Scope of Work.pdf

PDF 134 KB Posted

Attached to
Cohocton IRA - Generator Installation
Solicitation number
01170DE0-035D-4629-BDCF-1AC7A500E22D
Issued by
Steuben County, New York

About this file

The document is a Scope of Work for a NYS Public Works project to replace a generator and transfer switch at a residential facility owned by the Finger Lakes Developmental Disabilities Services Office (FLDDSO) in Cohocton, New York. The scope includes furnishing all labor and materials to completely install a replacement generator and transfer switch system, adhering to all applicable codes and regulations, and testing/tuning the equipment for optimal performance. The work must be completed within 60 days of the purchase order award. A mandatory site visit is scheduled for March 12, 2024 at 10:00 AM, and bids will only be accepted from vendors who attend this site visit. The project is not designated as a Service-Disabled Veteran-Owned Set Aside. The bid due date is March 20, 2024 at 8:00 PM, and the contract term is 30 days after completion of the project. The project is located in Steuben County, New York.

The bid price must include all materials, labor, disposal fees, and site clean-up. The contractor will be responsible for ensuring the safety and security of the occupied residence during the work period. Safety data sheets and environmental testing results will be provided to the contractor prior to the start of work. Smoking is prohibited, and the contractor must coordinate all work activities with the FLDDSO Operations and Maintenance staff.

View the file

Other files

File Type Posted
Request for Quote.pdf PDF
Permit.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SCOPE

DESCRIPTION:

Direct Replacement Installation of Generator and Transfer Switch at Residence. The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to scope of work. Work is to be completed within 60 days of award, unless modified below. This is a NYS Public Works project and prevailing wages are to be paid. Refer to attached specification for the following scope of work. Site must be cleaned, and all materials secured at the end of each workday. Absolutely no scraps, especially fasteners, are to be left unsecured. Upon completion of Generator Installation, before removal of equipment and scaffolding, contractor is to schedule a quality control and quality assurance inspection with Plant Superintendent.

SCOPE OF WORK includes, but is not necessarily limited to the following:

1. Furnish materials and labor to Completely Install Replacement Generator and Transfer Switch

System as per SCOPE (KOHLER 38RCLC-QS2 - 38 KW 1-PHASE Generator and KOHLER RXT, 400A, 240V, SERVENTR, Transfer Switch)

2. No splicing of service conductors is allowed in the system. Lug to lug connections are strictly enforced. circuits on the Generator / Transfer switch are to remain the same.

3. All work to be done per New York State, Federal Regulations, and 2014 NEC code.

4. Test and tune equipment for optimal performance. Submit startup documentation for warranty verification.

5. No payment will be processed until all necessary documentation and inspections are satisfactorily on file.

6. Work to be completed and invoiced within 60 days of receipt of P.O.

GENERAL REQUIREMENTS:

1. Bid price is to include all materials, labor, disposal of materials fees and site clean-up.

Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.

2. Work is to be done between the hours of TBD, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times.

3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each workday.

4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery.

Facility:

Cohocton IRA

Facility Address:

37 S Main St, Cohocton, NY 14826

Point of Contact:

Jim Colon – Maintenance Supervisor II

Contact Phone Number:

585-335-4119

Project Title:

Generator & Transfer Switch Installation Spec# JC0079

Summary of Work:

Install Direct Replacement Generator, and Transfer Switch for residence.

5. Smoking is prohibited by contractors at all residential and program sites owned by

OPWDD.

6. Prior to the commencement of the work, there shall be a meeting with FLDDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period.

7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property.

8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work.

SITE VISIT

A site visit is mandatory. The site visit date is scheduled for Tuesday, March 12, 2024 @ 10:00am at the project site. All prospective bidders are encouraged to attend.

A. Lawn Damage/Property Damage

• If the delivery of materials or any other work necessitates the contractor, his suppliers, or sub-contractors to drive on the lawn for ANY reason, the contractor shall be held responsible for the repair of the lawn.

• Personal vehicles are not to be parked on the grass.

• Any property damage caused by work performed is to be corrected to the condition existing prior to start of the job.

B. Continuity of Work/Communication/Scheduling

• Once the job has begun, it is to be worked on continuously until completed.

• If there are any delays, even if due to inclement weather, a Work Control Representative

MUST be contacted.

• Work must be completed within 60 days of receiving the purchase order.

C. House Safety

• The residence will be occupied during the job.

• The contractor must take all reasonable care to safeguard the residents and the staff.

• The contractor shall ensure all tools, materials and other items are picked up, removed or stored and are safely secured at the end of each workday.

• Any ladders, scaffolding or lifts used in conjunction with this job are to be stored to the satisfaction of the House Director at the end of the day.

• The work as indicated above shall be scheduled as not to interfered with other functions of the residence. All work performed as part of this job is to be coordinated with the House Director and Plant Superintendent listed above.

SCOPE OF WORK includes, but is not necessarily limited to the following:
1. Bid price is to include all materials, labor, disposal of materials fees and site clean-up. Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.
2. Work is to be done between the hours of TBD, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times.
3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each workday.
4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery.
5. Smoking is prohibited by contractors at all residential and program sites owned by OPWDD.
6. Prior to the commencement of the work, there shall be a meeting with FLDDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period.
7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property.
8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work.