Solicitation SEG30016Q0127-A001 Questions & Answers External Painting USG-Owned Residential Compound (FBOz) Page 1
Vendor’s Question and Contracting Officer’s Answers
SEG30016Q0127-A001
QUESTION 1:
I have a question about the Combined Synopsis/Solicitation posted to FBO under solicitation number
SEG30016Q0127? Is this a follow-on requirement? If so, could you please provide the incumbent contract number for this opportunity? If not, is this a new requirement?
ANSWER 1:
Solicitation SEG30016Q0127 is a New Requirement.
QUESTION 2:
In Carpentry Section Are the closet doors like the panelled doors? If yes we have folding closet door that is
60cm wide.. In This case we have to split the MDF to have two 30cm doors is that acceptable? What is meant that bathroom doors are with trims? What are the specs and dimension of the closet shelves?
ANSWER 2:
This Question is not related to Solicitation SEG30016Q0127-A001.
QUESTION 3:
In Plumbing Sections What are the plumbing materials GFI lists that are to be Gov furnished as they are not stated in the specs? Can domestic water supply pipes be priced on Polypropylene pipes?
ANSWER 3:
This Question is not related to Solicitation SEG30016Q0127-A001.
Solicitation SEG30016Q0127-A001 Questions & Answers External Painting USG-Owned Residential Compound (FBOz) Page 2
QUESTION 4:
Can we have the Elevation & Plan Drawings for the Buildings (Auto Cad Format); to start The Scaffolds' Design & shop Drawings?
ANSWER 4:
Apologies that will not be feasible.
QUESTION 5:
Regarding to the Solicitation documents; it’s already mentioned to submit the Scaffolds’ shop Drawings for Approval before Starting work. Kindly requested a Clarification concerning the Received Amendment; Are the Shop Drawings Requested as Bid Documents? OR after Receiving the AWARD (before Starting Execution).
ANSWER 5:
Vendor must submit conceptual design drawing for the scaffold’s as part of their bid as mentioned in the
S.O.W. section 3.2- F-7 and shop drawing after receiving the award.