Scope of Work for Aeration Blower Removal.pdf
PDF 136 KB Posted
- Attached to
- 406924 Aeration Blower Rebuild - ATP (Rebid)
- Solicitation number
- 57599
- Issued by
- Virginia Beach City, Virginia
About this file
The provided document is a Scope of Work for the Aeration Blower Removal, Rebuild, and Installation project, associated with the state and local contract opportunity "406924 Aeration Blower Rebuild - ATP (Rebid)" in Virginia. The supplier shall provide all materials and labor to remove, rebuild, and reinstall the Gardner Denver 2400 Multistage Centrifugal Blower Model 2405. The scope includes removing the blower from the plant site, transporting it to a repair shop, rebuilding the blower with new components, and then reinstalling the unit back at the plant site. The blower has a load weight of 19,000 lbs and dimensions of 8'8" x 6'8" x 7'x1".
The related state and local contract opportunity is being solicited by the Hampton Roads Sanitation District (HRSD) and is limited to the jurisdictions of Virginia Beach City in Virginia. Interested parties must submit their responses through the HRSD's online Oracle ERP system, and not through the Virginia eVA system. Detailed information about the solicitation, including specifications, is available through the HRSD's online Oracle ERP system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Getting Started in ERP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work for Aera on Blower Removal, Rebuild, & Installa on
The supplier shall provide all materials, labor, to remove, rebuild, and install the Gardner Denver 2400 Mul stage Centrifugal Blower Model
2405.
Removal
Remove of blower from plant site to include uncouple of Blower, unbol ng at inlet/discharge, unbol ng at Blower base/cas ng feet.
Dimensions and Load Weight:
Load Weight: 19,000 lbs
Dimensions: 8’8” x 6’8” x 7’x1”
Load unit for freight transport to repair shop.
Transport to repair shop.
Rebuild
The blower Rebuild shall include new sha , bearing housings, select fit bearings, seals, shims, locknuts, gaskets, and miscellaneous hardware.
The unit shall be thoroughly cleaned inside and out.
Reinstalla on
Transporta on of unit back to plant site from the repair shop.
Removal of unit from freight transport
Reinstall the blower Test the blower
File details come from the government source that posted it. Updated .