The document is a Scope of Work for a Bathroom Renovation project at the LaRue IRA facility located at 105 Charles St, Wayland, NY 14572. The work is being solicited by the Finger Lakes DDSO and includes furnishing all materials and labor to complete the renovation per the provided architectural drawings. A mandatory site visit is scheduled for February 22, 2024 at 11:00 am. Bids will not be accepted from vendors that do not attend this site visit. The project is a NYS public works project, and prevailing wages must be paid. The work must be completed within 90 days of receiving the purchase order.
The Scope of Work details several general requirements, including that the bid price is to include all materials, drywall, labor, disposal fees, and site clean-up. The work is to be conducted Monday through Friday during specified hours, and the contractor must ensure tools, materials, and debris are secured at the end of each workday. The contractor will also be required to coordinate with the FLDDSO Operations and Maintenance staff and provide safety data sheets prior to the start of work. This project is not designated as a Service-Disabled Veteran-Owned Set Aside. The due date for bids is March 1, 2024 at 8:00 PM.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Request for Quote.pdf | ||
| Design.pdf | ||
| Permit.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SCOPE
DESCRIPTION:
The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to scope of work and architectural drawings if supplied. Work is to be completed within 90 days of award and P.O is issued. This is a NYS Public Works project and prevailing wages are to be paid. Refer to attached specification for the following scope of work. Site must be cleaned, and all materials secured at the end of each workday. Absolutely no scraps, especially fasteners, are to be left unsecured. Upon completion of Bathroom Renovation, before removal of equipment, contractor is to schedule a quality control and quality assurance inspection with Point of Contact listed above.
SCOPE OF WORK includes, but is not necessarily limited to the following:
1. Furnish all materials and labor to complete the Bathroom Renovation per
Architectural/Engineered Blueprints from: Zaxis Architectural, Dated: 12/29/23.
GENERAL REQUIREMENTS:
1. Bid price is to include all materials, drywall, labor, disposal of materials fees and site clean-up. Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.
2. Work is to be done between the hours of TBD, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times.
3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each workday.
4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery.
5. Smoking is prohibited by contractors at all residential and program sites owned by
OPWDD.
6. Prior to the commencement of the work, there shall be a meeting with FLDDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period.
7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property.
8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work.
Facility:
LaRue IRA 263-FLA-2312
Facility Address:
105 Charles St, Wayland, NY 14572
Point of Contact:
Jim Colon MS2
Contact Phone Number:
585-335-4119
Project Title:
Bathroom Renovation SCOPE: JC0088
Summary of Work:
Renovation of Bathroom for LaRue IRA
SITE VISIT
A site visit is mandatory. The site visit date is scheduled for Thursday, February 22, 2024 @ 11:00am at the project site. All prospective bidders are encouraged to attend.
A. Lawn Damage/Property Damage
• If the delivery of materials or any other work necessitates the contractor, his suppliers, or sub-contractors to drive on the lawn for ANY reason, the contractor shall be held responsible for the repair of the lawn.
• Personal vehicles are not to be parked on the grass.
• Any property damage caused by work performed is to be corrected to the condition existing prior to start of the job.
B. Continuity of Work/Communication/Scheduling
• Once the job has begun, it is to be worked on continuously until completed.
• If there are any delays, even if due to inclement weather, a Work Control Representative
MUST be contacted.
• Work must be completed within 90 days of receiving the purchase order.
C. House Safety
• The residence will be occupied during the job.
• The contractor must take all reasonable care to safeguard the residents and the staff.
• The contractor shall ensure all tools, materials and other items are picked up, removed or stored and are safely secured at the end of each workday.
• Any ladders, scaffolding or lifts used in conjunction with this job are to be stored to the satisfaction of the House Director at the end of the day.
• The work as indicated above shall be scheduled as not to interfered with other functions of the residence. All work performed as part of this job is to be coordinated with the House Director and Plant Superintendent listed above.
| SCOPE OF WORK includes, but is not necessarily limited to the following: |
| 1. Furnish all materials and labor to complete the Bathroom Renovation per Architectural/Engineered Blueprints from: Zaxis Architectural, Dated: 12/29/23. |
| 1. Bid price is to include all materials, drywall, labor, disposal of materials fees and site clean-up. Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor. |
| 2. Work is to be done between the hours of TBD, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times. |
| 3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each workday. |
| 4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery. |
| 5. Smoking is prohibited by contractors at all residential and program sites owned by OPWDD. |
| 6. Prior to the commencement of the work, there shall be a meeting with FLDDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period. |
| 7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property. |
| 8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work. |
SITE VISIT
File details come from the government source that posted it. Updated .