This is a Special Provision document issued by the Department of Transportation, State of Georgia, for a construction project at Pooler Parkway, Benton Boulevard, Mill Creek Circle, and I-95 Southbound Ramps in Pooler, Georgia. The document outlines traffic control requirements and restrictions for the contractor during project execution. The contractor is prohibited from installing lane closures, pacing traffic, or moving equipment and materials that would interfere with traffic on the specified roadways and intersections during peak hours of 7:00 am to 9:00 am and 4:00 pm to 7:00 pm, Monday through Friday. Additionally, all milled surfaces must be covered with asphaltic concrete mix before being opened to traffic in accordance with applicable typical sections.

Non-compliance with the milling surface coverage requirement will result in the assessment of non-refundable deductions as specified in Special Provision Section 150.5.01 Enforcement and Adjustments. These provisions are intended to minimize traffic disruption and maintain roadway safety during construction activities on these high-traffic corridors serving commercial and interstate facilities in the Pooler area.

View the file

Other files

File Type Posted
Invitation to Bid.pdf PDF
Bid Sheet.pdf PDF
Invitation to Bid attachments.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF TRANSPORTATION

STATE OF GEORGIA

SPECIAL PROVISION

POOLER PARKWAY AT

BENTON BOULEVARD, MILL CREEK CIRCLE, AND

I-95 SOUTHBOUND RAMPS

POOLER, GEORGIA

SECTION 150 – TRAFFIC CONTROL

Add the following:

150.6 Special Conditions:

A. The Contractor shall not install lane closures, pace traffic, or move equipment or materials that interfere with traffic on Pooler Parkway, Tanger Outlets Boulevard, Benton Boulevard, Mill Creek Circle, Walmart Driveway, and the I-95 Southbound Ramps between the hours of 7:00 am to 9:00 am and from 4:00 pm to 7:00 pm, Monday through Friday.

B. Miscellaneous

1. Milled Surfaces:

All milled surfaces shall be covered before they are opened to traffic. Failure to cover milled surfaces with asphaltic concrete mix as required by the applicable typical section shall be considered a failure to comply with the requirements of Section 150 Traffic Control and shall result in the assessment of non-refundable deductions as specified in Special Provision Section 150.5.01 Enforcement and Adjustments.