Sidewalk_Carbo_Reduction_Grant_Scope.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Berlin Safe Routes to School Sidewalk Project
Solicitation number
2026-04
Issued by
Hartford County, Connecticut

About this file

This is a scope of work document for the Town of Berlin, Connecticut's Safe Routes to School Carbon Reduction Grant sidewalk project, funded by the Federal Carbon Reduction Program administered by the Connecticut Department of Transportation. The project encompasses sidewalk installation across six streets in the vicinity of Willard and Hubbard Elementary Schools to enhance pedestrian connectivity and safety. The specific streets and linear footage include Worthington Ridge (1,170 LF), Peter Parley Row (730 LF), Lower Lane (4,125 LF), Toll Gate Road (430 LF), Main Street, East Berlin (1,040 LF), and Meadow Lane (1,545 LF), totaling 9,040 linear feet of sidewalk improvements. The Town is seeking a Consulting Engineering firm to prepare contract plans and documents, with the selected firm potentially required to provide survey services, permitting assistance, environmental documentation, and construction inspection. The projected construction cost is estimated at $3,050,000, and design firms will be selected based on design and technical competence, capacity and capability to perform within the allotted timeframe, past performance record, and knowledge of Federal, State, and Municipal procedures, with the design fee to be negotiated on a lump sum basis.

Respondent firms should be adequately sized and sufficiently staffed to execute the scope of work. The project is funded through the Federal Carbon Reduction Program, eliminating the need for local cost-share. No explicit set-asides, incumbent vendors, response deadlines, or contract term information is specified in the scope document itself. The project advances the Town's objectives to improve pedestrian safety and sidewalk connectivity for school-age residents and families utilizing the nearby elementary schools.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BOE, no costs

Berlin Safe Routes to School Carbon Reduction Grant Scope
StreetLocationSideLength in LF
Worthington RidgePeter Parley Row to Middletown RoadW880
Worthington Ridge684 Worthington to Mill StreetW290
Peter Parley Row#11 -67N730
Lower LaneNorton to MeadowW4,125
Meadow Lane875 Lower Lane to 7 Meadow Lower LaneN1,545
Toll Gate RoadMeadow Ln to Olisky BlvdW430
Kensington RoadCarriage Drive to NortonW
Four Rod RoadWildemere to NortonE
Four Rod RoadWildemere to 975 Four RodE
Kensington RoadNorth of Arbor CommonW
Farmington Ave,Seymour to Patterson WayNE
Main Street, E BerlinChestnut to GroveW1,040
Magnolia La, E BerlinNorth sideN
Wilcox Avenue, E BerlinWest SideW
Total9,040

File details come from the government source that posted it. Updated .