This sources sought notice and statement of work describe a requirement by the U.S. Army's Mission and Installation Contracting Command at Fort Bragg to procure supplies for repair of the Sicily Drop Zone. Supplies include 13,500 cubic yards of fill material meeting soil classification and grading requirements, reinforced concrete pipe, lumber, rebar, stone and other construction materials. Responses were due by May 27, 2020, with intent to award a firm fixed-price small business set-aside contract for delivery of supplies within specified timeframes not exceeding 30 calendar days from award. Offerors were to provide information on small business socioeconomic status, percentage of work as prime contractor, and ability to provide and test fill material to specifications.

View the file

Other files

File Type Posted
Supplies for Sicily Drop Zone Sources Sought FINAL.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PROJECT NO. EA-00033-18

Repair Sicily FLS (Troop CONS)

FORT BRAGG, NORTH CAROLINA

Special Provisions and General Project Information:

1. The contractor shall prepare a technical quote for supplies needed for repair of Sicily FLS

(Troop CONS).

2. Project Title: Repair Sicily FLS (Troop CONS, Fort Bragg, North Carolina.

3. Project Number: EA-00033-18

4. Delivery Date: Forty-Five (45) day delivery timeframe.

5. Delivery Location: All supplies shall be delivered to Sicily Drop Zone, Fort Bragg, North

Carolina. Prior to delivery, coordination shall be made with ANDREW S. FOLZ, P.E. @ (910)-

396-7736; andrew.s.folz.civ@mail.mil .

6. The Mission and Installation Contracting Command-Fort Bragg (MICC-FB) has a requirement from the Directorate of Public Works (DPW) to procure supply materials to build culverts for Sicily Drop Zone at Fort Bragg, North Carolina. Supplies to be procured are:

Description Quantity Unit of Issue Delivery

Fill Material for Sicily FLS 13,500 CY Within 20 days of contract award

24" RCP (Meets ASTM C-76) 750 LF Within 10 days of contract award

4" Bolster (re-bar) Chairs 200 EA Within 10 days of contract award

#6 Rebar (20' sections) 36 EA Within 10 days of contract award

2x12 Lumber (16' sections) 9 EA Within 10 days of contract award

2x4 Lumber (16' sections) 18 EA Within 10 days of contract award

100' Wire Ties (Rebar Ties) 2 EA Within 10 days of contract award

#57 Stone 65 CY Within 10 days of contract award

3/4" Plywood sheets (4'x8') 33 EA Within 10 days of contract award

2x4 Lumber (8' Sections) 170 EA Within 10 days of contract award

200' of 16 gauge wire ties 4 EA Within 10 days of contract award

3/4" Concrete/Masonry Bit 3 EA Within 10 days of contract award

Concrete Epoxy 1 GAL Within 10 days of contract award

Concrete (4500 psi) 15 CY Within 20 days of contract award

SCOPE OF WORK NOTES:

7. The Contractor shall deliver all supplies within the specified timeframe outlined in this

Statement of Work. The Contractor shall deliver all supplies within the specified timeframe outlined in this Statement of Work. All supplies except the Fill Material and concrete shall be mailto:andrew.s.folz.civ@mail.mil

STATEMENT OF WORK

PROJECT NO. EA-00033-18

Repair Sicily FLS (Troop CONS)

FORT BRAGG, NORTH CAROLINA

delivered within ten (10) days of contract award. The Fill Material shall be delivered within twenty (20) days of contract award; and the concrete delivered once the culverts are ready.

8. The Contractor shall ensure the material must classify as Clayey Sands (SC) according to the

Unified Soil Classification System. The Liquid Limit is recommended to be between 20 and 50.

The plasticity index must be no less than 7, but is recommended to be above 10. The gradation should fall into the ranges below.

Sieve Size Percent Passing

9.5 mm (3/8in) 100

No 4 70-100

No 10 55-100

No 40 30-70

No 200 12-15

9. Inspection: The contractor shall have the technical capabilities to test and certify that the Fill

Material (Sand) meets the requirements for this buy.

10. The Contractor shall provide a Statement of Understanding for the supplies requested.

Specially, outlining a clear and concise understanding of the required Fill Material to be purchased. This statement shall include how the Contractor will obtain the end state and specifications the Government has requested the Fill Material to meet.

11. Contractor shall be able to provide all supplies, NO Partial Delivery.