This is a Request for Qualifications (RFQ) issued by St. Landry Parish Airport (KOPL) in Louisiana for engineering services related to Automated Weather Observation System (AWOS) and related airport infrastructure. The airport is seeking qualified engineering firms to provide comprehensive services for a five-year period beginning from the Notice to Proceed date of the first project under a Master Services Agreement. The scope of work encompasses AWOS replacements, installations, maintenance, repairs, upgrades, and updates; NAV-AID replacements, installations, maintenance, repairs, upgrades, and updates; airfield lighting, markings, and signage work; relocation and new construction of AWOS, NAV AIDs, lighting, markings, and signage; and DBE program administration oversight. The services required include topographic surveys, preliminary investigations, property acquisition services, DBE program methodology, alternative research, preparation of preliminary and final construction plans and specifications, construction safety and phasing plans, cost estimates, bid reviews, award recommendations, grant management, construction administration, and resident inspection. Statements of Qualifications must be submitted on Standard Form 330 (SF 330) and are due by 12:00 PM (noon) on December 15, 2025, to St. Landry Parish Airport, 299 Hangar Road, Opelousas, Louisiana 70570. Inquiries should be directed to the St. Landry Parish Airport Manager at (337) 407-1551.
Evaluation of submissions will be based on five weighted criteria: resumes of the proposed project team (weight value of 4), example projects illustrating team qualifications (weight value of 4), key personnel's participation in past projects (weight value of 5), firm size relative to project magnitude (weight value of 3), and proximity to the project location (weight value of 5). Scoring will use a numerical scale of 1 to 5, with each criterion's score multiplied by its weight factor. The top three applicants will be placed on a short list, and the sponsor may issue a Request for Proposals (RFP) to short-listed firms if further evaluation is deemed necessary. Following final evaluation, the sponsor will rank applicants and enter fee negotiations with the top-ranked firm; if unsuccessful, negotiations will proceed with the next-ranked firm. The selected firm will be required to execute the standard LADOTD Aviation Section contract. Projects are subject to availability of funding from the Federal Aviation Administration, the State of Louisiana, and the airport; the airport does not guarantee implementation of all listed projects. Failure to provide all requested information in the SF 330 submission may result in the submission being deemed nonresponsive and ineligible for scoring.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUESTS FOR QUALIFICATIONS
AUTOMATED WEATHER OBSERVATION SYSTEM (AWOS)
ENGINEERING SERVICES at St. Landry Parish Airport
Notice is hereby given that the St. Landry Parish Airport (KOPL) is requesting submittal of qualification statements from engineering firms interested in performing engineering services for the following project.
Submittal of qualification statements from engineering firms interested in performing engineering services for a five (5) year period beginning from the Notice to Proceed date of the first project as defined in the Master Services Agreement Contract.
The projects identified by the airport for implementation or development are presented herein. The projects are subject to the availability of funding from the Federal Aviation Administration, the State of Louisiana, and the airport. The projects are not necessarily listed by priority, nor does the airport guarantee the implementation of all projects.
SCOPE OF PROJECT:
PROJECT LIST:
1. AWOS replacements, installations, maintenance, repairs, upgrades, updates, and any other problem that may occur.
2. NAV-AID’s replacements, installations, maintenance, repairs, upgrades, updates, and any other problem that may occur.
3. Airfield Lighting Markings and signage replacements, installations, maintenance, repairs, upgrades, updates, and any other problem that may occur.
4. Relocation, and/or new construction of any AWOS, NAV AIDs, Lighting and Markings, signage, or related criteria.
5. Assure Parish Government is following the administration of Disadvantaged Business Enterprise (DBE)
Program.
SCOPE OF SERVICES: Provide topographic surveys, preliminary investigations, property acquisition services, DBE program and goal methodology (as required), research available alternatives, preparation of preliminary and final construction plans and specifications construction safety and phasing plan, cost estimates, review of bids, award recommendation, grant management, construction administration, resident inspection and other special or related services for projects as defined above.
GENERAL
Firms interested in performing these services shall furnish a statement of qualifications on a Standard Form 330 (SF330).
Interested firms may obtain SF 330 from the Sponsor or from the LADOTD Aviation Section. The criteria and weighing factors to be used by the Sponsor in evaluating responses will be as follows:
1. Resumes of the proposed project team with a weight value of 4.
2. Example projects that best illustrate the proposed team’s qualifications with a weighted value of 4.
3. Key personnel’s participation in past projects with a weighted value of 5.
4. Firm size as related to project magnitude, with a weighted value of 3.
5. Proximity of the Project Location with a value of 5.
The selection criteria shall be based on a numerical scale of 1 to 5, with 5 being the highest possible score and 1 being the lowest possible score. The score for each criterion will be multiplied by its weight factor, which indicates the importance of each criterion as it relates to this contract.
For selection criteria without an assigned weight value, the score shall be “pass/fail”, with a “fail” rating possibly resulting in the disqualification of the applicant prior to the rating process.
Following the evaluation of the Statements of Qualifications received by the Sponsor’s selection committee, the top three (3) applicants will be placed on a short list. It shall be the option of the Sponsor, if the sponsor or selection committee feels further evaluation of the qualified short list applicants is necessary in order to determine the top-ranked firm, to issue a Request For Proposals (RFP) to all short list applicants. The RFP issued to all short-list applicants shall contain instructions on the format (such as written proposal, interview, presentation, etc.) to be used in submitting proposals and information on how the proposals will be evaluated.
Following the final evaluation of qualified applicants, the Sponsor will place the applicants in a final ranking based on qualifications. The sponsor will then enter fee negotiations with the top-ranked firm for the contract, with the unsuccessful firms being notified accordingly. Should these negotiations be unsuccessful, the Sponsor shall enter negotiations with the next-highest-ranked firm, and so on. The Sponsor reserves the right to reject all applicants and re-advertise for the contract.
Following the final evaluation of qualified applicants, the Sponsor will place the applicants in a final ranking based on qualifications. The sponsor will then enter fee negotiations with the top-ranked firm for the contract, with the unsuccessful firms being notified accordingly. Should these negotiations be unsuccessful, the Sponsor shall enter negotiations with the next-highest ranked firm, and so on. The Sponsor reserves the right to reject all applicants and re-advertise for the contract.
Following the successful negotiation of fees with the Sponsor, the successful firm will be required to execute the standard LADOTD Aviation Section contract.
The Statement of Qualification for, SF 330, shall be mailed or delivered to the St. Landry Parish Airport, KOPL, 299 Hangar Rd., Opelousas, La. 70570
Statements of Qualifications will be accepted until 12 PM (noon), December 15, 2025.
Questions regarding this project should be addressed to (St Landry Parish Airport Manager, St. Landry Parish Airport, 299 Hangar Road, Opelousas, LA 70570 ~ KOPL (337) 407-1551. Firms wishing to apply must submit a fully completed SF 330. Failure to provide all information requested may result in the submission being considered nonresponsive, and the firm will not be given a total score in the evaluation process.