shell beach drive bridge over pithon coulee repair project information - Google Search.pdf

PDF 124 KB Posted

Attached to
Shell Beach Drive Bridge over Pithon Coulee Repair
Solicitation number
2023-735
Issued by
Calcasieu Parish, Louisiana

About this file

This document contains project information for the Shell Beach Drive Bridge over Pithon Coulee Repair Project managed by the City of Lake Charles, Louisiana (Project No. 2023-735, Capital Project No. CP3445). The project scope includes demolition of damaged bridge components and reconstruction of the northeast portion of the concrete bridge deck, substructure, and sidewalk using new reinforced concrete slabs. Additional work encompasses installation of new decorative handrails, ADA-compliant detectable warnings, site-specific temporary traffic control, replacement of all four bridge lighting fixtures with LED units, installation of new streetlamps at each bridge corner with associated conduit and electrical work, concrete pavement replacement, grout spalling repairs, and crack sealing. Bids for the project are scheduled to be opened on October 20, 2026.

The project was initiated following a March 2021 vehicle collision into the northeast corner of the bridge that damaged the handrail, deck, substructure, and a streetlamp. The document does not contain information regarding pricing terms, set-asides, incumbents, funding sources, contract amounts, or other financial details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The City of Lake Charles is managing the Shell Beach Drive Bridge over Pithon Coulee Repair Project (Project No. 2023-735, Capital Project No. CP3445 ) in Lake Charles, Louisiana.

Project Background

Cause of Damage: In March 2021, a vehicle crashed into the northeast corner of the bridge, twisting the handrail and severely damaging the deck, substructure, and a streetlamp.

Bid Opening Date: Bids for the project are scheduled to be opened on October 20, 2026.

Scope of Work

Reconstruction: Demolition of damaged bridge components and reconstruction of the northeast portion of the concrete bridge deck, substructure, and sidewalk using new reinforced concrete slabs.

Safety & Accessibility: Installation of new decorative handrails, ADA-compliant detectable warnings, and site-specific temporary traffic control.

Lighting & Electrical: Replacement of all four bridge lighting fixtures with LED units, installation of new streetlamps at each bridge corner, and associated conduit, raceway, junction box, and photocell work.

Surface Work: Concrete pavement replacement, grout spalling repairs, and crack sealing.

City of Lake Charles, LA +1 www.bidexpress.com

HigherGov +1

Bid Bana… +1

Bid Banana

Bid Banana

10/10/26, 11:14 PM shell beach drive bridge over pithon coulee repair project information - Google Search https://www.google.com/search?q=shell+beach+drive+bridge+over+pithon+coulee+repair+project+information&biw=1596&bih=842&sca_esv=6aa0da… 1/1 https://www.cityoflakecharles.com/DocumentCenter/View/1034/Project-No-2023-735-Capital-Project-No-3445-Shell-Beach-Drive-Bridge-over-Pithon-Coulee-Repair-PDF https://www.cityoflakecharles.com/DocumentCenter/View/1034/Project-No-2023-735-Capital-Project-No-3445-Shell-Beach-Drive-Bridge-over-Pithon-Coulee-Repair-PDF https://www.bidexpress.com/businesses/333/home?page=35 https://www.highergov.com/sl/contract-opportunity/tn-shell-beach-drive-bridge-northeast-corne-74429323/ https://bidbanana.thebidlab.com/bid/lRq8pSWjT18w9JJjzwfm https://bidbanana.thebidlab.com/bid/lRq8pSWjT18w9JJjzwfm https://bidbanana.thebidlab.com/bid/lRq8pSWjT18w9JJjzwfm

File details come from the government source that posted it. Updated .