SF1442 1.pdf
PDF 394 KB Posted
- Attached to
- FCI Marion - Emergency Repair Tornado Damage
- Solicitation number
- 15BBNF26Q40900001
About this file
Solicitation Summary
This is a sealed bid Invitation for Bid (IFB) issued by the Federal Bureau of Prisons for emergency repair of tornado damage at Federal Correctional Institution (FCI) Marion in Marion, Illinois. The solicitation number is 15BBNF26Q40900001, with requisition number 15B40926PR000233 and project number 25Z4AG1. The contract is structured as a Firm Fixed Price award with a single line item (0001) requiring the contractor to provide all materials, labor, and equipment to complete emergency tornado damage repairs. The deadline for sealed bid submission is December 3, 2026, at 12:00 PM Eastern Time at USP Marion, 4500 Prison Rd., Marion, IL 62959. The solicitation indicates the magnitude of this project is between $250,000 and $500,000.
The contractor must begin performance within 10 calendar days of award and complete the work within 90 calendar days. Performance and payment bonds are required, with each bond equal to 100% of the original contract price, due within 10 days of award. The solicitation includes extensive FAR clauses and special contract requirements covering prevailing wage rates for construction labor, Buy American requirements for construction materials, insurance requirements (Workers Compensation $100,000 minimum; General Liability $500,000 per occurrence; Auto Liability $200,000 per person/$500,000 per occurrence), personnel security clearances through DOJ, and various compliance certifications. The government requires submission of a bid bond (Standard Form 24) equal to 20% of the bid price or not to exceed $3,000,000. Additional requirements include pre-construction conferences, progress meetings, submittals for COR approval within 10 days of work commencement, a Schedule of Values, and contract closeout procedures including as-built drawings and warranties documentation within six months of physical completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WD IL20260002 05-18-2026.pdf | ||
| SUBMISSION COVER PAGE.pdf | ||
| Bid Bond SF24 (Updated) 1.pdf | ||
| Instructions to Offerors FCI Marion.pdf | ||
| Criminal History Check Form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15BBNF26Q40900001 Page 1 of 62
SOLICITATION,OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER
15BBNF26Q40900001
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
2. TYPE OF SOLICITATION 3. DATE ISSUED
10/05/2026
PAGE OF PAGES
1 62
IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER
15B40926PR000233
6. PROJECT NUMBER
25Z4AG1
CODE BFAO
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
7. ISSUED BY
Federal Bureau of Prisons USP Marion 4500 Prison Rd.
Marion, IL 62959
(O) 803-625-5298 csmart@bop.gov
8. ADDRESS OFFER TO
9. FOR
INFORMATION CALL:
a. NAME
Candi Smart csmart@bop.gov
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
The selected contractor shall provide all materials, labor, and equipment to complete the project titled Emergency Repair Tornado Damage at the Federal Correctional Institution (FCI) Marion, located in Marion, Illinois, in accordance with the attached Statement of Work.
PLEASE COMPLETE THE FOLLOWING ITEMS:
UNIQUE ENTITY IDENTIFIER (UEI):_____________________________
TAX IDENTIFICATION NUMBER: ____________________________
CAGE CODE:________________________________
CONTRACTOR E-MAIL:________________________________
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in
SAM.
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 90 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).
X YES NO
12b. CALENDAR DAYS
Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
12:00US/
Eastern a.
12/03/2026
b. An offer guarantee is, X is not required.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.
d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
15BBNF26Q40900001 Page 2 of 62
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CODE FACILITY CODE
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
17.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE
UNITED STATES CODE AT
26. ADMINISTERED BY 15BBNF
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
Candi Smart csmart@bop.gov
Federal Bureau of Prisons USP Marion 4500 Prison Rd.
Marion, IL 62959
Business Office MAR-BusinessOffice-S@bop.gov
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
Candi Smart
31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
15BBNF26Q40900001 Page 3 of 62
Table of Contents
Section Description Page Number
1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements 4 Contract Clauses 5 Attachments 6 Solicitation Provisions 7 Representations and Certifications
15BBNF26Q40900001 Page 4 of 62
Section 2 - Commodity or Services Schedule
Replace Overhead Power-lines and two Transformers FCI Marion project # 25Z4AG1
Firm Fixed Price
SCHEDULE OF SUPPLIES/SERVICES
CONTINUATION SHEET
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 The selected contractor shall provide all materials, labor, and equipment for Emergency Repair Tornado Damage at the Federal Correctional Institution (FCI) Marion, Illinois, in accordance with the attached Statement of Work.
PSC: Z2FF
Delivery Schedule:
Delivery Description:
Delivery Number: 1 Delivery Period:
Quantity: 1.000000
Delivery Address:
Federal Bureau of Prisons USP Marion 4500 Prison Rd.
Marion, IL 62959
John Jordan jxjordan@bop.gov
1 JB $________ $_________________
The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued by the Federal Bureau of Prisons. THE TOTAL PRICE SHALL BE WRITTEN ON LINE ITEM 17 OF THE STANDARD FORM 1442.
15BBNF26Q40900001 Page 5 of 62
Section 3 - Special Contract Requirements
Clauses By Full Text
FAO-0001 Bonds
(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)
(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows;
a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)
(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):
(1) A Payment Bond;
(2) An irrevocable letter of credit (ILC);
(3) A tripartite escrow agreement;
(4) A Certificate of Deposit; or
(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.
(d) Individual Sureties.
(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.
(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.
FAO-0002 Magnitude
The magnitude of this project is between $250,000.00 and $500,000.00.
15BBNF26Q40900001 Page 6 of 62
FAO-0003 Required Insurance
See FAR 52.228-5, Insurance - Work on a Government Installation.
The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the
Schedule or elsewhere in the contract.
TYPE AMOUNT
(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000
The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.
(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:
PER ACCIDENT OR
OCCURRENCE FOR BODILY INJURY $500,000
This insurance shall include contractor's protective and contractual liability.
(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:
PER PERSON $200,000
PER OCCURRENCE FOR BODILY INJURY $500,000
PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000
FAO-0004 Pre-Construction Conference
(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.
15BBNF26Q40900001 Page 7 of 62
Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered. The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.
(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.
FAO-0005 Submittals
Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.
The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.
(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.
(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specificat ions to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.
(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.
(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.
(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.
FAO-0006 Contractor Use of Premises
Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.
NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/
15BBNF26Q40900001 Page 8 of 62 exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.
Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.
Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.
Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.
Safety and Accident Prevention In performing work under this contract the contractor shall:
(a) Conform to the specific safety requirements established by this contract;
(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;
(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.
FAO-0007 Payment Services
(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form;
however, it shall contain similar information as the AIA Form G-702. The Contracting Officer’s Representative (COR) will approve the amount of payment by signing. The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.
(b) All small business contractors are required to self-certify on all invoices their small business status.
(c) The following information is required with each application for payment:
• Name and address of contractor
• Contract number
• Contractor invoice/application for payment number
• Description, price, and quantity of construction completed/rendered
• Payment terms (reference the contract payment clause)
• Other substantiating documentation or information required by the contract
• Name, title, and phone number of official to be notified in the event of a defective invoice
• Contractor TIN (Tax ID Number)
FAO-0008 Request for Final Inspection
The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.
FAO-0009(a) Construction Contract Security
FAO-0009(a) Construction Contract Security (Program Statement 3732.01 BOP Identifications and Background Investigation)
15BBNF26Q40900001 Page 9 of 62
In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021); (Alt. I) -- Classified Information – Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:
Criminal History Check – BP-A0660 (May 2018) CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, _3___ calendar days [contracting officer to insert the number of days based on performance period memo] have been included in the performance period specified in FAR clause 52.211-10. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed SF-1413.
**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**
FAO-0010 Assignment of Contract Administration Office and Functions
Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.
The Contract Administration Office is required, however, to obtain written authorization from the Procuring Contracting Officer (PCO) to perform any function listed under 42.302(b). Specifically, the Administrative Contracting Officer (ACO) is required to obtain written authorization to perform the below referenced functions FOR CONSTRUCTION CONTRACT
AWARDS:
(1) Negotiate or negotiate and execute supplemental agreements incorporating contractor proposals resulting from change orders issued under the Changes clause. Before completing negotiations, coordinate any delivery schedule change with the contracting office.
(2) Negotiate prices and execute priced exhibits for unpriced orders issued by the contracting officer under basic ordering agreements.
(3) Negotiate or negotiate and execute supplemental agreements changing contract delivery schedules.
(4) Complete Contractor Performance Assessment Report System (CPARS) evaluations of contractor performance in accordance with FAR Subpart 42.15.
15BBNF26Q40900001 Page 10 of 62
Should any other function under FAR Subpart 42.15 not listed above be required, the ACO is required to contact the PCO for authority.
FAO-0011 Schedule of Values
The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule.
The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.
(a) The SOV shall include:
(1) Project name, location, and contract number;
(2) Contractor’s name and address;
(3) Date of submittal.
(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:
(1) Description of Work or Material;
(2) Related specification section, if applicable;
(3) Name of subcontractor, if applicable;
(4) Name of manufacturer or fabricator, if applicable;
(5) Name of supplier, if applicable;
(6) Change orders (modifications) that have affected value, if applicable;
(7) Dollar value;
(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.
(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.
(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.
(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.
(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.
FAO-0012 Progress Meetings
The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.
(a) At a minimum, the attendees shall include but is not limited to:
(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administr ator/Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).
(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).
(b) The meeting should include, but is not limited to issues such as:
15BBNF26Q40900001 Page 11 of 62
Administrative Contracting Officer:
(1) Old business from previous progress meeting(s);
(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);
(3) Review of payments made to date and review/approve current payment request;
(4) Status of modification proposal requests;
(5) Discuss new business.
COR:
(1) Status of escort coverage;
(2) Review gate or sallyport entrance/exit issues;
(3) Discuss other delays contractor may be experiencing;
(4) Discuss performance/quality issues.
Contractor:
(1) Review/discuss updated progress schedule;
(2) Provide 30 day outlook;
(3) Discuss other issues affecting performance.
FAO-0013 Contract Closeout Procedures (for construction contracts exceeding SAT)
Contract Closeout must be completed within six (6) months of physical completion of the work.
Prior to payment of final invoice:
The contractor shall submit the following documents:
(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);
(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);
(3) All as-built drawings/shop drawings, if applicable;
(4) Contractor’s final invoice;
(5) Release of Claims (GSA Form 1142);
(6) Consent of Surety to Final Payment (AIA Document G707);
(7) Letter establishing warranty dates;
(8) Complete list of subcontractors with telephone numbers and points of contact;
(9) Guarantees and warranties;
15BBNF26Q40900001 Page 12 of 62
(10) All balance and test reports;
(11) All operation/maintenance manuals;
(12) All permits and certifications.
AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.
GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).
15BBNF26Q40900001 Page 13 of 62
Section 4 - Contract Clauses
Clauses By Reference
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov
Clause Title Fill-ins (if applicable)
52.203-6 Restrictions on Subcontractor Sales to the Government
(Jun 2020)
52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality
Agreements or Statements (Jan 2017)
52.204-9 Personal Identity Verification of Contractor Personnel
(Jan 2011)
52.204-13 (DEV) System for Award Management-Maintenance (Oct 2018)
(DEVIATION NOV 2025)
52.209-6 (DEV) Protecting the Government's Interest When
Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan
2025) (DEVIATION NOV 2025)
52.209-10 (DEV) Prohibition on Contracting With Inverted Domestic
Corporations (Nov 2015) (DEVIATION NOV 2025)
52.219-6 (DEV) Notice of Total Small Business Set-Aside (Nov 2020)
(DEVIATION DEC 2025)
52.219-8 (DEV) Utilization of Small Business Concerns (Jan 2025)
(DEVIATION DEC 2025)
52.219-16 (DEV) Liquidated Damages-Subcontracting Plan (Sep 2021)
(DEVIATION DEC 2025)
15BBNF26Q40900001 Page 14 of 62
Clause Title Fill-ins (if applicable)
52.222-1 (DEV) Notice to the Government of Labor Disputes (Feb 1997)
(DEVIATION DEC 2025)
52.222-3 (DEV) Convict Labor (June 2003) (DEVIATION DEC 2025)
52.222-6 (DEV) Construction Wage Rate Requirements (Aug 2018)
(DEVIATION AUG 2025)
52.222-7 (DEV) Withholding of Funds (May 2014) (DEVIATION DEC
2025)
52.222-8 (DEV) Payrolls and Basic Records (Jul 2021) (DEVIATION
DEC 2025)
52.222-9 (DEV) Apprentices and Trainees (July 2005) (DEVIATION DEC
2025)
52.222-10 (DEV) Compliance with Copeland Act Requirements (Feb
1988) (DEVIATION DEC 2025)
52.222-11 (DEV) Subcontracts (Labor Standards) (May 2014)
(DEVIATION DEC 2025)
52.222-12 Contract Termination - Debarment (May 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)
52.222-14 (DEV) Disputes Concerning Labor Standards (Feb 1988)
(DEVIATION DEC 2025)
52.222-15 Certification of Eligibility (May 2014)
52.222-35 (DEV) Equal Opportunity for Veterans (Jun 2020) (DEVIATION
DEC 2025)
52.222-36 (DEV) Equal Opportunity for Workers with Disabilities (Jun
2020) (DEVIATION DEC 2025)
52.222-37 (DEV) Employment Reports on Veterans (Jun 2020)
(DEVIATION DEC 2025)
52.222-40 (DEV) Notification of Employee Rights Under the National
Labor Relations Act (Dec 2010) (DEVIATION DEC
2025)
15BBNF26Q40900001 Page 15 of 62
52.222-50 (DEV) Combating Trafficking in Persons (Oct 2025)
(DEVIATION DEC 2025)
52.222-55 (DEV) Minimum Wages for Contractor Workers Under
Executive Order 14026 (Jan 2022) (DEVIATION DEC
2025)
52.222-62 (DEV) Paid Sick Leave Under Executive Order 13706 (Jan
2022) (DEVIATION DEC 2025)
52.222-90 Addressing DEI Discrimination by Federal Contractors
(APR 2026)
52.223-5 Pollution Prevention and Right-to-Know Information
(May 2024)
52.223-23 (DEV) Sustainable Products (May 2024) (DEVIATION DEC
2025)
52.226-8 Encouraging Contractor Policies To Ban Text
Messaging While Driving (May 2024)
52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)
52.228-2 Additional Bond Security (Oct 1997)
52.228-5 Insurance-Work on a Government Installation (Jan
1997)
52.228-11 Individual Surety-Pledge of Assets (Feb 2021)
52.228-14 Irrevocable Letter of Credit (Nov 2014)
52.228-15 Performance and Payment Bonds-Construction (Jun
2020)
52.229-12 (DEV) Tax on Certain Foreign Procurements (Feb 2021)
(DEVIATION AUG 2025)
52.232-23 Assignment of Claims (May 2014)
52.232-27 Prompt Payment for Construction Contracts (Jan 2017)
52.232-33 Payment by Electronic Funds Transfer-System for
Award Management (Oct 2018)
52.232-40 Providing Accelerated Payments to Small Business
Subcontractors (Mar 2023)
15BBNF26Q40900001 Page 16 of 62
52.233-3 (DEV) Protest after Award (Aug 1996) (DEVIATION NOV 2025)
52.233-4 (DEV) Applicable Law for Breach of Contract Claim (Oct 2004)
(DEVIATION NOV 2025)
52.236-2 (DEV) Differing Site Conditions (Apr 1984) (DEVIATION AUG
2025)
52.236-3 (DEV) Site Investigation and Conditions Affecting the Work
(Apr 1984) (DEVIATION AUG 2025)
52.236-5 (DEV) Material and Workmanship (Apr 1984) (DEVIATION
AUG 2025)
52.236-6 (DEV) Superintendence by the Contractor (Apr 1984)
(DEVIATION AUG 2025)
52.236-7 (DEV) Permits and Responsibilities (Nov 1991) (DEVIATION
AUG 2025)
52.236-8 (DEV) Other Contracts (Apr 1984) (DEVIATION AUG 2025)
52.236-9 (DEV) Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984)
(DEVIATION AUG 2025)
52.236-10 (DEV) Operations and Storage Areas (Apr 1984) (DEVIATION
AUG 2025)
52.236-11 (DEV) Use and Possession Prior to Completion (Apr 1984)
(DEVIATION AUG 2025)
52.236-12 (DEV) Cleaning Up (Apr 1984) (DEVIATION AUG 2025)
52.236-13 (DEV) Accident Prevention (Nov 1991) (DEVIATION AUG
2025)
52.236-14 (DEV) Availability and Use of Utility Services (Apr 1984)
(DEVIATION AUG 2025)
52.236-17 (DEV) Layout of Work (Apr 1984) (DEVIATION AUG 2025)
52.236-21 (DEV) Specifications and Drawings for Construction (Feb 1997)
(DEVIATION AUG 2025)
52.240-91 (DEV) Security Prohibitions and Exclusions (DEVIATION NOV
2025)
15BBNF26Q40900001 Page 17 of 62
52.240-92 (DEV) Security Requirements (DEVIATION NOV 2025)
52.240-93 (DEV) Basic Safeguarding of Covered Contractor Information
Systems (DEVIATION NOV 2025)
52.242-5 Payments to Small Business Subcontractors (Jan 2017)
52.242-13 Bankruptcy (July 1995)
52.243-4 (DEV) Changes (June 2007) (DEVIATION JUL 2025)
52.244-6 (DEV) Subcontracts for Commercial Products and Commercial
Services (Jan 2025) (DEVIATION APR 2026)
52.246-21 Warranty of Construction (Mar 1994)
52.248-3 Value Engineering-Construction (Oct 2025)
52.253-1 (DEV) Computer Generated Forms (Jan 1991) (DEVIATION
NOV 2025)
2852.222-70 Domestic Violence, Sexual Assault, and Stalking (DEC
2014)
52.225-10 Notice of Buy American Requirement-Construction
Materials (May 2014)
52.236-15 (DEV) Schedules for Construction Contracts (Apr 1984)
(DEVIATION AUG 2025)
52.242-14 Suspension of Work (Apr 1984)
Clauses By Full Text
52.246-12 Inspection of Construction (Aug 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
15BBNF26Q40900001 Page 18 of 62
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this-section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer.
The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may--
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
(End of clause)
52.211-12 Liquidated Damages-Construction (Sept 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of 1392.77 [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.212-4 Alt I (DEV) Terms and Conditions-Commercial Products and Commercial Services (Nov 2023) - Alternate I (Nov 2021) (DEVIATION NOV 2025)
(a) The clause at Federal Acquisition Regulation (FAR) 52.202-1, Definitions, is incorporated by reference. As used in this clause—
15BBNF26Q40900001 Page 19 of 62
Direct materials means those materials that enter directly into the end product, or that are used or consumed directly in connection with the furnishing of the end product or service.
Hourly rate means the rate(s) prescribed in the contract for payment for labor that meets the labor category qualifications of a labor category specified in the contract that are—
(1) Performed by the contractor;
(2) Performed by the subcontractors; or
(3) Transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.
Materials means—
(1) Direct materials, including supplies transferred between divisions, subsidiaries, or affiliates of the contractor under a common control;
(2) Subcontracts for supplies and incidental services for which there is not a labor category specified in the contract;
(3) Other direct costs (e.g., incidental services for which there is not a labor category specified in the contract, travel, computer usage charges, etc.);
(4) The following subcontracts for services which are specifically excluded from the hourly rate:
__________________ [Insert any subcontracts for services to be excluded from the hourly rates prescribed in the schedule.]; and
(5) Indirect costs specifically provided for in this clause.
Subcontract means any contract, as defined in FAR 2.101, entered into with a subcontractor to furnish supplies or services for performance of the prime contract or a subcontract including transfers between divisions, subsidiaries, or affiliates of a contractor or subcontractor. It includes, but is not limited to, purchase orders, and changes and modifications to purchase orders.
b) Inspection/Acceptance.
(1) The Government has the right to inspect and test all materials furnished and services performed under this contract at all places and times before acceptance. The Government will perform inspections and tests in a manner that will not unduly delay the work.
(2) If the Government performs inspection or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.
(3) Unless otherwise specified in the contract, the Government will accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they will be presumed accepted 60 days after the date of delivery, unless accepted earlier.
(4) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements. Except as otherwise specified in paragraph (b)(6) of this clause, the cost of replacement or correction shall be determined under paragraph (i) of this clause, but the “hourly rate” for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. Unless otherwise specified below, the portion of the “hourly rate” attributable to profit shall be 10 percent. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken.
__________________ [Insert portion of labor rate attributable to profit.]
15BBNF26Q40900001 Page 20 of 62
(5)(i) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the Government may—
(A) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or
(B) Terminate this contract for cause.
(ii) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute under the Disputes clause of the contract.
(6) Notwithstanding paragraphs (b)(4) and (5) of this clause, the Government may, at any time, require the Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to—
(i) Fraud, lack of good faith, or willful misconduct on the part of the Contractor’s managerial personnel;
or
(ii) The conduct of one or more of the Contractor’s employees selected or retained by the Contractor after any of the Contractor’s managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.
(7) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.
(8) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.
(9) Unless otherwise specified in the contract, the Contractor’s obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.
(c) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(d) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(e) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause FAR 52.233-1, Disputes, which is incorporated in this contract by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall—
(1) Notify the Contracting Officer in writing as soon as possible;
(2) Remedy the delay as quickly as possible; and
(3) Notify the Contracting Officer when the occurrence is over.
15BBNF26Q40900001 Page 21 of 62
(g) Invoice. The Government will handle invoices according to the Prompt Payment Act (31 U.S.C. 3903) and 5 CFR part 1315. The Contractor shall submit invoices to the address designated in the contract to receive invoices. An invoice must include the information required by 5 CFR part 1315.9(b).
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees, and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark, or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payments.
(1) Work performed. The Government will pay the Contractor as follows upon the submission of commercial invoices approved by the Contracting Officer:
(i) Hourly rate.
(A) The amounts shall be computed by multiplying the appropriate hourly rates prescribed in the contract by the number of direct labor hours performed. Fractional parts of an hour shall be payable on a prorated basis.
(B) The rates shall be paid for all labor performed on the contract that meets the labor qualifications specified in the contract. Labor hours incurred to perform tasks for which labor qualifications were specified in the contract will not be paid to the extent the work is performed by individuals that do not meet the qualifications specified in the contract, unless specifically authorized by the Contracting Officer.
(C) Invoices may be submitted once each month (or at more frequent intervals, if approved by the Contracting Officer) to the Contracting Officer or the authorized representative.
(D) When requested by the Contracting Officer or the authorized representative, the Contractor shall substantiate invoices (including any subcontractor hours reimbursed at the hourly rate in the schedule) by evidence of actual payment, individual daily job timecards, records that verify the employees meet the qualifications for the labor categories specified in the contract, or other substantiation specified in the contract.
(E) Unless the Schedule prescribes otherwise, the hourly rates in the Schedule shall not be varied by virtue of the Contractor having performed work on an overtime basis.
(1) If no overtime rates are provided in the Schedule and the Contracting Officer approves overtime work in advance, overtime rates shall be negotiated.
(2) Failure to agree upon these overtime rates shall be treated as a dispute under the Disputes clause of this contract.
(3) If the Schedule provides rates for overtime, the premium portion of those rates will be reimbursable only to the extent the overtime is approved by the Contracting Officer.
(ii) Materials.
(A) If the Contractor furnishes materials that meet the definition of a commercial product at FAR 2.101, the price to be paid for such materials shall not exceed the Contractor’s established catalog or market price, adjusted to reflect the—
(1) Quantities being acquired; and
(2) Any modifications necessary because of contract requirements.
(B) Except as provided for in paragraph (i)(1)(ii)(A) and (D)(2) of this clause, the Government will reimburse the Contractor the actual cost of materials (less any rebates, refunds, or
15BBNF26Q40900001 Page 22 of 62 discounts received by the contractor that are identifiable to the contract) provided the Contractor—
(1) Has made payments for materials in accordance with the terms and conditions of the agreement or invoice; or
(2) Makes these payments within 30 days of the submission of the Contractor’s payment request to the Government and such payment is in accordance with the terms and conditions of the agreement or invoice.
(C)…
This is the start of the file's text. The full file is on GovTribe.