Scope of Works-Shooting Range 15Feb24-V2..pdf
PDF 1 MB Posted
- Solicitation number
- W50S9324B0001
- Issued by
-
Department of the Army National Guard
About this file
This document outlines an upcoming federal contract opportunity for construction services. The 156th Wing at the Muniz Air National Guard Base in Carolina, Puerto Rico intends to issue an invitation for bids to award a firm fixed-price contract to provide reinforced concrete foundations and pads, utilities, communications infrastructure, and electrical work to support the installation of prefabricated modular small arms ranges. The scope of work includes 52276 square feet of construction with a period of performance of 180 calendar days. The contract is set aside exclusively for small businesses with a NAICS code of 236220 and size standard of $45 million in average annual revenue. The pre-bid conference is scheduled for March 12th, 2024 with questions due by March 26th and bid opening on April 18th, 2024. The solicitation will be posted on SAM.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUERTO RICO AIR NATIONAL GUARD
156TH WING
MUÑIZ AIR NATIONAL GUARD BASE
200 JOSE A. SANTANA AVE, CAROLINA, PR 00979-1502
~ Accountability, Trust, Leadership ~
CUI
Statement of Work: TUMR 232115
Allied Support Small Arms Range
156 WG Muñiz Air National Guard Base (ANGB), Puerto Rico (PR)
Prepared by:
156th Civil Engineer Squadron (CES) / Engineering Flight (CEN)
January 25, 2024
Table of Contents
1.0 DEFINITIONS AND ACRONYMS
2.0 GENERAL
3.0 GOVERNMENT FURNISHED PROPERTY, MATERIAL EQUIPMENT and SERVICES (GFP/M/E/S)
4.0 CONTRACTOR FURNISHED PROPERTY, MATERIALS, EQUIPMENT and SERVICES (GFP/M/E)
5.0 REQUIREMENTS. The Contractor shall:
6.0 SITE VISIT
7.0 FEDERAL ACQUISITION REGULATION (FAR)
8.0 COMPLIANCY
9.0 WORKPLACE SAFETY
10.0 APPLICABLE PUBLICATIONS
11.0 TECHNICAL EXIBITS
1.0 DEFINITIONS AND ACRONYMS
1.1 Definitions.
1.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific suppliers or services to the government. The term used in this contract refers to the prime.
1.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and/or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
1.1.3 CONTRACTING OFFICER’S REPRESENTATIVE (COR). An employee of the US
Government designated by the KO to monitor Contractor’s performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
1.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the work statement.
1.1.5 DELIVERABLE. Anything that can be physically delivered and included no manufactured things such as meeting minutes or reports.
1.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the key personnel listed in the SOW. When key personnel are used as an evaluation factor in best value procurement, and offer can be rejected if it does not have a firm commitment from the person that persons that are listed in the proposal.
1.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
1.1.8 QUALITY ASSURANCE. The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
1.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of
Contractor’s performance.
1.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
1.1.11 SUB-CONTRACTOR. One that enters into a contract with a prime contractor. The
Government does not have privacy of contract with the sub-contractor.
1.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
1.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.
1.2 Acronyms.
1.2.1 AEI – Army Enterprise Info Structure
1.2.2 AFARS – Army Federal Acquisition Regulation Supplement
1.2.3 ANG – Air National Guard
1.2.4 AR – Army Regulation
1.2.5 AUP – Acceptable Use Policy
1.2.6 BBP – Better Business Practice
1.2.7 CDM – Concept Development Meeting
1.2.8 CFR – Code of Federal Regulations
1.2.9 CM – Contract Manager
1.2.10 COMSEC – Communications Security
1.2.11 CONUS – Continental United States
1.2.12 COR – Contracting Officer Representative
1.2.13 COTS – Commercial-Off-The-Shelf
1.2.14 CUI – Controlled Unclassified Information
1.2.15 DA – Department of the Army
1.2.16 DAF – Department of the Air Force
1.2.17 DD250 – Department of Defense Form 250 (Receiving Report)
1.2.18 DD254 – Department of Defense Contract Security Requirement List
1.2.19 DFARS – Defense Federal Acquisition Regulation Supplement
1.2.20 DMDC – Defense Manpower Data Center
1.2.21 DOD – Department of Defense
1.2.22 FAR – Federal Acquisition Regulation
1.2.23 FEMA – Federal Emergency Management Agency
1.2.24 FPCON – Force Protection Condition
1.2.25 FPM – Final Planning Meeting
1.2.26 HQDA – Headquarter Department of Army
1.2.27 IA – Information Assurance
1.2.28 IAW – In Accordance With
1.2.29 IPM – Initial Planning Meeting
1.2.30 IT – Information Technology
1.2.31 JTR – Joint Travel Regulation
1.2.32 JTF – Joint Task Force
1.2.33 KO – Contracting Officer
1.2.34 MHE – Material Handling Equipment
1.2.35 MOA – Memorandum of Agreement
1.2.36 MPM – Mid-Planning Meeting
1.2.37 MSR – Monthly Status Report
1.2.38 NACI – National Agency Check Inquires
1.2.39 NGB – National Guard Bureau
1.2.40 NLT – Not Later Than
1.2.41 OCI – Organizational Conflict of Interest
1.2.42 OCONUS – Outside Continental United States
1.2.43 ODC – Other Direct Costs
1.2.44 OPSEC – Operations Security
1.2.45 PCO – Procuring Contracting Officer
1.2.46 PII – Protection of Personally Identifiable Information
1.2.47 POC – Point of Contact
1.2.48 PoP – Period of Performance
1.2.49 PRS – Performance Requirements Summary
1.2.50 SOW – Scope of Work
1.2.51 QA – Quality Assurance
1.2.52 QAP – Quality Assurance Program
1.2.53 QASP – Quality Assurance Surveillance Plan
1.2.54 QC – Quality Control
1.2.55 QCP – Quality Control Program
1.2.56 SME – Subject Matter Experts
1.2.57 TAR – Travel Authorization Request
1.2.58 TE – Technical Exhibit
1.2.59 WAWF-RA – Wide Area Workflow-Receipt and Acceptance
2.0 GENERAL
2.1 Scope. The Contractor shall provide supervision, transportation, labor, materials, equipment, fuel and any other needed materials and quality control necessary, except as specified in
Paragraph 3.0 as Government Furnished items, to perform work detailed, located in Muñiz
ANGB Carolina, PR as specified in this SOW.
2.2 Background. The mobile shooting range will need infrastructure to be properly secured and operational. Infrastructure requirements are detailed in following chapters.
2.3 Period of Performance (PoP). The PoP shall be 180 calendar days (6 months).
2.4 General Information
2.4.1 Quality Control (QC). The contractor shall develop and maintain an effective QC Plan
(QCP) to ensure services are performed in accordance with this SOW. The contract shall develop and implement procedure to identify, prevent and ensure no recurrence of defective services. The Contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the Contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance
Requirements Summary. A QCP shall be submitted to the COR NLT 10 days after contract award. After acceptance of the QCP, the Contractor shall obtain the KO’s acceptance in writing of any proposed changes to its QCP.
2.4.2 Quality Assurance (QA). The Government shall evaluate the contractor’s performance under this contract in accordance with the QA Surveillance Plan (QASP). This plan is primarily focus on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).
2.4.3 Recognized Holidays. The following are recognized US holidays. The contractor shall not perform services on these days.
2.4.3.1 New Year’s Day
2.4.3.2 Martin Luther King Jr.’s Birthday
2.4.3.3 President’s Day
2.4.3.4 Memorial Day
2.4.3.5 Juneteenth National Independence Day
2.4.3.6 Independence Day
2.4.3.7 Labor Day
2.4.3.8 Columbus Day
2.4.3.9 Veteran’s Day
2.4.3.10 Thanksgiving Day
2.4.3.11 Christmas Day
2.4.4 Place and Performance of Services. The Contractor shall provide services between the hours of 0730 – 1600 on Monday through Friday, except on recognized US holidays or when the
Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings.
Performance shall be the installation mentioned in paragraph 1.1. The contractor, shall at all times, maintain an adequate work force for the uninterrupted performance of all tasks defined within this SOW when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
2.4.4.1 Unscheduled gate closures by Security Forces may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by Contractor’s personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
2.4.4.2 The Contractor’s employees shall become familiar with and obey the regulations of the installation including fire, traffic, safety, and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All Contractor’s employees shall carry proper identification with them at all times. The Contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance.
2.4.5 Security Requirements. The Contractor shall comply with all applicable installation/facility access and local Security Forces procedures, which may be obtained from the COR. The
Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Security Office. The
Contractor shall ensure compliance with all personal identity verification requirements as directed by DOD and/or local policies. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
The Contractor shall coordinate all on-site activity, as required, in conjunction with the COR and the appropriate installation/facility representatives. Installation Entry Access List
(EAL) is required fifteen to thirty (15-30) calendar days ahead for processing, prior to base access approval being granted, along with DD Form 369, Police Record Check and valid Identification (e.g. driver’s license, passport, Real Id, etc.). Additionally, Contractor’s personnel will be responsible to coordinate any escorting required for temporary workers, as determined by Security Forces. Contractors are not compensated for failure to comply with Security Forces policies and procedures for entry.
2.4.5.1 For Contractors that do not require a Common Access Card (CAC), but require access to a DOD facility/installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures. Using the National Crime
Information Center Interstate Identification (NCIC-III) and Terrorist Screening
Database (TSDB) (Army Directive 2014 – 05/AR 190-13), and applicable installation, facility and area commander installation/facility access, and local Security Forces policies and procedures (provided by a Government representative).
2.4.5.2 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DOD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct
COMSEC monitoring and recording of telephone calls originating from, or terminating at DOD organizations. Therefore, the Contractor is advised that any time Contractor place or receive a call they are subject to COMSEC procedures. The Contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The Contractor shall abide by all Government regulations concerning the authorized use of the Government’s computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
2.4.5.3 Protection of Personally Identifiable Information (PII). The Contractor shall protect all
PII encountered in the performance of services in accordance with DFARS 224.103 and
DODD 5400.11, Department of Defense Privacy Program, and DOD 5400.11-R. If a
PII breach results from the Contractor’s violation of the aforementioned policies, the
Contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.
2.4.5.4 Anti-terrorism Level 1 (AT) Awareness Training. All Contractor’s employees requiring access to any installation/facility and controlled access areas shall complete AT Level 1 within ten (10) calendar days after contract start date and within ten (10) calendar days of new employees commencing performance. The
Contractor shall submit certificates of completion for each affected Contractor and sub-contractor employee, to the COR or KO if a COR is not assigned, within ten (10) calendar days after completion of training. AT Level 1 is available at https://jko.jten.mil/courses/AT-level1/launch.html.
2.4.5.5 Photos. Only key Contractor’s personnel are authorized to take pictures of the construction area. Careful planning must be taken to ensure no aircraft, facilities or military personnel appear in pictures inadvertently. A list of key personnel required to take pictures will be submitted to the COR for review and approval NTL ten
(10) days after project award. Once approved, the list shall be made available at any time in the construction site, if requested by COR, Security Forces, or Fire
Department.
2.4.6 Physical Security. The contractor shall safeguard all Government property provided for
Contractor use. At the close of each work period, Government Facilities, equipment and materials shall be secured. A construction work area plan shall (Physical Security Submittal) be submitted to the COR before placing construction fencing and must maintain emergency entry/exit access for Security Forces & Fire Department personnel.
2.4.6.1 Key Control. To access the site, a code will be provided by the COR to key personnel only. This code is to be protected at all times and cannot be divulge. Sharing the code without authorization may result in loss of base access privileges. Codes are expected to change bi-weekly, but the COR will make proper notifications in coordination with the Operations Flight of the Civil Engineer Squadron.
2.4.7 Special Qualifications. The contractor shall ensure all employees possess all required licenses for operating heavy equipment, welding licenses, Material Handling Equipment
(MHE) (i.e. forklift) and any others, in the performance of this contract. The Government does not provide training to Contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified and qualified to provide services. Certifications & licenses may be requested at any time by the COR, Base Safety and Fire Department.
2.4.8 Post Award Conference/Periodic Progress Meetings. The Contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition
Regulations (FAR) subpart 42.5. The KO, COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor’s performance. At these meeting, the KO will apprise the contractor of how the Government views the Contractor’s performance and the Contractor shall apprise the Government of problems, if any, being experienced. The Contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
2.4.8.1 Weekly Activity Report (WAR): The Contractor shall provide the Contracting Officer
(KO) and Contracting Officer Representative (COR) assigned with a WAR every
Friday at 1200 hours (AST).
2.4.8.2 Scheduled Percentage (%) Construction progress vs Actual Percentage (%)
Construction Progress
2.4.8.2.1 If the actual is over 10% Behind Schedule, please provide an explanation with a get-well plan.
2.4.8.3 Estimated Project Completion Date.
2.4.8.4 A simple summary of the upcoming key work being performed in the following weeks.
2.4.8.5 Submittals/Requests for Information (RFI) that are pending.
2.4.8.6 New pictures of the site of the work tasks accomplished during the week (A minimum of 4 new pictures every week).
2.4.8.7 Additional pertinent information requested by the COR or deemed necessary by the contractor.
2.4.9 Contract Manager (CM). The Contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the
Contractor when the CM is absent, shall be designated in writing to the KO within three (3) calendar days after contract award. The CM or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract.
The CM shall work through the COR, or KO if a COR is not assigned, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that Contractor’s employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure
Contractor’s employees understand that services performed outside the scope of the contract are performed wholly at the expense of the Contractor.
2.4.10 Identification of Contractor Employees. All Contractor’s personnel attending meetings, answering Government telephones and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The Contractor shall ensure that all documents or reports produced by Contractor’s personnel are suitably marked as
Contractor products or that Contractor participation is appropriately disclosed. The
Contractor’s status as a “Contractor” shall be predominantly displayed in all correspondence types (to include signature block on emails) and dealings with Government or non-
Government entities. Contractor’s personnel shall wear identification badges visibly displayed and also mark all vehicles with company name while inside the installation visibly displayed. The badges shall have the company name, employee name and the word
“Contractor” displayed. The Contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e. badges and vehicle passes) shall be returned to the COR within the ten (10) days of an employee’s departure or contract completion.
2.4.11 Combating Trafficking in Persons. The US Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and Contractor’s employees shall not engage in any forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the US Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The
Contractor shall take appropriate action, up to and including termination against employees or sub-contractors that violate US Government policy as described at FAR 22.17.
Contractor shall complete the following online training within ten (10) calendar days after contract award – Course available at https://jko.jten.mil/courses/J3TA-US1328-
A/launch.html.
2.4.12 Data Rights. The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the
Contractor without written permission from the KO. All materials supplied to the
Government shall be the sole property of the Government and may not be used for any other purpose. Provide a copy ten (10) calendar days after contract completion. This right does not abrogate any other Government rights.
2.4.13 Organizational Conflicts of Interest (OCI). The Contractor and sub-contractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection. In addition to substantial (e.g. cost or pricing information, budget information or analyses, specifications or work statements, etc.).
Perform evaluation services, which may create current or subsequent OCIs, as defined in
FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
2.4.14 Safety Plan. Contractor shall submit a Safety Plan to the COR NLT ten (10) calendar days after contract award.
2.4.15 Environmental Plan. Contractor shall submit an Environmental Plan to the COR NLT ten (10) calendar days after contract award. Include State permit requirements, to include but not limited to: “Oficina de Gerencia y Permisos” (OGPe for Spanish acronym), “Departamento de Recursos Naturales y Ambientales” (DRNA for Spanish acronym), and
“Permiso Unico Incidental” (PUI For Spanish Acronym) environmental requirements for the project, including evidence of environmental compliance such as Categorical Exclusion or
Environmental Assessment (National Environmental Policy Act, NEPA like process).
2.4.16 Waste Management Plan. Contractor shall submit Waste Management Plan to the
COR NLT ten (10) calendar days after contract award. The Contractor shall submit to the COR for approval prior to commencement of services, IAW UFGS 01 74 19
Construction Waste Management and UFGS 02 81 00 Transportation and Disposal of
Hazardous Waste. The project waste diversion goal is 60%. Approval of the Contractor’s
Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. This plan shall be coordinated with the installation waste management plan so there are no conflicts. This plan may be incorporated with the Environmental Plan. Disposal slips from landfill and/or recycler must be submitted to the COR to report amounts of debris landfilled or recycled on April 1st and October 1st of the past 6 months, respectively.
If the project ends before these dates, submit the report with the closure documentations.
2.4.16.1 April’s Report (October through March)
2.4.16.2 October’s Report (April through September)
2.4.17 Health and Safety Plan (HSP). The Contractor shall prepare a site-specific HSP to comply with Air Force, Occupational Safety and Health Administration (OSHA), United States
Environmental Protection Agency (USEPA), state Puerto Rico (PR-OSHA), and local health and safety regulations regarding the proposed work. The Contractor shall also submit a HSP that included worker health and safety practices for the asbestos and lead work activities. The HSP must include valid certificates for each worker that will be included in the demolition, showing they have completed the Asbestos Hazard Emergency Response
Act (AHERA), OSHA, and PR-OSHA training requirements. The Contractor shall notify the KO and COR within three (3) calendar days if a change is required to the HSP. The
Contractor shall adhere to USEPA guidelines for designating the appropriate levels of protection needed at the demolition site(s) as applicable. The Contractor shall maintain and have readily available written certification that the approved HSP has been reviewed and briefed with all personnel that work at the project site prior to the employee’s start date.
2.4.18 Site Closure Report. As applicable, the Contractor shall prepare and submit to the Base
Environmental Management Office and COR, for review and approval, a draft and final closure report, as required, for the asbestos and lead abatement permits. Typical processing time is twenty-one (21) calendar days for the initial review/approval and, if necessary, fourteen (14) days for resubmittal review/approval.
3.0 GOVERNMENT FURNISHED PROPERTY, MATERIAL EQUIPMENT and
SERVICES (GFP/M/E/S)
3.1 The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract.
3.2 Property. Government will authorize contractor to an area for material storage and temporary office.
3.3 Material. None.
3.4 Equipment. None.
3.5 Services. None.
3.6 Utilities. Contractor will be authorized, if needed, to connect to local water and electricity for administrative purposes. Use of water or electricity for construction work is prohibited.
Contractor will request approval to connect to any utility and follow strict base procedures.
Any deviation or damage will be solely the contractor’s responsibility to repair to original or better state.
4.0 CONTRACTOR FURNISHED PROPERTY, MATERIALS, EQUIPMENT and
SERVICES (GFP/M/E)
4.1 General. Except for those items specifically stated to be Government-Furnished in paragraph
3.0, the Contractor shall furnish everything required to perform these services as indicated in paragraph 2.1.
4.2 Bathroom. The Contractor shall provide portable bathrooms for their employees during the
PoP accompanied by its periodical maintenance.
5.0 REQUIREMENTS. The Contractor shall:
5.1 General infrastructure
5.1.1 Provide all required infrastructure IAW UFC 1-200-01 DOD BUILDING CODE for the
Small Arms Range equipment to be installed in a “plug and play” style, to include, but not limited to: civil site work, foundation, slab on-grade, access to and from facility and underground main electrical and communications connection. The equipment design is provided in Attachment 3, so the equipment can be installed and plugged without issues.
5.2 Site Preparation, solid work and sidewalks/access
5.2.1 All site preparation work shall be compliant with UFC 3-301-01 Structural Engineering, latest version, UFC 3-220-01 Geotechnical Engineering, latest version, and the Puerto Rico
Building Code, latest applicable version. If guidance conflicts, most restrictive guidance will be followed and submitted to COR for final review/acceptance.
5.2.2 Contractor shall prepare civil site area above the 100-year storm maps, as provided by
Federal Emergency Management Agency (FEMA), and compliant with UFC 3-301-01 elevation requirements above floodzone. Attachment 4 has the screenshot of the FEMA
Flood Map.
5.2.3 Once final elevation is prepared above flood zone, access to facility will need to be provided
IAW NFPA 101. Staircases, ramps, and sidewalks are to be considered and submitted.
General site layout has been provided in attachment 1 to include: building location, pads, sidewalks, and ramps.
5.3 Foundation
5.4 All foundation work shall be compliant with UFC 3-301-01 Structural Engineering, latest version, and the Puerto Rico Building Code, latest applicable version. If guidance conflicts, most restrictive guidance will be followed and submitted to COR for final review/concurrence.
5.5 The main purpose of this section is to provide foundation that can withstand the forces calculated, per the attachment 3. Sample foundation design has been provided in attachment
3.
5.6 Contractor shall design a footer and if needed, take soil samples, to validate or improve soil classification assumptions (Class D).
5.7 Concrete shall not be mixed on site for foundation requirements. It must be mixed and prepared in a concrete batch plant, IAW UFC 3-301-01 strength requirements and attachment
3 guidance. Compression and flexible strength results are to be submitted.
5.8 Slab on-grade
5.8.1 All slab on-grade work shall be compliant with UFC 3-301-01 Structural Engineering, latest version, and the Puerto Rico Building Code, latest applicable version. If guidance conflicts, most restrictive guidance will be followed and submitted to COR for final review/acceptance.
5.8.2 Slab on-grade design shall comply with load assumptions, per attachment 3, to include all the pads.
5.9 Concrete shall not be mixed on site for foundation requirements. It must be mixed and prepared in a concrete batch plant, IAW UFC 3-301-01 strength requirements and attachment 3 guidance. Compression and flexible strength results are to be submitted.
5.10 Electrical
5.10.1 All electrical work shall be compliant with UFC 3-501-01 Electrical Engineering, the latest version, the Puerto Rico Building Code, latest applicable version, and National
Electrical Code (NEC), applicable standard. If guidance conflicts, most restrictive guidance will be followed and submitted to COR for final review/acceptance.
5.10.2 The main purpose is to underground connect the facility to a primary high voltage line, via a new transformer, to properly function. The load requirements are provided by the design in attachment 3 and the connection to the base is on attachment 5: Electrical &
Communications Site Plan.
5.10.3 Per attachment 5, contractor shall design a connection from the primary high-voltage to a transformer, to the facility main electrical connection and provide for Government review and acceptance. Contractor shall ensure all lines are properly identified.
5.10.3.1 Primary line needs to be in the proper conduit, per code & criteria, and at least four (4) feet deep, IAW UFC 3-501-01 & NEC.
5.10.3.2 The transformer shall handle the load capacity designed and properly connect the high-voltage line to the facility, per attachment 3, and provide a corrosion resistant assembly.
5.10.4 A meter shall be installed before the final facility connection that will read the electrical consumption of the facility. The meter shall be legible visually and also provide the ability to read remotely via internet application accessible by the Base Civil Engineer.
Application and access shall be provided for the life of the facility. Further installation guidance may be provided on wireless connectivity.
5.10.5 Refurbish the primary high-voltage line manhole IAW code & criteria requirements, to include but not limited to: primary elbows, lightning protection, splice bar, etc. Pictures are provided on attachment 6: manhole pictures.
5.11 Communication Support
5.11.1 Provide underground conduit to connect facility from main communications point to main entrance point in facility per attachment X and IAW “State regulation here from Comm”.
5.11.2 A layout drawing with COMM drops and location shall be submit for review prior to installation.
5.11.3 COMM cable shall be Cat 6 U/UTP. Contractor shall submit a test report for all cables.
5.12 As-Builts
5.12.1 As builts for all work shall be provided in paper, pdf to scale and CAD format, as part of the final project documents and acceptance. Project will not be considered complete nor final payment considered without as-builts submitted.
5.12.2 A DD1354 will be prepared by the contractor as part of the as-built submittal, IAW DAFI
32-9005 Real Property Accountability.
5.13 Miscellaneous
5.13.1 Signage: Any required signs, IAW UFC 3-120-01 Design: Sign Standards, shall be provided and installed.
5.13.2 Project Construction sign: The contractor shall install a project sign compliant with UFC
UFC 3-120-01 Design: Sign Standards, paragraph 3-7.5, and UFGS 01 58 00. Sign shall be submitted for review and approval of COR before approval. Ensure the sign has the following information: 156th Wing emblem, Prime BEEF emblem, Contractor Name POC, and Base POC’s names (COR & Base Civil Engineer).
5.13.3 Project site: contractor shall secure the project site completely with construction fencing.
Signane shall be posted to not enter site, IAW OSHA & Safety AFI requirements.
5.13.4 Laydown yard: The contractor shall submit a laydown yard request for base consideration.
Laydown yard shall me limited in size and submittal must be justified with a site plan and material expected. Laydown yard shall be co-located with project site.
5.13.5 Maintenance Manuals & Training
5.13.5.1 All manuals for maintenance of the equipment shall be provided in English & Spanish.
5.13.5.2 Contractor shall offer two (2) training sessions, one in English and one in Spanish, in to maintain, troubleshoot, and operate the transformer, and a walkthrough of the main area of the project to the Civil Engineer Squadron, Operations Flight. The training shall be coordinated through the COR with sufficient notice, at least two (2) weeks.
6.0 SITE VISIT
6.1 All quantities and measurements herein are approximate. Contractor is responsible to conduct a site visit for verification prior proposal submission. If questions arise, Request for
Information (RFI) shall be submitted to the Contracting Officer and COR.
7.0 FEDERAL ACQUISITION REGULATION (FAR).
7.1 This statement of work does not supersede any FAR stipulations that may appear in this contract.
7.2 For more up to date information visit https://www.acquisition.gov/browse/index/far.
8.0 COMPLIANCE
8.1 The Contractor is subject to all Installation Fire, Safety, Security, Civil Engineer, OPSEC, Traffic Regulations and all applicable Federal and State Regulations.
8.2 Fire Safety. The Contractor shall comply with all local fire regulations and NFPA 241 during all demolition and construction work. All fire extinguishers required shall be provided and maintained by the contractor, but must be approved for use by the KO prior to use.
8.2.1 Hot-work operations. Those involving welding, soldering, brazing, or torch heating (i.e.
open flame or grinders) shall not commence before an AF Form 592 is completed and signed by the Fire Inspector. The Contractor shall contract the Fire Department’s inspection section at least one (1) work day prior to –hot work operations for assistance and completing the Form 592. There shall be no open burning of waste materials or debris during this contract.
8.3 Digging Permit. Contractor must request a digging permit to the COR and have it approved prior start any digging work. Timeliness is of importance, as dig permits take
15 calendar days, on average.
8.4 Confined Space Entry. Contractor must request a confined space entry AF Form 1024 to the COR and have it approved prior to entering a confined space.
8.5 Contractor must be registered (current) in the System for Award Management (SAM) internet program at http://www.sam.gov.
8.6 All invoices must be submitted using Wide Area Workflow (WAWF) internet program and verify the statuses at https://wawf.eb.mil.
8.7 RESERVED
9.0 WORKPLACE SAFETY
9.1 The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.
9.2 The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor. The KO may notify the
Contractor of hazards in Contractor’s operations/performance that endanger Government personnel or property and require appropriate abatement or mitigation action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.
9.3 Accident prevention principles must be thoroughly integrated into all operations. Unsafe conditions and practices, as identified by the KO or COR, must be corrected immediately,
9.4 Solid Waste Management. Any and all debris generated by the Contractor’s operations shall be removed from the base. All waste materials and debris generated by work under this contract shall be processed, handled, transported, stored, and disposed of by the Contractor
IAW all Federal, State, and local regulations and laws. All waste streams will be quantified and reported to the Base Environmental Manager. The Contractor shall be responsible for any permit or fees associated with the use of off-base disposal locations.
9.5 All refuse and remaining materials related to the work will be taken daily to a refuse container provided by the Contractor.
9.6 Only company cars with distinctive logos posted at the passenger and driver doors will be authorize inside Base premises.
9.7 All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.
9.8 At the end of each working day, all areas will be clear from equipment, tools and materials.
9.9 Special precautions will be taken at no cost to Government to protect Base property during the project execution.
9.10 The use of Personal Protective Equipment (PPE) is mandatory at all time while working on the project.
9.11 The Contractor shall be liable for any loss, destruction or damage and deterioration to
Government property, including vegetation and landscaping, resulting from Contractor operations. Any damage to Government or personal property shall be repaired or replace to the KO’s satisfaction at the Contractor’s expense.
9.12 All work under this project shall meet applicable County, Territorial, Federal and Air
National Guard construction codes, regulations and policies.
9.13 Contractor shall coordinate with KO to verify the existing site and facility conditions. Any differing conditions shall be notified in writing to request clarification.
9.14 Equipment or fixtures Government Furnished Contractor Installed (GFCI): None anticipated.
9.15 Comply with all specifications applicable found and included by reference in the www.wbdg.org site. This will include all UFC and UFGS.
9.16 For additional information on drawings and specifications, and for entering the site premises, please contact the COR or alternate point of contacts.
9.17 For additional environmental information, contact the Environmental Manager Office in
Building 71, Muñiz ANGB telephone (787)253-5192.
9.18 For additional safety information contact the Safety Office in Building 22, Muñiz ANGB telephone at (787)253-5275.
9.19 For additional fire information contact the Fire Department in Building 3, Muñiz ANGB telephone at (787)253-5222.
9.20 For additional security information contact the Base Defense Operation Center (BDOC) in
Building 99, Muñiz ANGB telephone at (787)253-5204.
10.0 APPLICABLE PUBLICATIONS
10.1 Publications applicable to this SOW are listed below. Always use latest publication.
Publication Website
Federal Acquisition Regulation www.acquisition.gov/browse/index/far Defense Federal Acquisition Regulation http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html
AR 190-13 The Army Physical Security http://www.apd.army.mil/ProductMaps/PubForm/AR.aspx
AR 530-1 Operations Security http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx DOD 5220.22-M National Industrial Security Program http://www.dtic.mil/whs/directives/corres/pub1.html
DG 415-5 General Facilities Design https://www.wbdg.org/FFC/ARMYCOE/NATLGUARD/dg_415_5.pdf
DAFI 91-202 THE US AIR FORCE
MISHAP PREVENTION
PROGRAM
https://static.e-publishing.af.mil/production/1/af_se/publication/dafi91-
202/dafi91-202.pdf
29 CFR 1926 OSHA Construction www.OSHA.gov
AR 385-10 Chapter 4 Safety Program http://www.ngbpdc.ngb.army.mil/pubs/385/ngr385_10.pdf
DAFI 32-9005 Real Property Accountability https://static.e-publishing.af.mil/production/1/af_a4/publication/dafi32- 9005/dafi32-9005.pdf
Main site for all United Facilities Criteria (UFC) www.wbdg.org
Site for United Facilities Guide Specifications (UFGS) https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/
UFC 1-200-01 DOD Building Code https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-
UFC 3-120-01 Design: Sign Standards https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-120-
UFC 3-220-01 Geotechnical Engineering https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-220-
UFC 3-301-01 Structural Engineering https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-301-
UFC 3-501-01 Electrical Engineering https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-501-
UFC 4-010-01 DOD Min. AT/FP Standards For Buildings https://pdc.usace.army.mil/library/ufc/4-010-01/
TECHNICAL EXIBITS
11.1 Technical Exhibit 1. Performance Requirements Summary (PRS)
11.1.1 This PRS included performance objectives the Government will use to determine
Contractor performance and will compare contractor performance to the Acceptable
Quality Level (AQL).
Discipline
Task
Perform ance Stand ard
Acceptable Quality Level
(AQL)
Surveillance Method/By Whom
Quality Control
a. Quality of Workmanship
b. Adequacy of the CQC Plan
c. Implementation of the CQC Plan
d. Quality of QC Documentation
e. Storage of Materials
f. Adequacy of Materials
g. Adequacy of Submittals
h. Adequacy of Testing
i. Adequacy of As-Built
j. Use of Specified Materials
k. Identification/Correction of deficiency works in a timely manner
100%
98%
Periodic
Inspection COR will review monthly work order logs.
Effectiveness of Management
a. Cooperation and Responsiveness
b. Management
Resources & Personnel
c. Coordination and Control of Subcontractors
d. Adequacy of Site Clean-up
e. Effectiveness of Job Site
Supervision
f. Compliance with Laws and
Regulations
g. Professional Conduct
h. Review/Resolution of
Subcontractors Issues
COR will review monthly
Timely
Performance
a. Adequacy of Initial Progress Schedule
b. Adherence of Approved Schedule
c. Resolution of Delays
d. Submission of Required Documentation
e. Completion of Punch List Items
f. Submission of Updated and Revised Progress Schedules
g. Warranty Response
COR will review monthly work order logs.
Compliance with Safety Standards
a. Adequacy of Safety Plan
b. Implementation of Safety Plan
c. Correction of Noted Deficiencies
Inspection COR will review monthly
11.2 Technical Exhibit 2. Submittal List
Description Type QTY Due Remarks Material Approval Submittals: (All materials used on project)
1. Mobilization plan, physical security & laydown yard
2. Quality Assurance Plan
3. Safety Plan
4. Approved Project Permits
5. Environmental & Waste
Management Plan
6. Final Civil Site elevation
7. Final Electrical Connection
8. Final Foundation
9. Final Slab-on grade
10. Final Communication connection
11. Civil site soil lift plan with passes & compaction requirements
12. Electrical materials
13. Electrical Technician license
14. Worker Compensation Insurance
Certificate
15. Concrete compression & flexible test reports
16. Civil site compaction report
17. Warranty Plan
18. As-Builts
19. Draft DD1354
AF Form
1 each (if needed to split, please advise
COR)
NLT 7 days prior installing
Must be signed by:
KO
COR
Contractor (return copy)
11.3 Technical Exhibit 3. Design and Construction Standards and References.
11.3.1 American Society for Testing and Materials (ASTM) – Latest Edition
11.3.2 Unified Facilities Guide Specification (UFGS)
11.3.3 All Federal applicable UFC, UFGS and ANG ETL’s must be verified at www.wbdg.org.
11.4 Technical Exhibit 4. Invoice Requirements.
11.4.1 Electronic pictures of work to be invoiced (Before and After).
11.4.2 Breakdown for Payment
11.4.3 RESERVED
11.4.4 Progress Report of activities
11.4.5 Contractor provide COR a Draft and Interim DD Form 1354 Transfer and Acceptance of
Real Property, IAW DAFI 32-9005 Real Property Accountability
11.5 Technical Exhibit 5. Closeout Documentation.
11.5.1 Contractor workmanship letter of warranty up to one year.
11.5.2 Recycling or landfill proof of disposition document.
11.5.3 Contractor certificates of no debts to suppliers and vendors.
11.5.4 Commissioning and acceptance of system.
11.5.5 Contractor and COR completed DD Form 1354 Transfer and Acceptance of Real Property
11.5.6 Certification of work by a professional refrigeration provider IAW Puerto Rico’s Law 416
11.5.7 Contractor’s as-built drawing (electronically PDF and CAD file) as applicable.
Attachment 1: Site Layout
Attachment 2: Site Pictures
EAST
SOUTH
WEST
NORTH
Attachment 3: Mobile Range Drawings
Provided in separate file.
Attachment 4: FEMA Flood Map
Attachment 5: Electrical & Communications Site Plan