This solicitation requests quotes for the removal of an existing gas-fired steam boiler and installation of an electric steam boiler, blowdown separator tanks, and water treatment systems at the NOAA Northeast Fisheries Science Center laboratory in Milford, Connecticut. Quotes are due by August 11, 2023. The work is a total small business set-aside under NAICS code 238220 with a size standard of $19.0M. Davis Bacon wage rates apply. The selected contractor must complete all work within 90 days of award. Quotes must include references, past performance questionnaires, and a technical approach.

View the file

Other files

File Type Posted
Past Performance Questionnaire.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

THIS RFQ IS IS NOT A SMALL BUSINESS SET-ASIDE

15. DATE OF QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

b. TELEPHONE

AREA CODE

NUMBER

STANDARD FORM 18 (REV. 6-95) Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

8. TO:

b. COMPANYa. NAME

c. STREET ADDRESS

d. CITY e. STATE f. ZIP CODE

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

c. CITY

d. STATE e. ZIP CODE

7. DELIVERY

FOB DESTINATION

OTHER

(See Schedule)

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)

IMPORTANT: This is a request for information and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or service. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NUMBER

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations are are not attached.

13. NAME AND ADDRESS OF QUOTER

a. NAME OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

PAGE OF PAGES

1. REQUEST NUMBER 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NUMBER 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG. 1

RATING

5a. ISSUED BY 6. DELIVER BY (Date)

5b. FOR INFORMATION CALL (NO COLLECT CALLS)

NAME TELEPHONE NUMBER

AREA CODE NUMBER

NF-FM7820-23-02257

NF-FM7820-23-02257

1305M323QNFFM0138

WESTERN ACQUISITION DIVISION

325 BROADWAY, SOU6

BOULDER CO 80305

MICHELLE WALTON

MICHELLE.WALTON@NOAA.GOV

Please See Continuation Page for Line Item Details

303 578-6582 AQUACULTURE SUSTAINBILITY BRNC

212 ROGERS ROAD F/NEC82

MILFORD

06460-6499CT

AUG 11, 2023

NOV 30, 2023

DUNS:

FM782000

SCHEDULE Continued

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

The magnitude of this project is between $100,000.00 and $250,000.00.

This is a total small business set-aside under NAICS code 238220 with a size standard of $19.0M.

Davis Bacon Wage Determination rates CT20230023, Modification 8 are incorporated and may be viewed at SAM.gov.

SITE VISIT:

The government recommends a site visit and vendors must pre-register with Domenick Capomolla at least 2 working days in advance via phone or email.

NOAA Northeast Fisheries Science Center 212 Rogers Ave Milford, CT 06460

Contact Domenick Capomolla at 203-627-0994 or email at domenick.capomolla@noaa.gov

All Offerors are strongly encouraged to make a site visit to inspect all proposed work and to acquire all necessary site information to properly prepare their Quote. Failure of the Offeror to visit the site and acquire all necessary site information to properly prepare the quote shall not be acceptable cause to justify a later request for additional costs after Contract Award. Any questions that come up at the site visit must be provided to Michelle Walton via email at michelle.walton@noaa.gov no later than Aug 9, 2023, 12:00pm MST. No questions will be answered on site.

Offerors must provide a detailed technical approach writeup with their quote regardless of whether or not a site visit was made and it cannot be a reiteration of the Statement of Work.

Offerors shall assume that the Government has no prior knowledge of them or their capability.

Quote shall include at least two references for similar services including the phone number, full address, and email address.

In addition, vendors shall complete Blocks 1 through 4 on Page 1 of the Past Performance Questionnaire.

The vendor is required to send the Past Performance Questionnaire to those Government and commercial activities provided by the vendor in their submission and email the completed survey form directly to MichelleWalton at michelle.walton@noaa.gov by the

DUE DATE OF THIS SOLICITATION

SERVICES, NON-PERSONAL, TO PROVIDE ALL

EQUIPMENT, LABOR, AND MATERIALS (UNLESS

OTHERWISE PROVIDED HEREIN) NECESSARY TO:

Demo existing natural gas steam boiler and install one autoclave electric steam boiler, one blowdown separator tank and one water treatment system in Building #1 at the Milford Lab, Milford, CT.

See attached, incorporated Statement of Work for exact detail.

All work is to be completed 90 days after award or sooner

1.00 JB

PAGE 2 OF 63 1305M323QNFFM0138

Table of Contents

Statement of Work

Construction Clauses

Davis Bacon Wage Determination

PAGE 3 OF 63 1305M323QNFFM0138

CLAUSES

Statement of Work

PAGE 4 OF 63 1305M323QNFFM0138

Statement of Work

For

NF-FM7820-23-02257

Two Autoclave Electric Steam Boilers in Building #1

At the Northeast Fisheries Science Center Milford CT Laboratory 212 Rogers Ave Milford CT 06460

DESCRIPTION

A. The National Marine Fisheries Service Laboratory is located at 212 Rogers Ave Milford CT 06460. Contact Domenick Capomolla, for a pre-bid job site inspection, 203-627-0994 cell phone or email at domenick.capomolla@noaa.gov Coordinate site visits at least 48 (two working days) hours in advance of intended site visit.

B. The National Marine Fisheries Service (NMFS), a part of the National Oceanic and Atmospheric Administration (NOAA) of the Department of Commerce (DOC), is a governmental agency charged with the mission of stewardship for living marine resources.

C. The Contractor shall be fully knowledgeable of all requirements of the contract documents and shall make themselves aware of all job site conditions that will affect their work.

D. The Contractor shall verify all dimensions and equipment prior to submitting bid quotation.

E. The Contract shall demolish and remove existing gas fired steam boiler. In addition, install one (1) new SUSSMAN ES-100 electric steam boiler or equivalent.

F. The Contractor shall demolish and remove all necessary water, steam and gas piping.

G. The contractor shall furnish and install all necessary electrical and plumbing to ensure proper installation as stated in the contract documents.

H. The Contractor shall provide and install all necessary hardware such as hangers, valves, breakers, wiring, controllers and fittings.

PAGE 5 OF 63 1305M323QNFFM0138

Site and Project Location: 212 Rogers Ave Milford, CT 06460

PRE-BID SITE VISIT

It is recommended that a site visit be conducted prior to submitting a quote in order to view site conditions, verify locations, verify measurements, and equipment. Contact Domenick Capomolla at 203-627-0994 cell phone or email at domenick.capomolla@noaa.gov to schedule a site visit between the hours of 7:30 AM– 3:00 PM, Monday through Friday. Please plan to coordinate site visits at least two working days in advance of the intended site visit.

PAGE 6 OF 63 1305M323QNFFM0138

GENERAL

A. The Contractor shall comply with all applicable codes and other published instructions for the installation of specified products, and installation requirements per the contract documents.

B. The Contractor shall have at a minimum 10 years of verifiable experience installing steam boiler systems for proper installation.

C. The Contractor shall provide knowledgeable tradesmen for installation of steam boiler systems and shall follow the applicable codes for the state of Connecticut.

D. The Contractor shall be responsible for tracing, verifying and isolating all utilities before construction begins.

E. The Contractor is responsible for his/her own security arrangements including sub Contractor’s materials, tools, equipment, and personnel.

F. Work in Progress: The Contractor shall be responsible for the protection and safe keeping of all work in progress prior to final acceptance by the Government.

G. All methods, materials and workmanship provided by the Contractor under this contract shall be performed in accordance with professional industry standards, manufacturer's specifications and shall comply with applicable codes for construction. Field measurements are the responsibility of the Contractor.

H. Professional agencies, associations, councils, institutes, codes, and standards as required or referenced by law, statue or manufactures recommendation including those listed in Appendix #5 are part of the contract requirements.

I. All permits and fees are the responsibility of the Contractor.

J. Appendix 1: Boiler and equipment cut sheets.

K. Appendix 2: Acronyms.

L. Appendix 3: Professional Organizations

SPECIFIC TASKS

A. The Contractor shall provide knowledgeable Plumbing/Electrical tradesmen to install one

(1) SUSSMAN ES-100 electric steam boilers or equivalent.

B. The Contractor shall provide knowledgeable electrical tradesmen to install all required electrical circuitry and electrical breakers.

C. The Contractor shall provide knowledgeable electricians to install (1) 300 amp 208 volt three phase breaker.

D. The Contractor shall provide knowledgeable electricians to make all necessary low voltage and high voltage connections on all equipment.

E. The Contractor shall provide knowledgeable plumbers to make all necessary connections to all equipment.

F. The Contractor shall provide all equipment, tools and labor to demolish, remove existing Columbia gas fired steam boiler.

G. The Contractor shall cap or remove all existing gas, steam and water lines that will no longer be in use.

H. The Contractor shall install one (1) SUSSMAN blowdown separator tank. Model # BDT- ASME 42 or equivalent.

I. The Contractor shall install one (1) GETINGE SRB 800 RO water treatment system or equivalent.

PAGE 7 OF 63 1305M323QNFFM0138

J. The Contractor shall insure proper installation of all system components.

K. The contractor shall supply all ancillary equipment, materials not specifically referenced required to complete the work such as supports, hangers, and hardware, etc.

L. The contractor shall ensure any existing penetrations through the existing walls and flooring are properly refastened and sealed upon completion of this project.

ACCESS TO WORK SITE

A. All persons employed within the boundaries of the property or restricted-access areas therein, and all persons permitted to enter such property and areas shall comply with the security regulations for the NEFSC Milford Laboratory.

B. The Government reserves the right to close down the job site and order Contractor personnel off the premises in the event of a national emergency or a shut-down, for as long as security problems persist. The Contractor may only return to the site with verbal approval from the TPOC/COR.

C. The Government reserves the right to exclude or remove from the site or building any employee of the Contractor or a sub-Contractor whom the Government deems incompetent, careless, insubordinate or otherwise objectionable, or whose continued employment on the work is deemed by the Government to be contrary to the public interest.

FINAL ACCEPTANCE AND INSPECTIONS

A. Inspection of work to be performed by the NEFSC Facilities Operations Manager - TPOC/COR. Any corrective action required because of the inspection will be accomplished prior to final billing.

B. The Contractor may be notified of deficiencies in performance in writing by the TPOC/ COR. Oral deficiency notifications will be confirmed in writing. The Contractor shall take prompt corrective action upon notice of deficiency.

C. The Contractor shall advise the Government when all work is completed. The Government will not accept the work until it determines that all work has been satisfactorily completed within the terms of the contract.

EXISTING CONDITIONS

If discrepancies are discovered between the existing conditions and those noted on the SOW/drawings, immediately notify the GPC/TPOC. Upon receipt of Bidding Documents, verify documents are complete. Notify GPC/TPOC if documents are incomplete. Immediately notify GPC/TPOC upon finding discrepancies or omissions in Bidding Documents.

JOB SITE PROTECTIONS

A. It shall be the responsibility of the Contractor to protect the property of others as well as his/her own property, and to repair or replace any property damaged by the Contractor in fulfilling this project. The Contractor shall keep the area clean and upon completion of

PAGE 8 OF 63 1305M323QNFFM0138

the project, the Contractor shall clean up the work area and remove all debris from the job site in a timely and legally acceptable manner so as not to detract from the aesthetics or the functions of the building. Government dumpsters will not be available for Contractor use. The Contractor shall repair or be responsible for costs to repair all property damaged during the performance of work.

B. The Contractor shall take precautions to prevent the spread of dust, moisture and debris.

The Contractor shall provide labor and materials to construct, maintain and remove necessary temporary enclosures to prevent dust or debris in the construction area(s) from entering the remainder of the building.

C. All work shall comply with applicable Federal, State and Local regulations

PERIOD OF PERFORMANCE

A. The actual start date shall be coordinated with the TPOC/COR.

B. Upon notice to proceed, the Contractor shall be required to complete work within 90 calendar days.

SUBMITTALS

The Contractor shall submit the following:

Schedule (5 days after date of award) Manufacturer's cut sheets.

Safety Data Sheets (SDS) (10 days after date of award) Safety Plan (5 days after date of award)

DELIVERY, STORAGE, HANDLING, AND PROTECTION

A. Deliver materials to the job site in the manufacturer’s original, unopened containers or wrappings with the manufacturer’s name, brand name and installation instructions intact and legible. Deliver in sufficient quantity to permit work to continue without interruption.

B. Comply with the manufacturer’s written instructions for proper material storage.

C. Any damaged materials shall be removed and replaced at the Contractor’s expense.

D. Care shall be taken to provide protection of surrounding structures, hallways and building structures.

QUALITY CONTROL

A. The Contractor shall submit manufacture cut sheets and other specification literature for all materials to be installed for the TPOC/COR approval.

B. All work described in the Statement of Work shall comply with the manufacturers installation guidelines.

C. The Contractor shall furnish all labor, materials, tools, transportation, services and supplies as stated in this requirement.

PAGE 9 OF 63 1305M323QNFFM0138

D. Work shall be completed in accordance with the construction industry standards and codes.

E. The Contractor shall supply the TPOC/COR with the onsite supervisor contact information and any other key personnel.

WARRANTY

The Contractor shall provide a written warranty for service including labor and materials for a period of one year from the date of startup with no dollar limitation. Including but not limited to all manufacturers warranties.

USE OF THE PREMISES

Before beginning work, the Contractor shall secure approval from the TPOC/COR for the following:

A. Contact the TPOC/COR for parking information and facility access.

B. Access to the site.

C. Areas permitted for storage of materials and debris.

D. Security: Obey the government’s requirements for personnel identification, inspection and other security measures.

E. Use of facility restrooms are provided.

F. The NEFSC is a smoke free campus. The Contractor and its employees shall adhere to all applicable rules and regulations regarding maintenance of a smoke free environment on the job site.

G. Use of Government facilities

1. Water and electricity for construction purposes are available at the work site.

2. Contractor shall provide storage for tools and materials. The Government is not responsible for providing storage or security of materials, tools, or equipment.

H. The premises will be occupied during the performance of the work. Contractor to coordinate work with the TPOC/COR to accommodate the work schedule, continuing access and completion date.

I. Working hours shall be 7:00 AM – 3:30 PM (M-F). Contractor shall observe all federal holidays.

WORKMANSHIP

All work shall be of highest quality and in strict accordance with the manufacturer’s published specifications and to the building owner’s satisfaction, most recent codes and standards.

QUALITY ASSURANCE

A. Unless otherwise noted in the contract documents, Contractor shall comply with the manufacturer’s current specifications and details.

B. The Contractor shall provide an adequate number of experienced workers regularly engaged in this type of work who are skilled in the application techniques of the materials specified.

PAGE 10 OF 63 1305M323QNFFM0138

C. There shall be a site superintendent on the job site at all times while work is in progress.

The site superintendent must be an employee of the general Contractor and on the site all times during the course of any ongoing work.

D. There shall be no deviations made from this specification or the approved shop drawings (if any) without the prior written approval of the CO/TPOC/COR. Any deviation from the manufacturer’s installation procedures must be supported by a written certification on the manufacturer’s letterhead and presented to the TPOC/COR for consideration.

E. All substitution requests for products, equipment, materials and methods described within the contract documents shall be submitted to the TPOC/COR. Substitute products will be considered when the request is submitted in writing to the TPOC/COR. The CO/TPOC/COR will have seven (7) working days to approve/disapprove the substitution request. Substitution requests shall not result in schedule extensions.

FACILITIES AND CONTROLS

A. The Contractor shall remove and dispose of all debris and trash from the job site in a timely and legally acceptable manner to not detract from the aesthetics or the functions of the building.

B. Contractor shall comply with all applicable Federal, State, and local laws and regulations concerning environmental pollution prevention control and waste disposal.

C. Contractor shall immediately inform the TPOC/COR of any environmentally hazardous situations that may arise as well as contact required regulatory agencies.

D. Perform daily clean up to collect all wrappings, empty containers, paper, and other debris from the project site. Upon completion, all debris must be disposed of in a legally acceptable manner. The Contractor shall ensure that the project area and areas adjacent to the project area are maintained in a clean and safe condition.

SAFETY

A. The Contractor shall be responsible for all means and methods as they relate to safety and shall comply with all applicable OSHA, NEC, NFPA, and EPA, local, state and federal requirements. Safety shall be the responsibility of the general Contractor. All related personnel shall be instructed daily to be mindful of the full time requirement to maintain a safe environment for the facility’s occupants including staff, visitors, customers and the occurrence of the public on or near the site.

B. The Contractor shall comply with the requirements of 29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards, and Health Administration (OSHA) General Industry and Health Standards and 29 CFR, part 1926 Construction Standards. The Contractor shall promptly correct any non-complying work or conditions. Contractor shall be responsible to ensure its work does not affect the safety of the public or employees of the Government. Neither the Government nor its representatives shall bear any responsibility for safety precautions at the project work site. If, however, in the opinion of the TPOC/COR a life-threatening condition exists, the TPOC will orally (to be confirmed in writing) require the Contractor to immediately suspend work in the affected area until the condition is corrected. Whenever Contractor’s operations may create a hazardous condition, it shall at its sole expense, furnish, install and maintain such guards, fences, barricades, railing, light, signs, or other devices

PAGE 11 OF 63 1305M323QNFFM0138

necessary to prevent accident, injury or damage to people or equipment.

C. Five days prior to start of work, the Contractor shall submit a safety plan. To include but not limited, open flames, welding, debris, cleanup, workplace safety methods, and emergency procedures. The Safety Plan must be available on site at all times and must be reviewed with all sub-Contractors working under this contract for the duration of the contract project.

E. It is the Contractor’s responsibility to ensure all employees; sub-Contractors, vendors, and other company representatives adhere to all safety rules, regulations, policies and practices.

F. Contractor shall observe lock/out tag/out regulations and as required by OSHA.

G. The Contractor shall keep the project site in a neat and orderly condition at all times.

JOB CONDITIONS, CAUTIONS AND WARNINGS

A. Safety Data Sheets (SDS) must be on location at all times during the transportation, storage and application of materials. A separate set shall be given to the TPOC/COR fifteen (15) days prior to starting of the work.

B. The Contractor shall not cause or permit any hazardous material to be brought upon, kept or used in or about the premises by its agents, employees, or subcontractors without the prior consent of the TPOC/COR. Hazardous materials that are necessary to the performance of this contract shall be used, kept and stored in a manner that complies with all laws regulating any such hazardous material brought upon or used or kept at this site.

Contractor shall provide Safety Data Sheets to the TPOC/COR for any hazardous materials used in the performance of this contract.

C. As used herein, the term “Hazardous Material” means any hazardous or toxic substance, material, or waste, including but not limited to, those substances, materials, and wastes listed in the Department of Transportation Hazardous Material Table (49 CFR 172.101) or by the Environmental Protection Agency as hazardous substances (40 CFR Part 68.130) and amendments thereto, petroleum products, or such other substances, material, and wastes that are or become regulated under any applicable local, state, or Federal law.

D. Site condition in and around the boiler is limited. Working space between boilers, walls and ceilings is limited.

PERSONNEL

A. The Contractor shall provide proof that all on-site employees are US citizens or legal aliens.

B. The Contractor shall not employ personnel with felony convictions, or with a record of narcotics use, for work at the Milford Laboratory.

PAGE 12 OF 63 1305M323QNFFM0138

APPENDIX 1

MRG 1200

RO Water Treatment Systems Product Specification

Municipal water treatment facilities primarily treat water to remove microbiological contaminants to provide safe drinking water but do little to remove organic and inorganic content that adversely affects the performance of water dependent medical and research reprocessing equipment.

Getinge water treatment systems are designed to supply high quality water for point-of-use steam generators;

medical washer disinfectors; cart washer disinfectors; lab glassware washers; and cage & rack washers. When used as instructed, the Getinge RO systems eliminate up to 99% of total dissolved solids (TDS); volatile organic compounds;

water hardness (CaCO3); and chlorine additives.

PAGE 13 OF 63 1305M323QNFFM0138

Quality Statement

Application

Confidence in the Getinge group is the most important quality criteria. This is the hallmark of all our external and internal commitments, activities and products. Products and services supplied by Getinge conform to the agreed terms and expectations. The achievement of these quality goals is the basis for continued competitive and successful enterprise.

The Getinge MRG 1200 Series are complete water treatment systems that includes an RO processor, an atmospheric float tank for storage and delivery, and a microprocessor controller.

Not intended to be used for drinking water.

ustomer Reference 1/4

PAGE 14 OF 63 1305M323QNFFM0138

PAGE 15 OF 63 1305M323QNFFM0138

PAGE 16 OF 63 1305M323QNFFM0138

Benefits •

Extends equipment life Reduces or eliminates boiler scale Increases heater element life

Equipment Features • •

115V, 50/60Hz, 1-Phase processor Floor mounted processor HW & CW mixing valve Atmospheric float tank with delivery pump Tank pressure gauge Stainless steel membrane housing Integrated pre-treatment Pre- and post-filter pressure gauges Permeate TDS/Conductivity meter Processor pump 55 dB A sound pressure level

Codes •

ETL Listed to IEC/UL Standard 61010-1 Certified to CAN/CSA C22.2 No. 61010-1

Ordering Information Mark your selections:nn

== Selected option

Models MRG 1200: 1200 Gallon-Per-Day (4542 LPD) System with 50-Gallon (189 L) Float Tank

Options Post-Treatment -ntt -Polyphosphate is used to increase conductivity for level sensing devices and to neutralize the effects of the slightly acidic nature of RO water.

MRG 1200-AB: 1200 Gallon-Per-Day (4542 LPD) System with 50-Gallon (189 L) Float Tank with Auto Bypass operation

Getinge USA, Inc.

17777 E. Henrietta Roadd Rochester NY 146233 Phone: 800.475.90400 info.northamerica@getinge.com

Getinge Canada, Ltd.

6685 Millcreek Drive, Unit 3 Mississauga, ON L5N 5M55 Phone: 800.387.33411 info.northamerica@getinge.com

PAGE 17 OF 63 1305M323QNFFM0138

Getinge Group is a leading global provider of products and systems that contribute to quality enhancement and cost efficiency within healthcare and life sciences. We operate under the three brands of ArjoHuntleigh, Getinge and Maquet.

ArjoHuntleigh focuses on patient mobility and wound management solutions. Getinge provides solutions for infection control within healthcare and contamination prevention within life sciences. Maquet specializes in solutions, therapies and products for surgical interventions, interventional cardiology and intensive care.

ROWater_PS_MRG1200_0115_RevA © 2015 Getinge USA, Inc. Printed in U.S.A. ArjoHuntleigh, Getinge, and MAQUET are registered trademarks. We reserve the right to make changes to specifications and product information.

PAGE 18 OF 63 1305M323QNFFM0138

Optional Equipment (con’t)

VACUUM BREAKER SYSTEMS

• For model ES boilers P/N ES89369

• For model SSB boilers P/N SSB89369

A vacuum breaker will prevent a boiler from flooding as a result of the steam condensing internally and creating a vacuum after boiler shutdown. The breaker allows air to enter the boiler shell breaking the vacuum. This system is a must for boilers connected to a condensate return tank. The vacuum breaker consists of a spring-loaded disc and associated piping and is factory plumbed to the boiler. The SSB89369 is of stainless steel construction.

AUTOMATIC BLOWDOWN SYSTEM

• Extends life of boiler

• Saves labor costs

• Starts the boiler automatically every day

• Shuts down the boiler every day

• Automatically blows down the boiler every day

• Completely programmable, can skip days, different start and shutdown times, different operational durations.

• ES81600 for all model boilers.

A stainless steel, motor driven straight-through, self-cleaning ball valve with Teflon seats handles particles and dirty fluid without the use of an up-stream strainer or other cleaning device. A timer (Standard analog time clock is set for two hour time intervals, optional digital time clock can be programmed to one minute intervals.) and electronic time delay relay control the boiler and the blowdown valve. A pilot light indicates when the blowdown valve is open.

The valve shall be plumbed to a proper drain or receptacle.

An automatic blowdown system can be installed on any boiler, regardless of size operating pressure or operating duty cycle.

BLOWDOWN SEPARATORS (see page 18)

Sussman Boilers Installation, Operation & Maintenance Manual

• For models ES12-48 and SSB12-48 p/n BDT-ASME36

• For models ES60-180 and SSB60-180 p/n BDT-ASME42

A separator accepts the flash steam and effluent from the boiler blowdown and reduces the temperature and pressure to insure a safe discharge of water and sludge. Steam flash and pressure are absorbed and pass harmlessly to the outside via a vent. The separator design utilizes a water seal at the outlet, which permits the operator to introduce cold water from the bottom to mix with the hot water and boiler steam in the blowdown separator. This reduces outlet temperature to a safe discharge level.

These separators require specific plumbing from the boiler blowdown valve and require connection to a cold water supply. [If the separator is less than half full of water after the boiler

PAGE 19 OF 63 1305M323QNFFM0138

is blown down cold water must be added to bring the water level to the halfway mark before the next blowdown.

• 0-30 psig pressure gauge; 0-200F temperature gauge; water sight gauge glass and valve set assembly are included.

CONTROL VOLTAGE STEPDOWN TRANSFORMER

• Provides 120 Volt (220 Volt export) from main power supply. Factory wired and fused.

MULTISTAGE LOAD PROGRESSIVE SEQUENCERS

Accurate control is provided by automatic progressive sequencing in the use of energy and minimizing wear on electrical components. The sequencers are designed to apply power progressively to larger KW boilers. A factory installed pressure sensitive sequential control reacting to steam boiler pressure progressive energizes or de-energizes heating elements through power contactors. A delay between sequencer steps before start-up and between each subsequent step eliminates power surges. Each sequencer is matched and factory pre- set to boiler system requirements. Electronic progressive sequencers give accurate control of multi-stage loads of the type used in steam boilers. Features include progressive sequencing [first on-first off] that equalizes the operating time of each load. Integral solid-state light emitting diodes show active stages. Should a power interruption occur, all elements are instantly de-energized for safety. Upon resumption of power the control will re-stage the loads one at a time.

PAGE 20 OF 63 1305M323QNFFM0138

Sussman Boilers Installation, Operation & Maintenance Manual

Blowdown Separator Tanks

Models BDT-ASME 36, 42, 48, 54

Dimensions and Features Suggested Hook-Up to Boiler

Blowdown Outlets

PAGE 21 OF 63 1305M323QNFFM0138

The Sussman separator design incorporates a water seal at the outlet which permits the operator to introduce cold water from the bottom to mix with the hot water and boiler steam blowdown in the separator. This reduces the outlet temperature to a level that makes it safe for discharge. If the separator is less than half full of water after the boiler is blown down, cold tap water must be added to bring the water level to the halfway mark before the next blowdown.

Note: 1 BHP is approximatley 10kW

Maximum boiler working pressure: 250 psi Maximum blowdown separator pressure : 65 psi Blowdown Separators are sized in accordance with National Board.

Standard Equipment 0-100 lb. Pressure Gauge 0-200 emperature Gauge Water Level Gauge

PAGE 22 OF 63 1305M323QNFFM0138

APPENDIX 2

ACRONYMS

Air-Condition and Refrigeration Institute ARI Air Movement and Control Association International , Inc AMCA

American Bearing Manufacturers Association ABMA American Concrete Institute ACI Asbestos Containing Material ACM American Institute of Steel Construction AISC American National Standards Institute ANSI American Plywood Association APA American Society of Civil Engineers ASCE American Wood Preserve Bureau AWPB American Wood Protection Association AWPA Above ground Storage Tank AST American Society for Testing and Materials ASTM American Society of Mechanical Engineers ASME American Welding Society AWS Best Management Practices BMP Building Officials and Code Administrators BOCA California Roof Rating Council CRRC Clean Air Act CAA Clean Water Act CWA Chain Link Fence Manufacturing Institute CLFMI Chromated Copper Arsenate CCA Cubic Feet per Minute CFM Code of Federal Regulation CFR Concrete Masonry Unit CMU Concrete Conc Contracting Officer CO Contracting Officer's Representative COR Contracting Officer's Technical Representative COTR Demarcation point DEMARC Demolition Demo Department of Environmental Protection DEP Drawing Dwg Ethylene Propylene Diene Monomer EPDM Electronic Industries Alliance EIA Elevation Elev Encased Burial EB Environmental Protection Agency EPA Feet Ft Factory Mutual FM Finish Floor FF

PAGE 23 OF 63 1305M323QNFFM0138

Fire Rated FR Fiberglass Reinforced Product FRP Gauge Ga General Contractor GC Gallons per Minute GPM Gypsum GYP Gypsum Association GA International Organization for Standardization ISO Inch In Information Technology IT Institute of Electrical and Electronic Engineers IEEE Leadership in Energy and Environmental Design LEED Linear Feet LF Maximum MAX Metal Lath/Steel Framing Association ML/SFA Mean High Water MHW Mean Low Water MLW Mile Per Hour MPH Material Safety Data Sheets MSDS National Electric Code NEC National Fire Protection Association NFPA National Institute of Standards and Technology NIST National Sanitation Foundation NSF Notice To Proceed NTP Not To Scale NTS On Center OC Ounce OZ Outside Diameter OD Occupational Safety and Health Act OSHA No Added Urea Formaldehyde NAUF National Electrical Manufacturers Association NEMA Not To Scale NTS Parts Per Billion PPB Parts Per Million PPM Pounds lbs Pounds per Square Inch PSI Polyvinyl Chloride PVC Professional Engineer PE Programmable Logic Controllers PLC Resource Conservation and Recovery Act RCRA Schedule Sch Steel Door Institute SDI Square Feet SF Statement Of Work SOW Solar Reflectance Index SRI Sound Transmission Class STC Square Sq Telecommunication Industry Association TIA Thick Thk Typical Typ Uniform Construction Code UCC Underwriters Laboratories UL United States Army Corps of Engineers USACE United States Coast Guard USCG United States Green Building Council USGBC Veneered Faced Panel Products HPVA

PAGE 24 OF 63 1305M323QNFFM0138

Underground Storage Tank UST Vinyl Asbestos Floor Tile VAT Volatile Organic Carbon VOC Welded Wire Fabric WWF Western Wood Products Association WWPA

APPENDIX 3

PROFESSIONAL AGENCIES, ASSOCIATIONS, CODES, COUNCILS,

INSTITUTES, AND STANDARDS

Air-Condition and Refrigeration Institute ARI Air Movement and Control Association International , Inc AMCA American Bearing Manufacturers Association ABMA American Concrete Institute ACI American Ladder Institute ALI American Institute of Steel Construction AISC American National Standards Institute ANSI American Plywood Association APA American Society of Civil Engineers ASCE American Society for Testing and Materials ASTM American Society of Mechanical Engineers ASME American Welding Society AWS American Wood Preserve Bureau AWPB American Wood Protection Association AWPA Building Officials and Code Administrators BOCA California Roof Rating Council CRRC Clean Air Act CAA Clean Water Act CWA Chain Link Fence Manufacturing Institute CLFMI Code of Federal Regulation CFR Concrete Reinforcing Steel Institute CRSI Construction Specification Institute CSI Department of Environmental Protection DEP Electronic Industries Alliance EIA Environmental Protection Agency EPA Gypsum Association GA International Organization for Standardization ISO Institute of Electrical and Electronic Engineers IEEE Leadership in Energy and Environmental Design LEED Metal Lath/Steel Framing Association ML/SFA National Asphalt Pavement Association NAPA National Association of Corrosion Engineers NACE National Electric Code NEC National Fire Protection Association NFPA National Institute of Standards and Technology NIST

PAGE 25 OF 63 1305M323QNFFM0138

National Sanitation Foundation NSF National Society of Professional Engineers NSPE Occupational Safety and Health Act OSHA National Electrical Manufacturers Association NEMA Plastic Pipe Institute PPI Portland Cement Association PCA Precast/Prestressed Concrete Institute PCI Resource Conservation and Recovery Act RCRA Steel Door Institute SDI Telecommunication Industry Association TIA Uniform Construction Code UCC Underwriters Laboratories UL United States Army Corps of Engineers USACE United States Coast Guard USCG United States Green Building Council USGBC Western Wood Products Association WWPA Western Wood Preservation Institute WWPI

Construction Clauses

PAGE 26 OF 63 1305M323QNFFM0138

PART I - CONSTRUCTION PURCHASE ORDER CLAUSES

(FIXED-PRICE)

UPDATED THROUGH FAC 2023-04 (JUN 2023) (DEVIATION 2023-09) (JUN 2023)

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:

https://www.acquisition.gov/far/index.html

(End of Clause)

CLAUSE

NUMBER TITLE DATE

52.203-12 Limitation on Payments to Influence Certain Federal Transactions

JUN 2020

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-9 Personal Identity Verification of Contractor Personnel

JAN 2011

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018 52.204-19 Incorporation by Reference of Representations and

Certifications DEC 2014 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities.

NOV 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.204-27 Prohibition on a ByteDance Covered Application JUN 2023 52.209-6 Protecting The Government's Interest When

Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

NOV 2021

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations

NOV 2015

52.211-6 Brand Name or Equal AUG 1999 52.219-6 Notice of Total Small Business Set-Aside NOV 2020 52.219-13 Notice of Set-Aside of Orders MAR 2020 52.219-28 Post-Award Small Business Program

Rerepresentation MAR 2023 52.219-32 Orders Issued Directly Under Small Business

Reserves

MAR 2020

52.222-3 Convict Labor JUN 2003 52.222-6 Construction Wage Rate Requirement AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination - Debarment MAY 2014

PAGE 27 OF 63 1305M323QNFFM0138

NUMBER TITLE DATE

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-19 Child Labor—Cooperation with Authorities and

Remedies

DEC 2022

52.222-21 Prohibition of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEPT 2016

52.222-27 Affirmative Action Compliance Requirements for Construction

APR 2015

52.222-35 Equal Opportunity for Veterans JUN 2020

52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020

52.222-50 Combating Trafficking in Persons JAN 2022 52.222-55 Minimum Wages Under Executive Order 14026 JAN 2022 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022 52.223-3 Hazardous Material Identification and Material

Safety Data (Alternate I)

FEB 2021

52.223-5 Pollution Prevention and Right-to-Know Information (Alternate I) (AUG 2003)

MAY 2011

52.223-18 Contractor Policy to Ban Text Messaging While Driving

JUN 2020

52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-11 Pledges of Assets (Deviation 2023-09) (Jun 2023) FEB 2021 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds-Construction

(Deviation 2023-09)(Jun 2023)

JUN 2020

52.232-5 Payments under Fixed Price Construction Contracts MAY 2014 52.232-18 Availability of Funds APR 1984 52.232-23 Assignment of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award Management.

OCT 2018

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors (Mar 2023) MAR 2023 52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984

PAGE 28 OF 63 1305M323QNFFM0138

NUMBER TITLE DATE

52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-12 Cleaning Up APR 1984 52.236-14 Availability and Use of Utility Services

Water and electric is provided to the contractor at no charge.

APR 1984

52.242-14 Suspension of Work APR 1984 52.243-5 Changes and Changed Conditions APR 1984 52.244-6 Subcontracts for Commercial Products and

Commercial Services

MAR 2023

52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.249-1 Termination for Convenience of the Government

(Fixed-Price) (Short Form)

APR 1984

52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991

FAR 52.252-6 Authorized Deviations in Clauses (Nov 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Department of Commerce (48 CFR 1352) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

(End of clause)

FAR 52.211-10 Commencement, Prosecution and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 days after award. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

FAR 52.225-9 Buy American—Construction Materials (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

PAGE 29 OF 63 1305M323QNFFM0138

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United

States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material.

PAGE 30 OF 63 1305M323QNFFM0138

The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph

(b)(2) of this clause if the Government determines that-

(i)The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

PAGE 31 OF 63…