SCOPE_OF_WORK.pdf

PDF 147 KB Posted

Attached to
HALLEN SCHOOL STEAM BOILER REPLACEMENT
Solicitation number
BMB008279
Issued by
Fairfield County, Bridgeport City, Connecticut

About this file

This Scope of Work document supports the City of Bridgeport, Connecticut's request for bids on the Hallen School Steam Boiler Replacement project. The project involves the replacement of the steam boiler system at Hallen School. Electronic bid submissions are being accepted through the City's e-Procurement Portal (OpenGov) at https://procurement.opengov.com/portal/bridgeportct, with a submission deadline of 2:00 pm on Tuesday, September 1, 2026. Bids will be publicly opened at that time at the Department of Public Purchases, 2nd floor, 999 Broad Street, Bridgeport, CT 06604. Prospective bidders must create a free OpenGov account to submit responses. The deadline for submitting written questions regarding the bid is 2:00 pm on Monday, August 24, 2026, and all questions should be posted through the OpenGov Procurement website question section. Bidders are instructed to monitor the procurement portal regularly for any issued addendums.

The document does not provide specific details regarding pricing terms, contract duration, renewal options, funding sources, or award timeline. Bidders should refer to the complete solicitation documents and any addendums posted on the OpenGov portal for comprehensive information about project specifications, technical requirements, insurance and bonding requirements, and other contractual terms and conditions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hallen School Steam Boiler Replacement

General Scope of Work:

One HB Smith 44 Mills boiler is to be removed, room abated and tested by others lnstall and pipe new HB Smith 28HE-10 Steam Boiler lnstall new Power Flame c G burner full modulation lnstallation of new jacket lnstallation of new boiler feed (inclusive of all wiring), operating and safety controls lnspect and test breeching and chimney

Rewire boiler and burner per Bridgeport Board of Education design

Upgrade all electric as necessary to meet code compliance

Re-pipe natural gas lnstall Distech DDC controls for complete boiler room per Bridgeport Board of Education standards

(included with package)

Will be added to VM platform lnsulate all new piping

Permits are the responsibility of the contractor

Contractor is responsible for start-up and testing

Turnover will not take place until accepted by the Board of Education