without limiting the generality of other requirements of the specifications, all work specified herein shall conform to or exceed the requirements of all applicable codes and the applicable requirements of the following documents to the extent that the provisions of such documents are not in conflict with the requirements of these Specifications nor the applicable codes.
B. References herein to "Engineer’s Manual" shall mean the City of Oceanside
Engineer’s Design and Processing Manual, latest edition, which are hereby incorporated in and made a part of these Contract Documents, to the extent of the applicable references thereto. Any reference to procedures or materials in the Engineering Manual is superceded by the Water Utilities Manual.
C. References herein to "Water Utilities Manual" shall mean the City of Oceanside
Water Utilities Department Water, Sewer and Recycled Water Design and Construction Manual, latest edition, which are hereby incorporated in and made a part of these Contract Documents, to the extent of the applicable references thereto. All references in the Water Utilities Manual take precedence over the Engineers Manual.
D. References herein to "Building Code" or UBC shall mean the Uniform Building
Code of the International Conference of Building Officials (ICBO). The latest edition of the code as approved and used by the local agency as of the date of award, as adopted by the agency having jurisdiction, shall apply to the work herein, including all addenda, modifications, amendments, or other lawful changes thereto.
E. References herein to “SSPWC” or “Greenbook” shall mean the “Standard
Specifications for Public Works Construction”, latest edition, Parts 2 and 3 only, unless other Parts are specifically listed in the Contract Documents, latest edition, including the County of San Diego Regional Amendments.
F. References to "Standard Drawings" shall mean the "Engineer’s Manual" including all current supplements, addenda, and revisions thereof. All water, sewer, and recycled water related “Standard Drawings” shall mean the “Water Utilities Manual” including all current supplements, addenda, and revisions thereof. References herein to “SDRSD” shall mean San Diego Regional Standard Drawings, latest edition.
G. References herein to "Cal-OSHA" shall mean State of California, Department of
Industrial Relations, Construction Safety Orders, as amended to date, and all changes and amendments thereto which are effective as of the date of construction.
H. References herein to "OSHA Regulations for Construction" shall mean Title 29, Part
1926, Construction Safety and Health Regulations, Code of Federal Regulations (OSHA), including all changes and amendments thereto.
CITY OF OCEANSIDE 01090 - 3
I. References herein to "OSHA Standards" shall mean Title 29, Part 1910, Occupational Safety and Health Standards, Code of Federal Regulations (OSHA), including all changes and amendments thereto.
J. No provisions of any referenced standard specification, manual or code, whether or not specifically incorporated by reference in the Contract Documents, shall be effective to change the duties and responsibilities of the AGENCY, Engineer, or CONTRACTOR from those set forth in the Contract Documents. Nor shall they be effective to assign to the Engineer any duty of authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of the Contract Documents.
K. In case of conflict between codes, reference standards, drawings and the other
Contract Documents, the most stringent requirements shall govern. All conflict shall be brought to the attention of the AGENCY for clarification and directions prior to ordering or providing any materials or labor. The CONTRACTOR shall bid the most stringent requirements.
L. Applicable Standard Specifications: The CONTRACTOR shall construct the work specified herein in accordance with the requirements of the Contract Documents and the referenced portions of those referenced codes, standards, and specifications listed herein.
1.4 MATERIAL ALTERNATIVES
A. The use of alternative materials, except those indicated in the Water Utilities
Manual, shall not be accepted.
SECTION 01300 – RECORD DRAWINGS AND SUBMITTALS
CITY OF OCEANSIDE 01300 - 1
SLRWRF RAS PIPE REPLACEMENT RECORD DRAWINGS AND SUBMITTALS
A. Wherever submittals are required hereunder, all such submittals by the CONTRACTOR shall be submitted to the AGENCY per this Section and the General Provisions.
B. Within 10 working days after the date of commencement as stated in the Notice to
Proceed, the CONTRACTOR shall submit the following items to the AGENCY for review:
1. A Submittal Schedule of Shop Drawings, Samples, and proposed
Substitutes (“Or Equal”) submittals. Additional submittals will not be accepted for review prior to acceptance of the Submittal Schedule by the
AGENCY.
2. A list of all permits and licenses the CONTRACTOR shall obtain indicating the agency required to grant the permit and the expected date of submittal for the permit and required date for receipt of the permit.
A. The work of the following Sections apply to Work of this Section. Other Sections of the Specifications, not referenced below, shall also apply to the extent required for proper performance of the Work.
1. General Conditions
2. Section 01048– Special Construction Conditions and Procedures
3. Section 15000– General Piping System and Appurtenances
4. Section 01630 – Product Options and Substitutions
5. Section 01700 – Project Closeout
1.3 CONTRACTOR’S OPTIONS
See Section 01630.
1.4 SHOP DRAWINGS
A. Submit Shop Drawings to AGENCY for review and acceptance in accordance with contract document requirements.
B. Determine and verify before submitting each Shop Drawing or Sample:
1. Field measurements, quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto.
2. Materials with respect to intended use, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the work.
3. Information relative to CONTRACTOR’s sole responsibilities in respect of
CITY OF OCEANSIDE 01300 - 2
SLRWRF RAS PIPE REPLACEMENT RECORD DRAWINGS AND SUBMITTALS
means, methods, techniques, sequences, and procedures of construction, and safety precautions and programs incident thereto.
C. CONTRACTOR shall also have reviewed and coordinated each Shop Drawing or
Sample with other Shop Drawings and Samples, and with the requirements of work and Contract Documents.
D. All CONTRACTOR shop drawing submittals shall be carefully reviewed by an authorized representative of the CONTRACTOR, prior to submission to the AGENCY. Each submittal shall be dated, signed, and certified by the CONTRACTOR, as being correct and in strict conformance with the Contract Documents. In the case of shop drawings, each sheet shall be so dated, signed, and certified. No consideration for review by the AGENCY of any CONTRACTOR submittals will be made for any items which have not been so certified by the CONTRACTOR. All non-certified submittals will be returned to the CONTRACTOR without action taken by the AGENCY, and any delays caused thereby shall be the total responsibility of the CONTRACTOR.
E. At the time of each submission, CONTRACTOR shall give AGENCY specific written notice of variations, if any, that the Shop Drawing or Sample submitted may have from the requirements of the Contract documents. The notice shall be in a written communication separate from the submittal; and, in addition, shall cause a specific notation to be made on each Shop Drawing and Sample submitted to AGENCY for review and approval of each such variation.
F. Review and approval of Shop Drawings and Samples will be only to determine if items covered by submittals will, after installation or incorporation in work, conform to information given in the Contract Documents, and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. Review and approval will not extend to means, methods, techniques, sequences, or procedures of construction, except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions. The review of CONTRACTOR shop drawing submittals shall not relieve the CONTRACTOR of the entire responsibility for the correctness of details and dimensions. The CONTRACTOR shall assume all responsibility and risk for any misfits due to any errors in CONTRACTOR submittals. The CONTRACTOR shall be responsible for the dimensions and the design of adequate connections and details. CONTRACTOR shall make corrections required to submittals and shall return the required number of corrected copies of Shop Drawings and submit as required new Samples for review and approval. CONTRACTOR shall direct specific attention in writing to revisions other than corrections called for on previous submittals.
G. Review and approval of Shop Drawings or Samples shall not relieve CONTRACTOR from responsibility for variation from requirements of the Contract Documents, unless CONTRACTOR has in writing called attention to each such variation at the time of submission, and written approval has been given of each such variation by specific written notation thereof incorporated in, or accompanying, the Shop Drawing or Sample approval.
CITY OF OCEANSIDE 01300 - 3
SLRWRF RAS PIPE REPLACEMENT RECORD DRAWINGS AND SUBMITTALS
H. Where a Shop Drawing or Sample is required by Contract Documents or schedule of Shop Drawings and Sample submissions accepted by AGENCY, related work performed prior to review and approval of pertinent submittal will be at the sole expense and responsibility of CONTRACTOR.
1.5 SUBMITTAL PROCEDURES
See General Provisions
1.6 SUBMITTAL FORMAT AND COPIES
A. Format for Shop Drawings:
1. Include on each drawing the drawing title, number, date, and…