This is a Statement of Work (SOW) for annual maintenance services on two electrically operated vertical folding acoustical walls (Skyfold Walls) located at Army Cyber Command (ARCYBER) Headquarters, Building 61501, 930 15th Street, Fort Gordon, Georgia 30905.

The contractor must provide comprehensive annual maintenance including all parts and labor to inspect and service the Skyfold Wall systems. Specific maintenance tasks include inspecting wall height limits, lifting cables, drums, bearings, pulleys, couplings, and rigging hardware; inspecting the lift motor gearbox and electromagnetic brake; inspecting the hydraulic checking device assembly and verifying operating pressure (0-100 psi during ascent, 200-300 psi during descent); testing the entire electrical system including control box, encoder, over-torque sensor, lifting motor, brake, obstruction/infrared sensor, end seals, switches, and all plugs and cables; inspecting lifting mechanisms for defects and abnormal wear; and visually inspecting and changing hydraulic oil as necessary. The contractor must deliver one Skyfold Wall Service Inspection Report upon completion. Work is performed Monday through Friday (weekends as required), excluding federal holidays and facility closures. The Government furnishes Building 61501 facilities and all standard utilities (electricity, water, sewage, heating, cooling, telephone, and internet) at no cost to the contractor. All contractor and subcontractor employees must comply with security requirements including background checks, personal identity verification per FAR clause 52.204-9, adjudication standards using the National Crime Information Center Interstate Identification Index and Terrorist Screening Database, and installation access policies. Contractor employees requiring facility access must complete AT Level I awareness training within 30 calendar days of contract start and Level I OPSEC Awareness training per AR 530-1, with training certificates submitted to the Contracting Officer Representative within 30 days of completion. This non-personal services contract maintains the system's eligibility for a 10-year extended warranty through adherence to the preventive maintenance schedule.

View the file

Other files

File Type Posted
Notice of Intent 1.pdf PDF

On GovTribe

Work with this file

  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Army Cyber Command

Skyfold Wall Maintenance Agreement

Statement of Work (SOW)

Statement of Work

TABLE OF CONTENTS

1.0 Introduction 2

1.1 Background 2

1.2 Scope 2

1.3 Objectives 2

2.0 Tasks 3

2.2 Deliverables 3

2.3 Schedule 4

3.0 Government Furnished Property 4

4.0 Security Requirements 4

5.0 Training Requirements 5

1.0 INTRODUCTION/OVERVIEW

This is a non-personal services contract to perform annual service on the Army Cyber

Command’s (ARCYBER) Skyfold Wall located at 930 15th Street, BLDG 61501, Fort

Gordon, GA 30905.

1.1 BACKGROUND

During the construction of the ARCYBER Headquarters two vertical folding acoustical walls were install offering soundproofing indexes above and beyond industry standards that is electrically operated and retracts neatly into the ceiling freeing up valuable floor space and when engaged offering a level sound proofing that is required in a classified environment.

1.2 SCOPE

The Contractor shall provide annual maintenance that includes all parts and labor to perform the annual service. Additionally, ARCYBER is wanting stay eligible for the 10-year extended warranty by maintaining this preventive maintenance agreement for the duration of that period.

1.3 OBJECTIVES

The contractor shall carry out any repairs required to the Skyfold wall due to defects in materials or workmanship and occurring under normal use, at no charge for parts and/or labor during the warranty period, provided that: The Skyfold wall was operated according to manufacturer’s specifications and/or operating instructions; The Skyfold wall was always operated by two people, one per side of wall, each activating a switch wired in series with the other; The Skyfold wall was operated in a normal environment like the one that prevailed when it was originally installed; All servicing and inspections have been performed by a local, authorized Skyfold dealer, according to the maintenance schedule included in the manual.

2.0 TASKS

2.1 Inspect wall height as the upper position limit and the lower position limit may need resetting.

2.2 Inspect lifting cable, drums, bearings, pulleys, couplings, tie-offs and other rigging hardware for wear, alignment and fit.

2.3 Inspect the lift motor gearbox.

2.4 Inspect the electromagnetic brake.

2.5 Inspect the hydraulic checking device assembly includes a manifold, a reservoir, a pressure gauge, a hydraulic motor, and a sprocket and chain. During normal operation, the gauge pressure should be 0-100 psi (0-800 kPa) while the wall is ascending and 200-300 psi (15000-2000 kPa) while the wall is descending. The hydraulic checking device must be inspected, and its operating pressure verified.

2.6 Test the entire electrical system including the following: the control box, encoder, over-torque sensor, lifting motor, electromagnetic brake, obstruction/infra-red sensor, end seals, switches, and all plugs and cables.

2.7 Inspect the lifting mechanisms for defects and abnormal wear.

2.8 Visually inspect the hydraulic oil and if necessary, change the oil.

2.2 DELIVERABLES

The Contractor shall provide one copy of the Skyfold Wall Service Inspection Report.

2.3 SCHEDULE

The work to be performed under this contract will at building 61501, 930 15th Street, Fort

Gordon, GA 30905. Work schedule Monday – Friday (weekends as required), with the exception of federal holidays or if facility is closed due to unforeseen circumstances.

3.0 GOVERNMENT FURNISHED RESOURCES

3.1 Facilities: The Government will make available to the Contractor building 61501 on Fort Gordon, GA to perform the work outlined in this

SOW.

3.2 Utilities: The Government will provide all standard utilities at no cost to the Contractor. Such standard services at a minimum will include electricity, water, sewage, heating and cooling, post telephone service and internet service. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, such as turning off the water faucets or valves after using the required amount.

4.0 SECURITY REQUIREMENTS

4.1 Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or

Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor

Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection

Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

4.2 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center

Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB)

(Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative).

5.0 TRAINING REQUIREMENTS

5.1 All contractor employees, including subcontractor employees, requiring access to

Army installations, facilities, and controlled-access areas shall complete the following training requirement:

5.2 AT Level I awareness training within thirty (30) calendar days after the contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within thirty (30) calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil.

5.3 Per AR 530-1 Operations Security, the contractor employees must complete Level I

OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter. OPSEC Level I training is available at the following website: http://jko.jten.mil.