SF-30-A0001_Solicitation Amendment to 191N6525Q0120.pdf

PDF 1 MB Posted

Attached to
SF30-A0001 Amendment to Solicitation 191N6525Q0120 - Supply, Installation, Testing and Commissioning of 100kW UPS
Solicitation number
SF30-A0001_Amendment_SolicitationNo191N6525Q0120
Issued by

About this file

This document is a Solicitation Amendment (SF-30) for a federal contract opportunity issued by the Department of State for the Supply, Installation, Testing and Commissioning of a 100kW Uninterruptible Power Supply (UPS) system at the American Embassy in New Delhi, India. The amendment extends the offer submission deadline to 1700 hours (India Time) on August 8, 2025, and includes a comprehensive questions and answers section that provides detailed technical specifications and clarifications for potential bidders.

Key technical requirements include a 100kW UPS with Li-Ion batteries offering 30 minutes of backup time, 10-year battery warranty, hot-swappable modular design, and future expandability up to 250kW. The solicitation specifies cable ratings, conduit lengths, MCCB configurations, and installation details. Bidders are required to provide the country of origin for UPS systems and batteries, and must submit their quotations electronically to Newdelhibids@state.gov with the specific solicitation number in the subject line. The contract does not allow modifications to the existing payment milestone structure and requires detailed technical compliance with the specified requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

END DATE FOR OFFER SUBMISSION IS EXTENDED

Quotations are due by/before 1700 hrs. (India Time) August 8, 2025. Your quotation must be submitted electronically to Newdelhibids@state.gov with the subject line “Solicitation No. 191N6525Q0120 for Supply, Installation, Testing and Commissioning of 100kW UPS”.

QUESTION AND ANSWERS

Question & Answers_Solicitation 191N6525Q0120

Sl.

Header Question Answer

1 Battery Back-up Time

At one section power back-up is mentioned as 2- 4Hours and at other place 30 minutes is mentioned.

The space available is the UPS Room is not sufficient hence we suggest to consider Lithium-Ion battery solution. We can offer Max. 45 Minutes back-up with liB Battery on 100KW, 0.95 P.f Load as per RFP. Pls suggest if u would like to buy LiB with 30 Mins or 45 Mins?

Quote for 30 Minutes back up with Li-Ion Batteries

2 Input & Output MCCB

It was discussed during site survey that 1 x Input MCCB is required in Electrical Room, 1 x Input MCCB Required in UPS Room, 1 x Output MCCB required in UPS Room. All MCCB to be supplied along with Wall Mount Enclosures. Pls confirm this understanding for sync of all bidders.

Yes, that’s correct. MCCB To be provided with proper cable terminations enclosures

3 Length of Input Cable

Pls define the Cable running length for UPS Feeder Panel to UPS Input MCCB (Panel Room) to UPS Input MCCB (UPS room) to UPS to UPS Output MCCB (in UPS Room) to Final Distribution Panel

Total Cable Length to be considered roughly 250Feets (Main Incomer Power supply Tap to the UPS Room), Conduit and cable Length from UPS Room to the panel where output of the UPS to be connected is roughly 90Feet.

4 Cable Cross Section

We request you to define the cable cross section for a sync in bidding to all vendors. 1Core x 120 Sq. mm Copper Flexible cable will be sufficient for 100KW + 40% additional.

Choose copper cable to carry full load current of 100kW load with spare capacity as mentioned in the SOW.

mailto:Newdelhibids@state.gov

5 Length of GI Conduit

Pls define the length for GI Conduit required from UPS Feeder Panel to UPS Input MCCB (Panel Room).

Total Cable Length to be considered roughly 250Feets (Main Incomer Power supply Tap to the UPS Room), Conduit and cable Length from UPS Room to the panel where output of the UPS to be connected is roughly 90Feet.

6 Length of GI Conduit

Pls define the length for GI Conduit required from UPS Output MCCB to Final Distribution Panel

Total Cable Length to be considered roughly 250Feets (Main Incomer Power supply Tap to the UPS Room), Conduit and cable Length from UPS Room to the panel where output of the UPS to be connected is roughly 90Feet.

7 UPS

Expandability to 250 KVA

Due to limited space in UPS room, We foresee a challenge in adding batteries to 100KW UPS in the UPS Room in future when modules are added and hence, we suggest considering no expansion for future. In case u select 125 KW as base chassis today, this can be future expandable to 250KW by adding 1 x 125 KW chassis in parallel load sharing.

Follow solicitation specifications

8 Redundancy Module within same chassis

We understand that you have asked for a 100KW UPS but there is no mention of an additional redundant Module above 100KW. Wherever a customer buys single chassis solution, they always buy 1 Additional Module within the same chassis to meet the redundancy requirement also. We request you to clarify if we have to consider 1 extra module above 100KW or not. EX: 4 x 25KW +1 x 25 KW - Total 125

KW.

No-we need 100kW UPS Only having capability to add modules which can go up to 250kW for future expansions.

9 UPS & Battery Country of Origin

Please confirm if there is any restriction for bidders for COUNTRY of manufacture for UPS Systems / Batteries. Or If you want, we then all bidders can declare the country of Origin in their bid for your review.

Yes, please provide country of origin.

10 Lithium-Ion battery Warranty

As per tender 12V VRLA battery warranty is asked as 5 years however Lithium-Ion battery Warranty can be offered as 5,6,7,8,9 or 10 Years also. Pls suggest what will be your choice while selecting LiB batteries.

Please quote 10 years battery warranty

11 Lithium-Ion battery Safety Certification

LiB Battery comes with UN38.3, UL1973, UL1998, UL9540 & UL9540A Certifications. The LiB Batteries following above standards are the safest available LiB Solutions for UPS Applications

Noted and accepted

12 Cybersecurity aspect

UPS Systems SNMP & Modbus cards are often connected to your office communication network.

Now a days technology advancement has helped in offering SNMP & MODBUS cards which are Cybersecurity certified for UL & IEC Cybersecurity standards. Would u like to buy a cyber security certified SNMP/MODBUS card or a normal card.

No

13 Material Unloading till UPS Room

Please confirm if there is LIFT available to move the material to the UPS Floor or it will be a manual movement thru stairs.

Hand carts can be provided on an accessible ramp.

14 Bid Extension We request you to allow 7-10 days time for bid submission post issuance of " reply to queries"

Extended till 1700 hrs August 8, 2025.

15 UPS Rating UPS Rating is mentioned 100kW and expandable up to 250kw: since requirement is vertical base N+1 hot swappable modular UPS in this case please specify the N rating + 1 Module for redundancy.

We just need a single UPS of 100kW which must have capability for future expansion up to 250kW.

16 Static bypass switch

You have mentioned in technical specification that the static bypass switch shall be of modular design.

Since you have common chassis for all modules in that scenario UPS module chassis should have hot swappable static bypass switch. Please specify the same

Yes, the Bypass switch should be hot swappable, manufacturer specific is acceptable.

17 Backup Time UPS & Battery Room Size is 2400MM X 2400MM, here we can accommodate maximum 250kW chassis along with 30 Minute backup on 100kw load, here SMF batteries come with standard 2 or 3year warranty from Battery OEM. Hence for more backup and warranty you need to select Lithium Batteries.

Please clarify the same

Please consider 30 minutes back up with Li-Ion batteries having 10 years warranty.

18 UPS Input & Output cable

UPS Input & Output cable rating for 100kw should 95Sq MM Copper Armed or Copper flexible considering 125%. Please specify the Cable length in 1 core or 4 Core.

Total Running Cable Length to be considered roughly 250Feets (Main Incomer Power supply Tap to the UPS Room), Conduit and cable Length from UPS Room to the panel where output of the UPS to be connected is roughly 90Feet.

19 GI conduit Dia Please specify the GI conduit Dia in inches for Cable entry

This is vendor’s design basis as per the spare capacity mentioned in the contract.

20 Panel bus bar picture

During the site visit we could not see the panel bus bar for Input & Output Panel. Hence, we request you to share bus bar photos to check the availability of holes on bus bar to tap off the UPS Input cable.

21 MCCB We will be required 3 MCCB’s along with enclosure (1 for electrical room, 1 for UPS Room Input supply and 1 for UPS output supply which will connect to Load.)

here please specify the MCCB rating, Thermal base or Microprocessor base, Indicator & Metering requirement on enclosure. 100kw UPS rating minimum 250Amp MCCB required and considering future expansion it will be 600Amp MCCB. Please specify the same.

Install MCCB as per 100kW UPS, LSIG Microprocessor based with no metering. Having extended rotary handle, accessories for LOTO.

22 VRLA

batteries

In the case of VRLA batteries delivery timeline should be 8 weeks and Lithium batteries it should be 12-14 weeks

Please refer to Solicitation requirements for deliverables.

23 Payment milestones

Payment terms mentioned in tender is multiple milestone basis. We request you cut down the milestone to avoid multiple processes. If possible, to be consider 10% on submission of drawing and balance 90% against installation or within 30days of supply whichever is earlier.

No change.