This Request for Qualifications (RFQ) is issued by the Sanford Housing Authority (SHA) seeking a qualified developer partner to participate in the repositioning of Stewart Manor, a vacant 99-unit elderly mid-rise public housing property located at 500 Dudley Street, Sanford, North Carolina. The Authority is considering rehabilitation or redevelopment using low-income housing tax credits (9% and/or 4%), bonds, FHA-insured or conventional financing, project-based voucher assistance, and other public and private sources. The developer partner will be required to serve as a co-developer with the Authority and will be responsible for arranging appropriate financing, preparing tax credit applications, coordinating development activities, and overseeing construction. The minimum qualification requires that respondents or joint venture members have served as lead developer on at least two LIHTC projects successfully placed in service within the past five years. The deadline for submission of questions is December 7, 2026, with responses issued by addendum on December 18, 2026. Qualifications are due by 4:00 p.m. Eastern Time on January 14, 2027. An optional exterior site visit is available by appointment before the question deadline. The contract award is tentatively scheduled for February 8, 2027, pending Board of Commissioners approval. No contract term limitations are specified beyond the requirement that any agreement exceeding five years is subject to HUD approval.

This is a qualifications-based selection (QBS) procurement in which price is not an evaluation factor, and respondents must not submit fee amounts or developer-fee proposals with their qualifications. The Authority reserves the right to select one developer partner or reject all submissions. Evaluation criteria include development experience and qualifications (35 points), financial capacity (25 points), development and financing approach (25 points), team capacity and key personnel (10 points), and Section 3 and affirmative steps performance (5 points), for a total of 100 points. The Authority will negotiate fees and business terms only with the top-ranked respondent using an independent cost estimate and HUD's developer-fee safe harbor guidelines. If negotiations fail, the Authority will proceed to the next-ranked respondent without returning to previous respondents. The Authority will require financial statements demonstrating adequate capacity to fund predevelopment costs and provide required guarantees, and the successful developer partner must provide commercial general liability insurance of $1,000,000 per occurrence/$2,000,000 aggregate before execution of the development agreement. The project budget and fiscal provisions, as well as funding availability and HUD approval, are prerequisites for contract award.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sanford Housing Authority — RFQ: Developer Partner / Co-Developer, Stewart Manor

SANFORD HOUSING AUTHORITY

REQUEST FOR QUALIFICATIONS No. SHA-2026-_11__

DEVELOPER PARTNER / CO-DEVELOPER (QUALIFICATIONS-BASED

SELECTION)

For submission of LIHTC award and/or other financing

FOR

Stewart Manor

500 Dudley Street, Sanford, NC 27330

99-unit Elderly Apartment Community

Single Five-Story Building

Issued: November 11, 2026

Due: January 14, 2027, 4:00 p.m. ET

TABLE OF CONTENTS

Solicitation Summary and Schedule of Events

PART I — GENERAL INFORMATION

1.1 Executive Summary

1.2 Rules, Regulations, and Licensing Requirements

1.3 Contract Form and Issues

1.4 Procurement Method (Qualifications-Based Selection)

1.5 Contact with the Sanford Housing Authority Staff, Commissioners, Residents

1.6 Incurred Costs in Preparing Qualifications

1.7 Section 3 and Affirmative Steps for Small, Minority, and Women's Businesses; 1.8 Conflict of Interest and Identity of Interest; 1.9 Public Records and Confidential Information; 1.10 Protests

PART II — PROJECT INFORMATION

2.1 General Overview (including Site Visit)

2.2 General Scope of Services

2.3 Preferred Concepts

2.4 Development Strategy

2.5 Role of the Sanford Housing Authority

2.6 Role of Developer Partner; 2.7 Property Information and Reports

PART III — PROCUREMENT PROCESS

3.1 Directions for Submission

3.2 Minimum Qualifications and Qualification Criteria

3.3 Qualification / Technical Response Requirements

3.4 Certifications and Assurances

3.5 Organization of Qualifications

3.6 Evaluation of Qualifications

3.7 Evaluation Factors

3.8 Selection and Negotiation Process

3.9 Execution of Contract; 3.10 Insurance

ATTACHMENTS: A – Respondent Information and Acknowledgment of Addenda; B – Development Experience Schedule; C – Conflict of Interest and Identity of Interest Disclosure; D – North Carolina Certifications; E – Non-Collusion Certification; F – Section 3 and Affirmative Steps Plan Summary; G – Required Federal Contract Provisions (2 CFR Part 200, Appendix II); H – HUD-5369-B, Instructions to Offerors – Non-Construction; I – HUD-5369- C, Certifications and Representations of Offerors – Non-Construction; J – HUD-5370-C, General Conditions for Non-Construction Contracts, Section I; K – HUD-50071, Certification of Payments to Influence Federal Transactions; L – SF-LLL, Disclosure of Lobbying Activities

Solicitation Summary The Sanford Housing Authority (the Authority or SHA) is seeking statements of qualifications from qualified developer partners to participate in the repositioning of Stewart Manor, a vacant, 99-unit, elderly mid-rise public housing property at 500 Dudley Street, Sanford, North Carolina.

The Authority is considering rehabilitation or redevelopment of the site using any combination of low-income housing tax credits (9% and/or 4%), bonds, FHA-insured or conventional financing, project-based voucher assistance, and other public and private sources. It reserves the right to select one developer partner or to not make an award.

The Authority is seeking a developer who can provide resources to assist with the repositioning of Stewart Manor. The Authority will require that it be listed as a Co-Developer. To create the desired results will require comprehensive planning, leveraging of resources, and the coordination of planning efforts. The Authority expects to continue working with Stogner Architecture, PA on this project as the architect.

Minimum qualification: the respondent (or a member of its joint venture) must have served as lead developer on at least two (2) low-income housing tax credit (LIHTC) projects that were successfully completed (placed in service) within the past five (5) years. Respondents must include resumes and evidence of recent successful experience in financing, developing, rehabilitating, constructing, owning, and/or operating similar properties. Experience with the North Carolina Housing Finance Agency (NCHFA) Qualified Allocation Plan is evaluated under Factor 1 (Section 3.7). Submission requirements are in Section 3.1.

This is a Request for Qualifications under the qualifications-based selection (QBS) method permitted for development partners by HUD Handbook 7460.8 REV-3, Sections 7.3 and 17.4, and 24 CFR 905.604(h)(1). Respondents shall NOT submit fees, prices, or developer-fee amounts with their qualifications. Price is not an evaluation factor. Following the submission of qualifications on January 14, 2027, the Authority will rank the respondents and may create a shortlist, based on the predetermined evaluation criteria, of 2-4 developers that may then be requested to participate in in-person interviews. The Authority will then negotiate fees and business terms with the top-ranked respondent. The contract award is tentatively scheduled for February 8, 2027, pending Board of Commissioners approval.

Please direct all inquiries regarding this Request for Qualifications in writing to the following individual:

Anthony Goodson, Jr., Chief Executive Officer 504 N. First Street Sanford, NC 27331 agoodson@sha-nc.org

The Authority will accept qualifications received on or before Thursday, January 14, 2027, at 4:00 p.m.

Eastern Time. Submissions received after this date and time will not be accepted, except as provided in HUD-5369-B, paragraph 6.

The Authority reserves the right to reject any or all submissions, and to advertise for new qualifications to accomplish this solicitation by any means determined to be in the best interest of the Authority.

The Authority will evaluate qualifications to determine the most highly qualified respondent to satisfy the needs of the Authority.

AUTHORITY – SCHEDULE OF EVENTS

Issue Date of RFQ November 11, 2026

Deadline for Submission of Questions December 7, 2026

AUTHORITY Response to Questions Issued (Addendum)

December 18, 2026

Deadline for Submission of Qualifications January 14, 2027, 4:00 PM

Award Date February 8, 2027

All times are Eastern Time. Dates after the submission deadline are tentative and may change at the Authority's discretion.

PART I – GENERAL INFORMATION

1.1 Executive Summary

The Sanford Housing Authority (AUTHORITY) is seeking a Developer Partner to partner in the repositioning (rehabilitation or redevelopment) of Stewart Manor, which is owned by the AUTHORITY.

The AUTHORITY provides affordable housing to people in the City of Sanford, North Carolina, and is committed to providing quality, affordable housing in safe and economically viable neighborhoods through partnerships with our residents and other groups, fostering neighborhood development and opportunities for those we serve to achieve self-sufficiency. The AUTHORITY receives funding through the U.S. Department of Housing and Urban Development (HUD) to administer affordable housing programs.

The AUTHORITY envisions that the selected developer partner would be responsible for working with the AUTHORITY and its related entities (the AUTHORITY and its related entities, as used collectively herein, are the "Authority") in arranging the appropriate financing for all phases of the repositioning of Stewart Manor. The developer partner would also be responsible for seeking tax credits as well as other financing.

The Authority's repositioning path for Stewart Manor (for example, Section 18 demolition/disposition, RAD/project-based voucher Transfer of Assistance, mixed-finance development, or a combination) is subject to HUD approval. The selected developer partner will assist the Authority in evaluating rehabilitation versus redevelopment and in obtaining the required HUD approvals.

1.2 Rules, Regulations and Licensing Requirements

The developer partner shall comply with all laws, ordinances, and regulations applicable to the services contemplated herein, especially those applicable to conflict of interest. The developer partner must be familiar with all federal, state, and local laws, ordinances, codes, rules, and regulations that may in any way affect the services to be provided. The developer partner must not be debarred, suspended, or otherwise ineligible to contract with the AUTHORITY, and must not be listed as excluded in the System for Award Management (SAM.gov) or on HUD's Limited Denial of Participation List.

1.3 Contract Form and Issues

No contractual rights shall arise from the process of negotiation until such time as the AUTHORITY and the selected Developer Partner have signed an agreement. Work under the agreement shall commence upon issuance of a notice to proceed following execution of such agreement. Parties further concur that the AUTHORITY Board of Commissioners must approve the agreement and both agree to work diligently to implement changes as required, including changes required by HUD, NCHFA, lenders, or equity investors. The Authority intends to enter into a Memorandum of Understanding or predevelopment agreement followed by a Master Development Agreement. Any agreement with a term exceeding five (5) years, including options, is subject to HUD approval as required by HUD Handbook 7460.8 REV-3, Section 12.2(I), or through HUD's applicable mixed-finance, RAD, or Section 18 approvals.

1.4 Procurement Method (Qualifications-Based Selection)

This solicitation uses the qualifications-based selection (QBS) method under 2 CFR 200.320(b)(2), HUD Handbook 7460.8 REV-3 Sections 7.3 and 17.4, and 24 CFR 905.604(h)(1). Respondents are evaluated and ranked on qualifications only. The Authority will negotiate a fair and reasonable fee and business terms with the top-ranked respondent. If agreement cannot be reached, the Authority will terminate negotiations and proceed to the next-ranked respondent, and may not return to a respondent with whom negotiations were terminated (REV-3, Section 7.3(B)). The Authority has prepared an independent cost estimate before receipt of submissions (REV-3, Sections 3.2 and 17.4(C)).

1.5 Contact with the Sanford Housing Authority, Staff, Board of Commissioners and Residents During the solicitation period and subsequent evaluation process, respondents shall not contact the AUTHORITY's staff, consultants, board of commissioners, or residents other than the individual identified in the Solicitation Summary of this Request for Qualifications, except to file a protest under Section 1.10. Violation may result in disqualification.

1.6 Incurred Cost in Preparation of Qualifications

The respondent shall be responsible for all costs in preparing a response to this REQUEST FOR QUALIFICATIONS. All material and documents submitted by a prospective developer partner shall become property of the AUTHORITY and will not be returned. The developer partner(s) selected for further interviews and negotiations shall be responsible for all costs they incur during the process.

1.7 Section 3 and Affirmative Steps for Small, Minority, and Women's Businesses The AUTHORITY is committed to providing small businesses, minority businesses, women's business enterprises, and labor surplus area firms the opportunity to participate in its contracting, as required by 2 CFR 200.321.

Furthermore, it is the policy of the AUTHORITY to prohibit discrimination against any person or business in pursuit of these opportunities based on race, color, sex, religion, disability, familial status, or national origin and to conduct its contracting and purchasing programs so as to prevent such discrimination.

It is expected that the developer partner will submit, as a part of its response to this RFQ, a summary of the affirmative steps it will take under 2 CFR 200.321(b)(1)-(6) when subcontracting, and its Section 3 plan under 24 CFR Part 75 (Attachment F). The Authority encourages a participation goal of 20 percent for small, minority, and women's business enterprises; the goal is not a set-aside or quota, and no respondent will be selected or rejected based on the race or sex of its owners.

1.8 Conflict of Interest and Identity of Interest

Respondents must disclose any actual or potential conflict of interest or identity of interest with the Authority, its commissioners, employees, agents, consultants, or their immediate family members (Attachment C), as required by 2 CFR 200.318(c)(1), HUD Handbook 7460.8 REV-3 Sections 4.4 and 17.7, 24 CFR 905.604(h)(2), and the Authority's procurement policy. No person who participates in the decision-making process may obtain a financial interest or benefit from this procurement during his or her tenure or for one (1) year thereafter. Any firm that assisted the Authority in preparing this RFQ or the independent cost estimate may not compete.

1.9 Public Records and Confidential Information

Submissions become public records under N.C. Gen. Stat. Chapter 132 after award, subject to applicable exceptions. A respondent that considers any portion of its submission a trade secret must mark each such page "CONFIDENTIAL — TRADE SECRET" when submitted (N.C. Gen. Stat. 132- 1.2). Blanket designations of an entire submission will not be honored. During evaluation, submissions are held in confidence (REV-3, Section 7.2(H) and (J)).

1.10 Protests

Protests shall be submitted in writing to Anthony Goodson Jr, Chief Executive Officer, agoodson@sha-nc.org and must include the protester's name, address, and telephone number; the RFQ number and title; a detailed statement of the grounds; supporting documents; and the relief requested. Protests of the terms of this RFQ must be received before the submission deadline. Protests of a selection must be received within ten (10) calendar days after the protester receives notice of the selection. The Authority will issue a written decision stating the basis for its decision and any appeal rights under the Authority's procurement policy (REV-3, Section 10.4).

mailto:agoodson@sha-nc.org mailto:agoodson@sha-nc.org

PART II - PROJECT INFORMATION

2.1 General Overview

A. All communications regarding this RFQ shall be in writing, preferably by email, and must be directed to the following individual:

Anthony Goodson, Jr., Chief Executive Officer 504 N. First Street

B. Oral Communications: Any oral communications shall be considered unofficial and non-binding with regard to this RFQ.

C. Questions/Clarifications Submission Deadline: Any questions or requests for clarification shall be directed via email to the individual listed under paragraph A above on or before December 7, 2026.

Answers will be issued to all known recipients of the RFQ in a written addendum on or about December 18, 2026.

D. Delivery Requirement: Each respondent shall assume the risk of the method of dispatching any communication or submission to the AUTHORITY. The AUTHORITY assumes no responsibility for delays, delivery, or system failures resulting from the dispatch.

E. Reservation of Rights: The AUTHORITY reserves the right to determine, at its sole discretion, the appropriate and adequate responses to written comments, questions, and requests for clarification.

F. Amendments: Only written addenda issued by the AUTHORITY shall constitute an amendment to this RFQ. Respondents must acknowledge all addenda on Attachment A (HUD-5369-B, paragraph 3).

G. Only the AUTHORITY's official, written responses and communications shall be considered binding with regard to this RFQ. The AUTHORITY reserves the right to determine, at its sole discretion, the method of conveying official responses and communications pursuant to this RFQ (e.g., electronic mail to all known recipients, posting on the AUTHORITY's website, or other electronic means).

H. Modification of Solicitation: The AUTHORITY reserves the right to amend this solicitation by written addendum as deemed necessary where it is consistent with the AUTHORITY's policies or strategies to do so.

I. Modification of Contract: The AUTHORITY reserves the right to negotiate the scope of the development agreement with the selected respondent, to waive minor informalities and technicalities, and to make awards consistent with the AUTHORITY's policies, and the applicable laws governing HUD or other federally regulated programs.

J. Contractor Status: The developer partner shall be an independent contractor and will not be an employee of the AUTHORITY.

K. Funding Limitations: The AUTHORITY shall not be bound to any contract if funding or a required approval has been disallowed or denied by HUD.

L. Government Restrictions: In the event any governmental restrictions may be imposed that would necessitate alteration of the material, quality, workmanship, or performance of the goods or services offered, it shall be the responsibility of the successful developer partner to immediately notify the AUTHORITY in writing specifying the regulation which requires an alteration. The AUTHORITY reserves the right to accept any such alteration, including any reasonable price adjustments occasioned thereby, or to cancel the contract at no expense to the AUTHORITY.

M. Section 3: The successful developer partner shall comply with all applicable provisions of Section 3 of the Housing and Urban Development Act of 1968, as amended, 12 U.S.C. 1701u, and the regulations issued pursuant thereto, as set forth in 24 CFR Part 75, and all applicable rules, directives, and orders issued by HUD thereunder. Section 3 requires that, to the greatest extent feasible, opportunities for training and employment generated by a Section 3 covered project be given to public housing residents and other low-income persons residing in Lee County, North Carolina, and that contracting opportunities be provided to Section 3 business concerns.

N. Due Diligence: All procurement transactions shall be conducted only with responsible contractors, that is, those contractors who have the technical and financial competence to perform and who have a satisfactory record of integrity and performance. Where warranted and before awarding a contract, the AUTHORITY shall review the proposed contractor's ability to perform the contract successfully, considering factors such as the contractor's integrity, compliance with public policy, record of past performance (including vendor performance reports and contacting previous clients of the contractor), and financial and technical resources. Contracts shall not be awarded to debarred, suspended, or ineligible contractors. The AUTHORITY shall not contract with firms and/or individuals listed as excluded in SAM.gov or on HUD's Limited Denial of Participation list. If a prospective contractor is found to be non-responsible, a written determination of non-responsibility shall be prepared, and the prospective contractor shall be advised of the reasons for the determination.

O. Site Visit: The building is vacant and has been condemned; mold, asbestos-containing materials, and other hazards are present. Respondents may request an optional exterior site visit by appointment with the contact in paragraph A before the question deadline. Attendance is not mandatory and is not an evaluation factor (REV-3, Section 6.7). No one may enter the building without an Authority escort and the protective equipment the Authority requires. Information provided at a site visit is not binding unless issued by addendum.

2.2 General Scope of Services

The Authority is seeking qualifications from an experienced professional developer partner of affordable housing to plan, finance, and implement the rehabilitation or redevelopment of Stewart Manor as a tax credit project. We are seeking a developer who can provide financial resources to assist with the development of this project. Further, the developer partner is expected to provide the necessary research, documentation, and completion of an LIHTC 9% application for the next available LIHTC funding cycle. The AUTHORITY prefers to pursue a 9% LIHTC award. The developer partner will assist the AUTHORITY through this process and advise AUTHORITY staff on financing strategies, LIHTC rules, and the application process. Respondents should note that NCHFA's 9% preliminary application deadline has historically fallen in late January; a 2027-cycle preliminary application may not be feasible after a February 2027 selection, and respondents should address the realistic cycle in their schedules.

The successful firm is preferred to possess or have available consulting and technical expertise in the following HUD programs, HUD regulations, and related areas: Low Income Public Housing Program, Section 18 Demolition/Disposition, Rental Assistance Demonstration (RAD), project-based vouchers, mixed-finance development, Housing Choice Voucher Program, Tax Credits, and related programs of affordable housing and/or public housing units/communities. The firm must also excel in preparing low-income housing tax credit applications and providing technical guidance to housing authorities regarding LIHTC and other development/repositioning initiatives. This solicitation is subject to the project budget and fiscal provisions under which the AUTHORITY operates, and award of a contract is subject to funding availability and the AUTHORITY's determination, in its sole and absolute discretion, of its needs.

Through this solicitation, the AUTHORITY will select one developer partner. The selected developer partner will be required to propose financing strategies for the property. The strategies shall provide supporting documentation and information in sufficient detail to be competitive in the 9% LIHTC application process. This process may include feasibility studies, needs analysis, site scoring analysis, and others.

The AUTHORITY desires an aggressive approach which includes the submission of a 9% tax credit application in the next available cycle. If necessary, the AUTHORITY is considering using bonds and 4% tax credits as a secondary option.

The AUTHORITY also expects the developer partner to assist in the formulation of a viable relocation and return plan for former public housing residents (the building is vacant; residents have already been relocated), if appropriate and/or required, including compliance with the Uniform Relocation Act and HUD requirements as applicable. Secondly, the developer partner shall develop a financing plan and package specific to financing sources for the project. The developer partner, in the AUTHORITY's sole discretion, may be requested to serve in the role of Property Manager for the Tax Credit development for an initial period (see Section 2.3); however, the intent is for the AUTHORITY to serve as Property Manager, as the AUTHORITY currently has experience in this arena.

2.3 Preferred Concept(s)

The AUTHORITY desires to manage the Low-Income Housing Tax Credit units. However, in recognition of the investor's contribution and risk, there may be an initial period in which the investor or its designee may prefer to manage the property. At a mutually agreed upon and appropriate time, the AUTHORITY or its designated affiliate intends to resume management of the Tax Credit units.

2.4 Development Strategy

In undertaking this initiative, the Authority is seeking a developer partner that can provide creative and innovative ways of financing and repositioning its property in carrying out the mission of providing affordable housing for elderly households.

The development strategy must address the following:

A. Providing high-quality housing that will be attractive, energy-efficient, accessible (including Section 504/UFAS-compliant units), and will have long-term viability.

B. Identifying new forms of ownership, management, financing, resident selection, and service delivery that will assist the Housing Authority in carrying out its mission of providing high quality, safe living environments.

C. Leveraging funds to the maximum extent feasible by aggressively pursuing both public (state, local, and federal) and private (foundations, conventional, equity, and debt, etc.) sources of funding.

D. Ownership Structure: The developer partner and the Authority will develop an ownership structure that complies with all Federal regulatory requirements. The structure will identify and define the role of each entity involved. It is the intent of the Authority to negotiate a development agreement with its developer partner. The Authority reserves the right, in its sole discretion, to serve through a related Authority-controlled entity as co-general partner or to hold an interest in the general partner of the owner entity; provided, however, all ownership structures must be approved by HUD as required. The Authority will favorably review creative approaches that mitigate risk to the Authority and provide meaningful participation by the Authority. Specific fee amounts and splits will be negotiated only with the top-ranked respondent; do not include fee amounts in the submission.

2.5 Role of the Sanford Housing Authority

The Authority will play the following roles in the development process:

A. Housing Authority Role as Co-Developer and Receipt of Fees. The Authority expects to play a significant role in each phase of development and may, in its sole discretion, elect to serve through a related entity as a co-general partner of each phase owner entity. The Authority expects to receive an appropriate portion of the developer fee and cash flow for each phase. Any developer fee earned by the Authority is subject to HUD's cost control and safe harbor guidelines and the Authority's disclosure obligations (REV-3, Section 17.14(B)-(C)). Respondents should describe their approach to the Authority's co-developer role, but fee amounts will be negotiated only with the top-ranked respondent.

The Authority will consider ground lease payments or other fees in addition to the Authority's receipt of a portion of the developer fee and cash flow during negotiations.

B. Deal Structure and Asset Management: The developer partner will be responsible for providing comprehensive services with respect to the physical improvements. As landowner and asset manager, the Authority or its development entity will be concerned about preserving long-term asset value through attentive property management, and ensuring compliance with applicable HUD and Authority management requirements. The exact terms and relationships for property management are to be negotiated with the development entity. However, it will be the intent of the Authority to negotiate a specific management initiative that will transition the responsibility of property management to the Authority over an agreed upon period of time and upon mutually agreeable benchmarks that will be negotiated before closing.

C. Cooperate with Developer to Obtain Low Income Housing Tax Credits: The Authority will partner with the developer partner to obtain Low Income Housing Tax Credits ("LIHTC"). The developer partner will be responsible for preparing the LIHTC application for review, comment, and approval of the Authority. After receipt of the Authority's approval of an LIHTC application, the developer partner shall be responsible for making timely application for tax credits to develop each tax credit phase of the development. The developer partner may suggest an alternative financing structure when appropriate.

The Authority may, in its sole discretion, use its bonding authority or work with an eligible issuer to secure bonds for assisting in financing all identified development projects.

D. Option/Right of First Refusal: The Authority shall have a right of first refusal under Internal Revenue Code Section 42(i)(7) to acquire the property at the minimum price permitted under the Internal Revenue Code (i.e., existing debt plus exit taxes).

E. Legal Counsel: The Authority will retain legal counsel for the revitalization efforts for its sole use.

The developer partner is responsible for providing its own legal services.

F. Guarantees: The Authority will not provide completion, operating deficit, tax credit, or other guarantees to investors or lenders from public housing development, Capital Fund, or Operating Fund sources or public housing operating receipts (REV-3, Section 17.14(A)). All such guarantees are the developer partner's responsibility.

2.6 Role of Developer Partner

The developer partner shall be a partner in the effort to reposition Stewart Manor. The developer partner shall be required to work closely with the Authority throughout the revitalization effort. The developer partner will be responsible for:

A. Preparing and submitting a complete tax credit application(s) to the North Carolina Housing Finance Agency and other appropriate agencies in a timely manner.

B. Complying with all representations, terms, conditions, and requirements set forth in the Authority's agreements with HUD.

C. Work closely with the AUTHORITY's legal counsel regarding financing structuring as it relates to Internal Revenue Code Section 42, IRS Technical Advice Memoranda (TAMs), other relevant Code sections, and other applicable federal, state, and local regulations.

D. Obtaining any additional market analysis and appraisals needed to develop and obtain financing for the development.

E. Preparing applications to obtain 9% and/or 4% tax credits and bond allocations from the North Carolina Housing Finance Agency in accordance with the applicable Qualified Allocation Plan. The developer will also be responsible for soliciting the general contractor and other development team members, following the Authority's approval of the solicitation process.

F. Working with the AUTHORITY'S Architect for developing design and construction documents;

obtaining AUTHORITY approval, obtaining NCHFA approval on low-income tax credit units, and obtaining the City of Sanford approvals and permits. If the Authority elects to pursue bond financing, working with the Authority on submission of application and approval for bonds.

G. Determining realistic public and private financing sources, uses, schedule, and availability, assembling financing packages, preparing necessary financing applications, and providing all necessary financial guarantees and assurances.

H. Coordinating all development activities, including reporting and budget requirements, with the Authority.

I. Developing and implementing a Section 3 plan under 24 CFR Part 75.

J. The Authority will rely upon the developer to finance predevelopment activities but may, in its sole discretion, provide other financial sources. The Authority expects the developer to be responsible for all predevelopment costs.

K. Identifying various options concerning the following:

1. Feasible financial resources needed and available to implement the plan (i.e., private market lenders, limited partnerships, bond financing, tax credits, project-based vouchers, federal insurance programs, and equity).

2. The plan must address financing in satisfaction of due diligence and the underwriting requirements of conventional lenders, the U.S. Department of Housing and Urban Development (HUD), and the Authority.

L. The Authority envisions that there may be multiple sources of funding, which may include the following: (1) NCHFA Low-Income Housing Tax Credits; (2) Bond Financing; (3) Local Contributions;

(4) FHA Financing; (5) HOME Funds; (6) Federal Home Loan Bank Affordable Housing Program (AHP) Grants; (7) Project-based voucher or RAD assistance, if approved by HUD.

M. Seeking sources of additional funding through economic development grants, etc.

N. Recommending management and marketing options that will ensure the successful implementation of the development plan.

O. Procuring construction in accordance with HUD and Authority requirements. If the developer partner or an identity-of-interest entity wishes to serve as general contractor, it may do so only if its bid is the lowest bid submitted in response to a public request for bids and HUD approves through the development proposal process (REV-3, Section 17.7(B)(2)). Oversee construction and ensure completion in a timely and effective manner. Ensure all required occupancy permits and other necessary approvals are obtained after construction completion to permit occupancy and operation of the development.

P. Implement management policies and overseeing lease-up activities. Provide day-to-day management and maintenance for any initial period agreed under Section 2.3.

Q. Coordinating, conduct, and document all meetings with any and all former public housing residents and resident associations, neighborhood groups, city agencies, officials, HUD, Authority staff, businesses in the area, and any other stakeholders.

R. Identifying and securing appropriate detailed financial information to support the revitalization and any supportive service initiatives identified.

S. The selected developer partner shall provide written monthly status reports as well as written and verbal presentations to the Authority. Compliance with the Section 3 plan and the affirmative steps in Section 1.7 must be a part of the monthly status report.

T. Providing development, operating, and tax credit recapture guarantees, as required by lenders and equity providers. Provide a performance and completion guaranty to the Authority.

U. Securing an option/right of first refusal for the Authority with the LIHTC investor and minimizing investor exit taxes due when the Authority exercises its option or right of first refusal.

2.7 Property Information and Reports

Stewart Manor, 500 Dudley Street, Sanford, NC 27330 (listed by some sources as Dudley Avenue).

Stewart Manor was constructed circa 1975–1977 (original drawings dated 1975).

The building is five floors, multi-family, and elderly, approximately 74,180 gross square feet on approximately 5.6 acres.

Ninety-nine (99) apartments: 39 efficiency (studio), 56 one-bedroom, and 4 two-bedroom units (D3G PNA). The building is vacant.

Two hydraulic elevators. On-site generator. Common-area fire sprinkler and standpipe system.

Roof repaired in 2020 (approximately), patched, not replaced.

Building contains mold and asbestos and requires remediation and abatement.

The D3G Section 18 PNA found estimated rehabilitation costs of $15,127,146.65, or 73.50% of HUD Total Development Cost ($20,582,253), above the 62.5% elevator-structure threshold of 24 CFR 970.15(b)(2).

See Attached Field Observation and Recommendation Report by Stogner Architecture, PA, dated September 23, 2020.

See Attached Section 18 Physical Needs Assessment Report by Dominion Due Diligence Group (D3G Project No. 2025-000325) dated March 18, 2024.

These reports are provided for information only. Respondents should not rely on them as a complete statement of conditions.

PART III - PROCUREMENT PROCESS

3.1 Directions for Submission

Submit One (1) bound and secured printed copy of the qualifications with original signatures, and a labeled electronic copy in searchable PDF format on a thumb drive. An e-mailed PDF to the contact below is also accepted if it is under 10 MB; e-mailed submissions are held unopened until the deadline.

The time of receipt is the Authority's date-time stamp (hard copy) or the e-mail server time stamp (e-mail).

To assure that your submission arrives at the proper place, on time, and to prevent opening by unauthorized individuals, your submission must be identified on the envelope or package (or e-mail subject line) as follows:

Sanford Housing Authority - Developer Partner Qualifications – Stewart Manor – RFQ No. 2026-11 Anthony Goodson, Jr.

504 N. First Street

Submissions are due by 4:00 p.m. ET on Thursday, January 14, 2027. Late submissions will be handled under HUD-5369-B, paragraph 6, and REV-3, Section 7.2(I). Submissions will not be opened publicly.

3.2 Minimum Qualifications and Qualification Criteria

Minimum qualification (pass/fail): the respondent, or a member of its joint venture, must have served as lead developer on at least two (2) LIHTC projects placed in service within the past five (5) years.

Respondents that do not meet this requirement will not be evaluated further.

Development Team: The developer partner for this project must be capable of handling the development and ongoing oversight of the revitalization project. The selection committee will evaluate the following:

A. Previous experience developing and managing affordable housing, including both public housing and low-income tax credit housing.

B. Previous experience and success in securing financing for mixed-finance affordable housing, particularly Low-Income Housing Tax Credits and Tax-Exempt Bond Financing.

C. Previous experience providing development and financial advisory services to Public Housing Authorities, including Section 18, RAD, or mixed-finance repositioning.

D. Financial capability to complete the project.

The developer partner should be experienced in financing, managing, and developing multi-family rental housing, and may include construction, legal, and financing professionals as well as a licensed general contractor with demonstrated financial capability.

3.3 Qualification Response and Technical Response Requirements The developer partner shall be required to submit the following information in narrative and/or diagrammatic presentation:

A. Team Participants and their Specific Roles: All entities that comprise the team shall be identified, indicating their specialization(s) and specific contribution to the team. Development partners are encouraged to include specialists for all components of the program, including construction, legal, and financing professionals, as well as expertise in integrating community and supportive services. The project manager shall be clearly identified. Ultimately, the identified project manager shall be held responsible for the performance of all members of the development team. If the team members are unrelated parties, the managing party (Project Manager) should enter into individual agreements with each member to assure performance. Any small, minority-owned, women-owned, or Section 3 business team members shall be so identified.

B. Personnel and Table of Organization: Development partner shall submit an organizational chart showing all of the individuals that will be assigned to this development effort. This chart should reflect the hierarchy and lines of communication. Also, resumes of the key individuals shall be included with a detailed description of the responsibilities that they will be required to perform. Additionally, with respect to the project manager and lead individuals in each discipline, describe the degree to which such individuals and firms can dedicate their professional time to this initiative.

C. Financial Statements: Development partner shall provide its two (2) most recent audited financial statements (or CPA-reviewed statements if audited statements are not prepared). The statements shall show assets, liabilities, and net worth of the entity. These statements shall demonstrate the financial capacity of the developer partner, or the entity that would most likely be responsible for executing all applicable guarantees. Financial statements may be submitted in a separate sealed envelope marked "Confidential."

D. Financing Approach: The development partner shall include a discussion of its proposed financing approach. This narrative shall include the development team's reaction to the financing options included in this REQUEST FOR QUALIFICATIONS and include any suggested alternate or additional source of funding. The developer partner shall also indicate if the development entity plans to make any cash investment in the project and shall address its perspective on the priorities of the AUTHORITY as set forth in this RFQ. Do not include developer fee amounts, fee splits, or other pricing.

E. References: Three to five (3-5) references shall be submitted for each member of the development team. References that are relevant to the scope of work as anticipated in this REQUEST FOR QUALIFICATIONS are desirable.

F. Development Capacity: Development partner should indicate its ability to devote significant team resources to the project and list its current development pipeline.

G. Section 3 and Affirmative Steps: The response shall include a discussion of the approach and methods the development team would use to meet Section 3 requirements and take the affirmative steps in 2 CFR 200.321 when subcontracting (Attachment F). Demonstrated performance by team members in meeting Section 3 benchmarks and conducting outreach to small, minority, and women's businesses will be viewed favorably by the selection committee.

3.4 Certifications and Assurances

The REQUEST FOR QUALIFICATIONS, as a general requirement, specifies that all work be performed in accordance with professional standards, HUD regulations, requirements and criteria, and local codes, regulations, ordinances, and statutes. It is the Authority's full expectation and it will be a contractual requirement that the successful developer partner fully and routinely meet this requirement.

Provide all required certifications on forms included as Attachments of the REQUEST FOR QUALIFICATIONS as follows:

• Attachment A – Respondent Information and Acknowledgment of Addenda (signed)

• Attachment H – Instructions to Offerors – Non-Construction (HUD-5369-B; read and retain, no signature required)

• Cover Letter of Interest (Section 3.5.A)

• Attachment B – Development Experience Schedule

• Attachment I – Form HUD-5369-C, Certifications and Representations of Offerors – Non-

Construction (signed)

• Attachment D – North Carolina Certifications (debarment, Iran Divestment Act, Divestment from Companies That Boycott Israel, E-Verify) (signed)

• Attachment E – Non-Collusion Certification (signed; notarization not required)

• Attachment C – Conflict of Interest and Identity of Interest Disclosure (signed)

• Attachment F – Section 3 and Affirmative Steps Plan Summary

• Attachment K – HUD-50071, Certification of Payments to Influence Federal Transactions

(signed), and Attachment L – SF-LLL, Disclosure of Lobbying Activities (if applicable)

• Attachment J – General Conditions for Non-Construction Contracts (HUD-5370-C, Section I;

for information, incorporated into the agreement), and Attachment G – Required Federal Contract Provisions (2 CFR Part 200, Appendix II) (REV-3, Sections 10.5(B), 17.7(C), and 17.13)

3.5 Organization of Qualifications

The instructions below provide further guidance on the preparation of Qualifications. Their purpose is to establish the requirements, order, and format of qualifications so that submissions are complete, contain all essential information, and can be evaluated easily. Submissions should not exceed 50 pages, excluding resumes, financial statements, and attachments, on 8.5" x 11" pages with tabs matching the items below.

Assemble your submission in the order described below:

A. Letter of Interest: Each submission shall be accompanied by a letter of interest listing the development team members and identifying the primary contact person. The letter should summarize the team's qualifications and experience relevant to the proposed project and must be signed by a person authorized to bind the respondent.

B. Team Experience and Qualifications

1. Organizational Chart: Development partner shall submit an organizational chart showing all the individuals/firms that will be assigned to this development effort. This chart should reflect the hierarchy and lines of communication. Provide a narrative on the composition of the development team, including developer partner, developer attorney, general contractor, financial advisor (if applicable), property management company, and the anticipated relationships of these team members. Also, in accordance with the stated preferences of the Authority in this RFQ, please clearly identify how you propose to involve the Authority as a co-developer and in the ownership structure.

2. Profile of the Developer Partner:

• Provide an overview of developer partner experience in developing housing like what is proposed.

• Identify all market-rate, public housing, Section 8 Project Based, RAD, Section 18, and LIHTC efforts the development entity has been involved in (Attachment B).

• Provide profiles on the key staff, including the project manager, that are anticipated to be involved in the revitalization effort. This information shall specify key roles and previous experience with large housing development and revitalization efforts.

• Attach resumes of all key personnel of the development entity.

• Attach financial statements as described in Section 3.3.C.

• Attach references as described in Section 3.3.E.

3. Profile of Development Team Members: For each team member not directly employed by the development entity, provide an overview of their experiences in contributing to affordable housing development in a role as anticipated in your response to this solicitation. Include the resumes of all such team members.

4. List and Executive Summary of Recent Relevant Development Experience

5. Example of at least two (2) Recent Relevant Financing Models for Development Deals

6. Application Development Schedules – This schedule should denote the process in which the developer partner plans to aggressively meet the time frames in regard to the preparation and submission of tax credit application or applications (the AUTHORITY's highest priority). In addition, the AUTHORITY desires the developer partner to provide a proposed schedule or schedules for the proposed financing and development milestones, including HUD approvals.

7. Section 3 and Affirmative Steps (Attachment F)

8. Contract Requirements and Certifications: Provide all required certifications on forms included as attachments of the REQUEST FOR QUALIFICATIONS as described in Section 3.4.

9. Other Attachments: Development partner may attach, at the end of its submission, other promotional materials or work products that would demonstrate its experience and qualifications.

3.6 Evaluation of Qualifications

All submissions that meet the minimum qualification shall be evaluated based on the evaluation criteria outlined below. A Selection Committee of an odd number of members, three (3) or more, appointed by the Contracting Officer, shall be established and will be responsible for overseeing the selection process and making a recommendation for approval. Each member will sign a conflict-of-interest and nondisclosure certification before receiving submissions (REV-3, Section 7.2(J) and (K)(2)). If residents or local government staff serve on the committee, Authority staff will constitute a majority (REV-3, Section 17.9(B)). The Selection Committee shall score and rank the respondents based on the established criteria and point system as detailed below. The Committee may invite the highest-ranked respondents (generally two to four) to an interview with the Selection Committee and may adjust scores based on the interviews, using the same criteria.

The Selection Committee may consider unacceptable any submission for which critical information is lacking, or the submission represents a major deviation from the requirements of this RFQ. Minor omissions, such as incomplete references, may be, at the sole option and discretion of the Authority, corrected subsequent to the submission due date.

3.7 Evaluation Factors

The following evaluation factors shall be used in ranking respondents, with a total possible score of 100 points. Price is not an evaluation factor (REV-3, Section 7.3(B)). Factors not listed below will not be considered.

Evaluation factor What will be evaluated Max.

points

1. Development Experience and Qualifications

Experience as lead developer in the development, financing, and management of affordable rental housing, including LIHTC, public housing repositioning (Section 18, RAD, mixed-finance), and elderly housing; experience with the NCHFA Qualified Allocation Plan; rehabilitation or redevelopment of mid-rise buildings; record of on-time, on-budget completion; references.

2. Financial Capacity Overall financial strength; ability to fund predevelopment costs and provide required guarantees; record of securing equity, debt, and other sources for comparable projects.

3. Development and Financing Approach

Understanding of the Authority's goals and of HUD requirements;

proposed financing approach and alternatives; approach to the Authority's co-developer and ownership role; long-term property and asset management and transition approach; involvement of former residents; realistic schedule. No fee amounts.

Evaluation factor What will be evaluated Max.

points

4. Team Capacity and Key Personnel

Qualifications and availability of the project manager and key staff; completeness of the team (legal, construction, finance, management); current workload.

5. Section 3 and Affirmative Steps

Quality of the Section 3 plan (24 CFR Part 75) and affirmative steps for small, minority, and women's businesses (2 CFR 200.321); past performance.

TOTAL 100

3.8 Selection and Negotiation Process

The AUTHORITY will use the following process to evaluate submissions. In its sole discretion, the AUTHORITY may change the schedule by written addendum.

A. Review for Compliance with Submission Requirements: Submissions that arrive at the AUTHORITY by the due date and time will be opened after the deadline, in confidence, by the AUTHORITY's Chief Executive Officer or a designee. The AUTHORITY will initially review all submissions to determine if they comply with the submission requirements and the minimum qualification specified in this RFQ.

The AUTHORITY may reject any submission without further review if the AUTHORITY in its sole judgment determines that it does not comply with these requirements. The AUTHORITY may, in its sole option and discretion, allow a respondent to later correct minor omissions, informalities, or irregularities.

B. Ranking: An Evaluation Committee that the AUTHORITY will convene (the "Committee") will review all qualifying submissions according to the criteria set forth in this RFQ. Each member will score individually, and the Committee will then meet to reach a consensus score and ranking (not an average of individual scores). The Committee will rank the respondents according to said criteria and prepare a written evaluation report.

This is the start of the file's text. The full file is on GovTribe.