Scope Summary.pdf

PDF 87 KB Posted

Attached to
Modular/Pre-Fabricated SCIF Federal contract opportunity
Solicitation number
W912DY21R0063
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

This document provides details for a federal contract opportunity to construct a modular Sensitive Compartmented Information Facility in Hawaii. The U.S. Army Corps of Engineers Engineering Support Center Huntsville plans to issue a request for proposal for a firm fixed price contract between $1,000,000 to $5,000,000 to provide management, materials, labor and equipment to construct a 2,000 square foot modular SCIF building to be located at Fort Shafter, Hawaii within 180 calendar days. Interested vendors must complete a Statement of Affiliation and submit it by June 30, 2021 to receive the control unclassified information attachments, which will include the technical requirements and response date. The procurement will be a total small business set-aside under NAICS code 236220 for commercial and institutional building construction.

View the file

Other files for this federal contract opportunity

Other files attached to Modular/Pre-Fabricated SCIF, newest first.
File Type Posted
Statement of Affiliation (SoA).docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope Summary Modular/Prefabricated Building

Ft Shafter, Hawaii

The objective for this contract is to provide all management, materials, labor, and equipment to construct a 2,000 SF, one-story Sensitive Compartmented Information Facility( SCIF). A SCIF is a U.S. Government–Accredited Facility where Sensitive Compartmented Information (SCI) can be stored, discussed, or electronically processed.

This facility shall be a totally self-contained, modular construction that can be pre-fabricated and shipped or prefabricated and built on site with all mechanical (heat pump) and electrical utilities incorporated for a true plug and play facility that meets or exceeds ICD 705 (SCIF) standards for accreditation. This facility will not include any toilets or sewer connections but will require electrical connections and some site modifications such as fence addition, tree removal and concrete pavement /walks additions and modifications.

This building shall be placed on a new foundation adjacent to an existing building that will allow for easy, underground electrical power connections from a nearby switchgear.

Modular furniture shall not be a contract required but electrical outlets and power poles shall be designed for the furniture layout included in the scope of work or requested by the users during the design process.

Work shall be performed by a US Owned Company.

Work will be located at Ft Shafter, Hawaii.

The Contractor shall begin performance within 14 calendar days. The contract duration shall be limited to 180 calendar days

File details come from the government source that posted it. Updated .