This Statement of Work (SOW) details a project for maintaining airfield paint and rubber removal at Offutt Air Force Base, designated as Project SGBP 26-0002. The primary objectives include applying airfield paints and reflective media to paved surfaces and removing 85% of rubber deposits from 100% of the marked runway area. The contractor must furnish all labor, equipment, materials, and perform work according to specified standards (UFC 3-260-04, UFGS standards), including applying various markings such as white and yellow reflective/non-reflective paints for runway designations, edge lines, chevrons, taxi lines, and vehicle driving lanes. The project requires careful paint and rubber removal without damaging pavement surfaces, cleaning and disposing of old materials, and providing a full 1-year warranty on all materials and labor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
PROJECT: SGBP 26-0002
PROJECT NAME: MAINTAIN AIRFIELD PAINT & RUBBER REMOVAL. F666
OBJECTIVES:
Contractor shall furnish all paint, labor, equipment, and materials and perform all operations in connection with the application of airfield paints and reflective media to paved (concrete and asphalt) airfield surfaces, and airfield vehicle driving lane surfaces.
Contractor shall furnish all labor, equipment, tools, appliances, and materials required to remove 85 percent of the rubber deposits from 100 percent of the rubber covered area marked by the drawings on the airfield active runway.
Reference attached map for project scope locations.
GENERAL REQUIREMENT:
Project includes, but is not limited to, the following work elements. The contractor shall furnish all materials, labor, transportation, equipment, special tools, expertise, supervision, and services requested to fulfill the requirements of this contract. All task specifications of this Statement of
Objectives (SOO) will herein be referred to as “requirements”. No alterations, additions, or deletions shall be made unless by prior approval of the government Project Manager and the government
Procuring Contract Officer (PCO). The work shall conform to UFC 3-260-04, UFGS 32 01 11.51, UFGS 32 17 23.19, and manufacturers recommendations. The Contractor shall abide by all required safety regulations, including OSHA requirements, and provide all required PPE. Work shall be completed in a neat, substantial, and competent manner.
The contractor shall perform quality assurance activities that conform to the quality assurance processes outlined in International organization of Standards (ISO) 9001, Quality Management
Systems. The Contractor shall use SOO requirements, ESE-SIT-0001, AFI 31-101, and Original
Equipment manufacturer (OEM) guidelines to evaluate whether or not the equipment and systems are being installed and integrated properly.
During construction the Government will occupy the existing facilities. The contractor shall not restrict nearby pedestrian or vehicular traffic and shall coordinate with the Contracting Officer to facilitate usage. The Contracting Officer shall be notified not less than 15 calendar days in advance of any interruptions in building utilities / services, which will be described in writing.
PROJECT REQUIREMENT:
- Upon request from the Contractor, a site visit can be arranged prior to bid or starting work.
- Work shall be performed in coordination with the Government to ensure needed notifications to users on cooling and heating outages.
- The Contractor shall measure and confirm paint and rubber removal measurements in-field if necessary to meet project objectives.
- Marking on airfield pavements shall be applied in widths as specified by the drawings provided at the time of award and shall consist of white reflective and non-reflective paint, black non-reflective, and yellow reflective and non-reflective paint.
- Marking of airfield shall conform to UFC 3-260-04, AIRFIELD AND HELICOPTER
MARKINGS. Airfield markings on the runway include yellow reflective chevrons, yellow reflective edge lines, white reflective runway designation numbers, center line, active edge line and bar markings in accordance with UFC 3-260-04. Aircraft taxi lines on the airfield, taxiways and aprons shall consist of three 6-inch width stripes of one yellow reflective bordered on both sides by 6-inch width black non-reflective paint.
- Airfield vehicle driving lanes shall consist of 4-inch to 6-inch width stripes of white non-reflective paint, as specified by the drawings at time of award. Vehicle driving lane arrows shall also be painted and may require hand painting with paint rollers. Restrictive area markings and warning sign stenciling (red, black and white paint) to match existing.
- The paint removal is to be completed without damage to the pavement surface, joints, and joint and crack seals, or any other government property. The term "paint" used herein may include obsolete paint markings and/or loose and poorly bonded paint buildup.
- The rubber removal is to be completed without damage to the pavement surface, joints, and joint and crack seals, or any other government property.
- The Contractor shall clean up and dispose of all old paint and rubber, as well as any trash generated from the work. Refuse shall be disposed of off-Base in accordance with Offutt AFB Environmental
Special Conditions section 01 57 19.
- The Contractor shall provide a full 1 year warranty on all material and labor.
- The Contractor shall be responsible for repairing any damage to Government property resulting from contractor activities, assuring the property is returned to its original or better condition.