Section J -W9128F21R0033_ERS_MEGA_MATOC_Spreadsheet.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- DRAFT RFP- $240M Environmental Remediation Services (ERS) Unrestricted (UNR) MATOC Federal contract opportunity
- Solicitation number
- Not on record
About this file
This document contains a draft request for proposal for an environmental remediation services multiple award task order contract with a total value of $240 million. The contract will be awarded by the U.S. Army Corps of Engineers Omaha District as an unrestricted indefinite delivery/indefinite quantity multiple award task order contract. The draft RFP includes a Section J cost spreadsheet attachment outlining fully burdened binding capped labor rates for various home office and field office personnel as well as other direct costs and subcontractor costs. Industry is requested to provide any comments or concerns regarding the draft RFP by submitting questions via the Bidder Inquiry Key provided in ProjNet. No proposals should be submitted in response to the draft RFP, as a formal RFP under the same solicitation number will be released at a later date.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Draft RFP W9128F21R0033 - 25 Feb 21.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section J Spreadsheet
| Section J- Attachment Cost Spreadsheet (W9128F21R0033 - $240M ERS NWD MEGA MATOC) | ||||
| A. Home Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Program Manager | Hrs. | 80 | $ - 0 | |
| Project Manager | Hrs. | 400 | $ - 0 | |
| Senior Contract Manager | Hrs. | 120 | $ - 0 | |
| Procurement Specialist | Hrs. | 240 | $ - 0 | |
| Safety and Health Manager | Hrs. | 160 | $ - 0 | |
| Clerical | Hrs. | 160 | $ - 0 | |
| Total Section A- Home Office Personnel | $ - 0 | |||
| B. Field Office Personnel | Fully Burdened Binding Capped Labor Rate (Hourly) | Units | Quantity | Subtotal |
| Site Superintendent/ On-Site Supervisor | Hrs. | 320 | $ - 0 | |
| Civil Engineer | Hrs. | 320 | $ - 0 | |
| Chemist | Hrs. | 280 | $ - 0 | |
| Site & Safety Health Officer | Hrs. | 320 | $ - 0 | |
| Contractor Quality Control Supervisor | Hrs. | 320 | $ - 0 | |
| Regulatory Specialist | Hrs. | 320 | $ - 0 | |
| Hazardous Waste Specialist | Hrs. | 320 | $ - 0 | |
| Process Engineer | Hrs. | 240 | $ - 0 | |
| Total Section B- Field Office Personnel | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | Each | 20,000.00 | $ 20,000.00 | |
| Markup Rate (Base Period Year 1) | ||||
| Markup Amount (Base Period Year 1) | $ - 0 | |||
| Subtotal | ||||
| Subcontract effort (plugged number) | Each | 200,000.00 | ||
| Markup Rate (Base Period Year 1) | ||||
| Markp Amount (Base Period Year 1) | $ - 0 | |||
| Subtotal | $ - 0 | |||
| Total Section C | $ - 0 | |||
| Total Estimated Cost (A+B+C) | ||||
| Total Estimated Cost | $ - 0 | |||
| Fixed Fee | ||||
| Fixed Fee Rate | ||||
| Fixed Fee Amount | $ - 0 | |||
| Total Estimate Cost Plus Fixed Fee | $ - 0 |
File details come from the government source that posted it. Updated .