Statement of Work Septic Sand and Delivery (Hauling)

Big Cypress National Preserve – National Park Service

Description:

Septic Perk Sand and hauling of the sand are needed to filter drain fields at Dona Drive and Oasis recreational campsites. This sand is required for the proper filtering for the drain fields and the trucks are required for this quantity of sand being delivered.

Multiple drain fields are being replaced and 635 cubic yards of septic perk sand is required along with truck delivery to complete this project. It is preferred that one contractor or vendor with multiple trucks provide delivery.

Approximate Addresses/Locations for Delivery:

Oasis Dona Drive 52105 Tamiami Trail E 36362 Tamiami Trail E Ochopee, FL 34141 Ochopee, FL 34141

• This requirement is only for procurement of septic perk sand and delivery to the sites.

• Contractor shall provide 635 cubic yards of septic perk sand or equivalent with delivery included in their submitted quote.

• 300 Cubic Yards will be delivered to the Oasis location and 335 cubic yards will be delivered to the Dona Drive location.

• Awardee shall deliver the septic perk sand to two different locations within the preserve near the given addresses which are both within 30 miles of Big Cypress National Preserve Headquarters.

• Big Cypress will provide an inspector to inspect the septic perk sand being delivered. If the incorrect sand is delivered it will be the responsibility of the contractor/vendor to take the sand back and bring proper specific sand at no additional charge to the Government.

• Contractor/Vendor shall have proper licensed CDL drivers and all vehicles/equipment must have proper documentation and insurance.

• Contractor/Vendor must be flexible in delivery in the case of any unforeseen occurrences (I.E. weather, flooding on property) which may reasonably lead to a later or postponed delivery.

• The Contractor must adhere to all government regulations while in the preserve.

• The Contractor must have proper roads signs (if applicable or required by law) posted where the deliveries are being made inside the preserve.

• A site visit will not be required however, after an award is made, it is highly recommended that the awardee come out prior to deliveries to check for any road hazards or flooding and to see the two areas they are dumping at.

• Contact information for the requirement will be given after award.