This Scope of Work document outlines a partial roof replacement project for the Office for People with Developmental Disabilities (OPWDD) at the French Road Facility in Utica, New York. The project involves complete demolition of existing roofing materials down to the roof sheathing, installation of new plywood decking where necessary at $155 per sheet, replacement of all flashing and drip edge components, installation of ice and water barriers extending 36 inches inside the exterior wall line, application of Pro Armour synthetic underlayment across the entire roof surface with specialty underlayment in valleys, and installation of Owen Corning Duration brand starter shingles and hip and ridge shingles fastened with a minimum of six nails per shingle. The work must conform to the 2020 New York State Residential Building Code with specified exceptions regarding valley construction, ice barriers, and material restrictions. A mandatory site visit is scheduled for Thursday, November 12th at 10 a.m. at 315 French Road, Utica, NY 13502. The project must be completed within 30 days of award, and all work shall be performed between unspecified hours Monday through Friday in coordination with the House Director and project manager. This is designated as a New York State Public Works project requiring prevailing wage payments under PRC# 2026030260.

The bid price must include all materials, labor, disposal fees, and site cleanup costs. The contractor shall maintain a clean and orderly job site at all times, utilizing a roller magnet to remove all nails from walks, drives, parking lots, and lawns. The contractor bears full responsibility for any lawn or property damage caused by material delivery or work performance and must restore the property to its pre-project condition. Prior to commencing work, a meeting with DDSO Operations and Maintenance staff must occur to address safety requirements, and all applicable environmental testing shall be provided to the contractor beforehand. The residence will be occupied during the project, requiring contractors to implement safety measures to protect residents and staff, secure all tools and materials at day's end, and coordinate work to avoid interference with facility operations. Smoking is prohibited at all OPWDD residential sites, and any unforeseen conditions that may alter the established price must be reported immediately to the Plant Superintendent.

View the file

Other files

File Type Posted
CNY BID FORM- French Rd IRA Roof.doc DOC document
CNY DDSO Contractor Requirements 2026.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SCOPE

DESCRIPTION:

The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to scope of work and architectural drawings if supplied. Work is to be completed within 30 days of award, unless modified below. This is a NYS Public Works project and prevailing wages are to be paid, PRC# 2026030260. Refer to attached specification for the following scope of work. Site must be cleaned and all materials secured at the end of each work day. Absolutely no scraps, especially fasteners, are to be left unsecured. Upon completion, before removal of equipment and scaffolding, contractor is to schedule a quality control and quality assurance inspection with project manager.

SCOPE OF WORK includes, but is not necessarily limited to the following:

General Requirements

A. The scope of this work includes all labor and material, equipment, and services necessary to complete the work herein specified at various locations throughout the Central New York

Developmental Services county areas.

B. All work and materials shall conform to the 2020 New York State Residential Building Code with the following exceptions:

• Staples and aluminum nails are not allowed.

• Open valleys are not permitted.

• Valley linings shall be specialty underlayment complying with ASTM D 1970 and at least 36” wide centered in the valley.

• An ice barrier shall only consist of a self-adhering polymer bitumen sheet and extend to a point at least 36” inside the exterior wall line of the building, as per R905.2.7.1.

• Installation or materials specified in scope exceed code requirements.

C. No asbestos-containing products or materials may be used.

D. A product specification sheet and Safety Data Sheet will be provided to PSES for all products being used or provided for approval prior to use.

E. Do not install shingles, felt, or sheathing when it is raining or over wet surfaces.

F. Do not apply shingles when air temperature is below 32 degrees Fahrenheit.

Facility:

Frech Rd.

Facility Address:

315 French Rd. Utica N.Y. 13502

Point of Contact:

Jim Bell

Contact Phone Number: 315-281-7760

Project Title:

Roof Replacement

Summary of Work:

Partial roof replacement.

G. All scraps and debris shall be removed from the job site at the end of each workday. Entire job and work areas shall be kept neat and orderly as reasonably possible at all times while work is underway. Clean up includes the use of a roller magnet to assure all nails are removed from walks, drives, parking lots, and lawns.

Demolition and Disposal:

The contractor shall strip all existing materials down to the roof sheathing and dispose of them.

This includes but is not limited to shingles, underlayment, flashing and any other roofing components.

Plywood Replacement:

• Plywood shall match existing decking, OSB not acceptable.

• Plywood sheets that need replacing will be paid for at $155 per sheet.

Flashing and Penetrations:

All existing flashing and drip edge shall be removed and replaced with new flashing and drip edge.

2” aluminum drip edge color matched to the trim shall be installed along the rake and eave edges of the roof. Roof penetration boots shall also be removed and replaced with new boots.

Chimneys: Crickets shall be installed above chimneys, sized and sloped to direct water around the chimney.

Ice and Water Barrier:

The contractor shall install an ice and water barrier that extends 36” inside the exterior wall line of the building, using a self-adhering polymer bitumen sheet.

Synthetic Underlayment:

The contractor shall install Pro Armour synthetic underlayment on the entire roof surface, except in valleys where specialty underlayment complying with ASTM D 1970 shall be used.

Shingles:

• Starter shingles: Owen Corning Duration brand starter shingles shall be installed.

• Hip and roof shingles: Owen Corning Duration brand shingles shall be installed on hips and the entire roof surface.

• Fastening: Shingles shall be fastened with a minimum of 6 nails per shingle, installed according to manufacturer specifications and code requirements.

Venting:

• Hip and roof venting shall be installed according to manufacturer specifications.

• Ridge vents shall be installed if deemed necessary by the contractor to meet code requirements or ensure proper ventilation. If installed, ridge vents shall be:

o aluminum or PVC, with exterior cover and end caps o Installed according to manufacturer specifications and code requirements o Filtered or screened to prevent pest entry, if required by code or specifications

Hip and Ridge:

Pro Edge hip and ridge components from Owen Corning Duration brand shall be installed.

Installation:

All roofing components shall be installed according to the manufacturer's specifications, and in compliance with the 2020 New York State Residential Building Code with the noted exceptions.

GENERAL REQUIREMENTS:

1. Bid price is to include all materials, labor, disposal of materials fees and site clean-up.

Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.

2. Work is to be done between the hours of ___ and ___, Monday through Friday.

Contractor is advised that this is an occupied home and may be occupied during these times.

3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each work day.

4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery.

5. Smoking is prohibited by contractors at all residential and program sites owned by

OPWDD.

6. Prior to the commencement of the work, there shall be a meeting with DDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period.

7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property.

8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work.

SITE VISIT

A site visit is mandatory. The site visit date is scheduled for Thursday, November 12th at 10 a.m.

at the project site. All prospective bidders are encouraged to attend.

A. Lawn Damage/Property Damage

• If the delivery of materials or any other work necessitates the contractor, his suppliers, or sub-contractors to drive on the lawn for ANY reason, the contractor shall be held responsible for the repair of the lawn.

• Personal vehicles are not to be parked on the grass.

• Any property damage caused by work performed is to be corrected to the condition existing prior to start of the job.

B. Continuity of Work/Communication/Scheduling

• Once the job has begun, it is to be worked on continuously until completed.

• If there are any delays, even if due to inclement weather, a Work Control Representative

MUST be contacted.

• Work must be completed within ___ days of receiving the purchase order.

C. House Safety

• The residence will be occupied during the job.

• The contractor must take all reasonable care to safeguard the residents and the staff.

• The contractor shall ensure all tools, materials and other items are picked up, removed or stored and are safely secured at the end of each workday.

• Any ladders, scaffolding or lifts used in conjunction with this job are to be stored to the satisfaction of the House Director at the end of the day.

• The work as indicated above shall be scheduled as not to interfered with other functions of the residence. All work performed as part of this job is to be coordinated with the House

Director and project manager above.