Standard_Operating_Procedure_-_AHA.docx

DOCX document 17 KB Posted

Attached to
Replacement of underground fuel storage tank in Kolkata, India
Solicitation number
SIN30016Q0016
Issued by

About this file

SOP- work space safety

View the file

Other files

File Type Posted
Solicitation_No._SIN30016Q0016.doc DOC document
SF_18.pdf PDF
Workplace_Hazard_Assessment_Checklist.doc DOC document
Safety_Standards_-_July_2016.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Standard Operating Procedure Activity Hazard Analysis Below is the SOP is driven by one of the recommendations from SHEM on identifying the hazards involved in any project and its remedial measure included in safety plan.

Step 1.Inform POSHO office for any new project on USG properties.
Step 2.15 FAM 967 requires that the POSHO be involved during the planning stages of post-managed contractor activities to identify safety, health, and environmental management hazards, including but not limited to the requirements of the Accident Prevention Clause specified in the Department of State Acquisition Regulations (DOSAR) 652.236-70.
Step 2.The POSHO must ensure that the project Scope of Work identifies safety, health, and environmental management hazards.
Step 3.The contractor must document in the bid for the work how the control of each hazard will be implemented and maintained during the project by submission of a safety plan and activity hazard analysis (AHA) for high hazard activities. The POSHO or qualified Post representative must review the contractor's proposal and provide feedback to the responsible project manager and Contracting Officer prior to acceptance of the bid.
POSHO New DelhiStandard Operating Procedure