SF1442 Fargo 06 Electrical transformer upgrade .pdf
PDF 1 MB Posted
- Attached to
- Fargo FB/CH Electrical Transformer Upgrade Federal contract opportunity
- Solicitation number
- 47PJ0022R0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI 1 Transformer Upgrade.pdf | ||
| SF30 Solicitation Amendment 47PJ0022R0004_0001.pdf | ||
| Universal Scope Requirementsv2 01-30-2019.pdf | ||
| Badging and Security Requirements 5-3-2017.pdf | ||
| Fargo 06 Electrical transformer upgrade Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
PAGE
GENERAL SERVICES ADMINISTRATION
ITEM NO.
(a)
SUPPLIES OR SERVICES
(b)
QUANTITY
ORDERED
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
Place of Performance: 655 1ST AVE N FARGO, ND 58102-4932
300 kVA rated T-B1 transformer located in the annex basement
PoP: 12/01/2021 - 02/01/2022 power quality at the Fargo Federal Building / Courthouse transformer. This scope of work will involve replacing the
In 2021, GSA commissioned MBN Engineering to investigate
Contract Type: Firm Fixed Price a transformer with a K-rated harmonic mitigating phase shift
PSC: Z2AA -- REPAIR OR ALTERATION OF OFFICE BUILDINGS
Upgrade Electrical Transformer provided by MBN June 24, 2021, indicated the need to replace transformers in the building. The resulting harmonic study
LS
Deliverable boiler room of building ND0006ZZ.
because of elevated temperatures within electrical
OF
| topmostSubform[0]: |
| Page2[0]: |
| USC10[0]: |
| TelephoneNo\: |
| [0]: |
| Date31c[0]: |
| CheckBox29[0]: Off |
| AmendmentNo4[0]: |
| AdministeredBy[0]: GSA PBS ND PROPERTY MGMT TEAM 8PSMMN |
657 2ND AVENUE NORTH RM 244
FARGO, ND 58102-4727 USA
| FacilityCode[0]: |
| AmendmentDate4[0]: |
| AmendmentNo7[0]: |
| AuthorizedSignature[0]: |
| Date30c[0]: |
| Amounts[0]: |
| AmendmentNo5[0]: |
| AmendmentDate8[0]: |
| AmendmentNo1[0]: |
| AccountingData[0]: |
| AmendmentDate3[0]: |
| Amount[0]: |
| AmendmentNo10[0]: |
| AmendmentDate7[0]: |
| PaymentMadeBy[0]: PBS PAYMENTS BRANCH -https://finance.ocfo.gsa.gov/ |
P.O. BOX 17181
https://finance.ocfo.gsa.gov/
FORT WORTH, TX 76102-0181 USA
| AmendmentNo8[0]: |
| NameofOfferor[0]: |
| NameContractingOfficer[0]: Cody Lee |
| Copies28[0]: 1 |
| NameTitleSign[0]: |
| NameandTitle[0]: |
| OfferDate[0]: |
| Signature30b[0]: |
| AmendmentDate9[0]: |
| AmendmentNo6[0]: |
| ItemsAccepted[0]: |
| AmendmentDate2[0]: |
| AmendmentNo2[0]: |
| AmendmentDate6[0]: |
| RemittanceAddress[0]: |
| USC41[0]: |
| CalendarDays2[0]: |
| AmendmentNo9[0]: |
| CheckBox1[0]: Off |
| AmendmentDate10[0]: |
| CodeField[0]: |
| AmendmentNo3[0]: |
| AdministeredByCode[0]: 8PSMMN |
| CheckBox28[0]: 1 |
| Item[0]: 27 |
| AmendmentDate1[0]: |
| AmendmentDate5[0]: |
| CheckBox2[0]: Off |
| Signature31b[0]: |
| Page1[0]: |
| Code[0]: 8PSMMN |
| Sealed[0]: Off |
| PurchaseRequestNo[0]: EQ8PSMMN-22-0003 |
| Mandatory[0]: 1 |
| AddressOfferTo[0]: GSA PBS ND PROPERTY MGMT TEAM 8PSMMN |
657 2ND AVENUE NORTH RM 244
FARGO, ND 58102-4727 USA
| Is[0]: Off |
| Yes[0]: 1 |
| NumberofCopies[0]: |
| Award[0]: Off |
| Pages[0]: 77 |
| WorkDescribed[0]: In accordance with SOW, upgrade the transformers at the Fargo FB/CH. |
| PhoneNo[0]: 701-239-5453 |
| Hour[0]: 2:00 PM (CST) |
| Proceed[0]: 1 |
| See[0]: |
| SolicitationNo[0]: 47PJ0022R0004 |
| CalendarDays[0]: |
| CalendarDaysComplete[0]: 90 |
| Name9a[0]: Cody Lee |
| Page[0]: 1 |
| Negotiated[0]: 1 |
| By[0]: |
| Negotiable[0]: Off |
| IsNot[0]: 1 |
| ProjectNo[0]: |
| DateDue[0]: 11/24/2021 |
| IssuedBy[0]: GSA PBS ND PROPERTY MGMT TEAM 8PSMMN |
657 2ND AVENUE NORTH RM 244
FARGO, ND 58102-4727 USA
| ContractNo[0]: |
| No[0]: Off |
| CalendarDaysStart[0]: 15 |
| LessCalendarDays[0]: 30 |
| DateIssued[0]: 11/4/2021 |
File details come from the government source that posted it. Updated .