Scope of Work STA NOLA Sewage pump.pdf

PDF 720 KB Posted

Attached to
USCG Station New Orleans Sewage Pump replacement
Solicitation number
70Z02925QNEWO0097
Issued by

About this file

This document is a Contract Specification for replacing a sewage lift station pump at the U.S. Coast Guard Station in New Orleans, Louisiana. The project requires a contractor to furnish labor, tools, equipment, and materials to install a new sewage pump matching the existing functioning pump, diagnose and repair issues with float switches and relays, and ensure proper lead/lag system operation. The contractor must be a Louisiana-certified plumber and electrical contractor, comply with National Electric and International Plumbing Codes, and complete a mandatory site visit prior to bidding.

Key project parameters include a 120-calendar day performance period, work to be conducted Monday through Friday from 7:00am to 4:00pm, and all associated parts and materials must be new and unused. The project involves replacing the existing number 2 sewage pump, associated piping, and electrical components at the Coast Guard Station located at 201 Metairie-Hammond Highway. The solicitation is a small business set-aside with a Firm-Fixed Price Construction Contract to be awarded on a Best Value basis, with quotes due by 3:00pm CST on May 12, 2025.

View the file

Other files

File Type Posted
FAR Clause Replace Sewage Lift Station Pump.pdf PDF
SF1442-2-1.pdf PDF
Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT SPECIFICATIONS

REPLACE SEWAGE LIFT STATION PUMP

AT

UNITED STATES COAST GUARD

Station New Orleans

Metairie, LA

PROJECT NUMBER 29096866

April, 2025

Project location:

USCG Station New Orleans 201 Metairie-Hammond Hwy Metairie, LA 70005

POC: MKCS Robert W. Zaabel, EPO Alt POC: MK1 Robbie Johnson, AEPO Contact number: 504 428 8002

Section 01 11 00

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1. GENERAL DESCRIPTION

1.1.1. General Work Requirements

Furnish all labor, tools, equipment, and materials for the instillation of a new number 2 sewage pump to match the number one sewage pump and all associated piping at Coast Guard Station New Orleans. Supply and replace pump for lift station. Diagnose issues with float switches and relays that maybe causing the lead/lag system to malfunction. Inspect wiring, connections, and relays to identify faults. Check the float switches to ensure they are properly adjusted and functioning. Verify relay operation and proper sequencing in the lead/lag system. Perform continuity tests, voltage checks, and review control logic for proper operation. Make any repairs as necessary to restore proper system operation.

A. Contractor shall provide and install a new Sewage pump to match the Number one pump already installed.

B. Contractor shall provide replacement of associated piping, test and replace any faulty electrical components to include float switches, limit switches, etc. to bring both pumps to proper working order as designed.

C. Contractor Shall provide all materials associated with the completion of this project.

D. This summary is not all inclusive and delineates only those work items deemed as major to the contract. Ancillary work items necessary to attain the completed project, shall be included in the contract as inherent to the work.

1.1.2. SPECIFIC WORK REQUIREMENTS

A. Qualifications

(1) The installation shall be performed by a plumber and electrical contractor certified in the state of Louisiana.

(2) The installation shall comply with the most current edition of the National Electric Code and the International Plumbing Code.

B. Additional Performance Requirements

(1) Contractor is required to complete a site visit prior to submitting a bid.

(2) Contractor shall be responsible to dispose of the existing number 2 sewage pump and associated piping.

(3) Both pumps must operate as designed and work with the current control unit on the second floor of the Station New Orleans main building.

(4) All associated parts, materials, and equipment shall be new and unused.

1.1.3. SPECIAL WORK REQUIREMENTS

A. Comply with all hot work requirements of the Coast Guard unit.

B. Coordinate all staging and laydown areas with the Coast Guard Station New Orleans POC prior to work starting.

C. Comply with all OSHA and industry standards for confined space entry.

1.2. TEMPORARY FACILITIES OR UTILITIES

None required.

1.3. PROJECT PERFORMANCE PERIOD

A. The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.

B. The total contract performance period is 120 calendar days.

1.4. LOCATION

The work is located at:

U.S. Coast Guard Station New Orleans 201 Metairie- Hammond Hwy Metairie, Louisiana, 70005

Arrangements for visiting the site may be made by contacting:

Senior Chief Robert Zaabel, MKCS, EPO Email: Robert.w.zaabel@uscg.mil Telephone: (504) 428-8002

1.5. DRAWINGS ACCOMPANYING SPECIFICATION

There are no drawings accompanying this specification.

1.6. WORK HOURS

1.6.1. Normal Working Hours

A. Perform all work at the site from Monday through Friday from 7:00am to 4:00 pm, unless otherwise approved. The contractor shall plan a schedule to minimize disruptions to building operations.

B. Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.

1.7. SPECIFIC ENVIRONMENTAL REQUIREMENTS

There are no specific environmental requirements. Refer to section titled Environmental for general environmental requirements.

1.8. SAFETY PROGRAM

1.8.1. General

The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.

1.9. AVAILABILITY OF UTILITY SERVICES

A. Reasonable amounts of the following utilities will be made available to the Contractor without charge.

(1) Electricity

(2) Potable Water

(3) Access to toilet facilities

B. The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The contractor shall be responsible for making connections including providing back flow preventers, transformers and for disconnection.

1.10. UNDERGROUND AND CONCEALED UTILITIES

A. Any utility locations provided are diagrammatic, not exact.

B. Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.

1.11. UTILITY OUTAGES

Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).

1.12. CONTRACTOR USE OF PREMISES

The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Provide temporary covers on excavations that remain open overnight.

1.13. CLEANUP

The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.

1.14. ENVIRONMENTAL

1.14.1. Protection of the Environment

The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act (MBTA), National Historic Preservation Act (NHPA), the Resource Conservation and Recovery Act (RCRA), and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).

1.14.2. Generated Waste

A. Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.

B. Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with RCRA and all applicable federal, state, and local laws and ordinances.

C. Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.

1.15. DISPOSITION OF MATERIALS

A. All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.

B. The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal.

1.16. STORM PROTECTION

The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property. Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

1.17. RECEIPT OF MATERIALS

The Contractor is responsible to receive all equipment, materials, and supplies.

1.18. DELIVERY AND STORAGE

The Contractor is responsible for the proper transport and storage of all equipment and materials.

1.19. SECURITY

A. Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.

B. Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior Notification, for notification requirements.

Only personnel on the approved list are allowed onto the project site.

C. All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the Real ID Act of 2005. Non-compliant personnel shall be escorted off Government property.

1.20. FINAL INSPECTION AND ACCEPTANCE

A. Electronically submit a written request for final acceptance to the Coast Guard.

1.21. WARRANTIES

A. Endorse all warranties or guarantees to the Government.

1.22. TRAINING

A. The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.

1.23. SUBMITTALS

A. Submittals will be reviewed by the Coast Guard and returned within 10 working days after receipt, unless otherwise stated.

1.24. SUBMITTAL LIST

A. ROSTER OF PERSONNEL

(1) As required by the paragraph titled Security.

B. PROJECT SCHEDULE

(1) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.

C. SAFETY PLAN

(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety Program.

D. PRODUCT DATA

(1) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts.

Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.

1.24.2. OPERATION AND MAINTENANCE MANUALS

A. Submit electronically and provide the following:

(1) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier;

(2) Warranty information;

(3) Test procedures;

(4) Results of all testing and commissioning procedures;

(5) Performance data;

(6) A control sequence describing start-up, operation and shut-down instructions;

(7) Installation instructions;

(8) Maintenance instructions;

(9) Operating instructions;

(10) Parts list.

-- End of Section –