This is a Scope of Work document prepared by the City of Atlanta Department of Transportation for pedestrian mobility improvements along Cleveland Avenue in Georgia. The project encompasses 1.42 miles of roadway and includes installation of pedestrian signal upgrades, ADA-compliant ramps, pedestrian hybrid beacons (PHBs), rectangular rapid flashing beacons (RRFBs), pedestrian refuge islands, new and replacement crosswalks, speed detection and notification signs, minor intersection geometry modifications, new sidewalks, and landscaping. The project spans seven identified locations: Dearwood Drive, 3rd Avenue, Forrest Hills Drive, Steele Avenue, 47 Cleveland Avenue SW (Cleveland Avenue Branch Library mid-block crossing), Lois Lane, and Altaview Drive. All work must comply with Georgia Department of Transportation (GDOT) standards and specifications, current edition, and City of Atlanta Department of Public Works details. The contractor is responsible for demolition and removal of existing infrastructure not retained per construction plans, tree protection and removal per approved tree protection plans, installation and maintenance of erosion control measures throughout construction, and maintenance of driveway and mailbox access. Work must be performed within existing or proposed right-of-way and easements as detailed in Right of Way plans.
The contractor shall complete work according to milestones established in Exhibit A.3 of the Agreement, with liquidated damages of $500 per calendar day assessed for each day Substantial Completion is delayed beyond the established deadline without prior written City approval. Unit and lump sum prices quoted in the Schedule of Unit and Lump Sum Prices are firm, all-inclusive prices covering all costs incurred by the contractor. Quantities listed are approximations subject to variations, with payment made for actual quantities incorporated into the work based on established unit prices. All prices are fixed for the contract duration with no escalation permitted. Within fifteen days of contract award or before site mobilization (whichever is earlier), the contractor must submit a contract schedule and materials submittals, with ongoing submissions including schedule updates and sidewalk and lane closure applications submitted two weeks prior to closure commencement. A mandatory preconstruction conference will be held with the lowest responsive, responsible bidder, the City, contractor, and selected DBE firms. Off-duty police officers are required at all signalized intersections, and debris cleanup from patching, milling, or resurfacing must be completed within seven working days of notification or costs will be deducted from contractor payment.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
For
CLEVELAND AVENUE PEDESTRIAN MOBILITY IMPROVEMENTS
SCOPE OF WORK
1.0 SCOPE OF WORK
The scope of work for this project consists of roadway and pedestrian improvements along Cleveland Avenue.
The length of the project is 1.42 miles. All improvements shall be constructed according to the construction plans for each location and by all GDOT standards and specifications.
The purpose of the Cleveland Avenue Pedestrian Mobility Improvement project is to install pedestrian signal upgrades, ADA-compliant ramps, new pedestrian hybrid beacons (PHBs) and rectangular rapid flashing beacons (RRFBs) at unsignalized intersections and mid-block crossings, pedestrian refuge islands, include new and/or replace crosswalks, speed detection and notification signs, minor intersection geometry changes to enhance pedestrian crossings, new sidewalks, and new landscaping.
Locations:
Location#1 Dearwood Drive
Location#2- 3rd Avenue
Location#3- Forrest Hills Drive
Location#4 Steele Avenue
Location#5 47 Cleveland Avenue SW
Cleveland Avenue Branch Library Mid-block Crossing
Location#6 Lois Lane
Location#7 Altaview Drive
Notes
1) Erosion control measures will be installed at the beginning of the construction and maintained throughout construction.
2) see construction drawings for additional information.
Contractor shall perform the Services for the purpose of providing enhancements to Cleveland Avenue as more particularly described in the scope of work and accepted proposal from Contractor attached incorporated herein, including the attached schedule of unit prices for performing the required services.
Coordination will be required with utility companies to adjust facilities to final grade and with the facilities that conflict with ramp locations.
The contractor is responsible for the demolition and removal of existing infrastructure that is not to be retained per the construction plans. Tree protection and tree removal shall be according to the tree protection plan. Contractor shall install and maintain temporary and permanent erosion control per the construction plans through the duration of construction. Access to driveways and mailboxes shall be maintained. The contractor shall perform work inside existing or proposed right of way and easements as detailed in the Right of Way plans.
2.0 MILESTONES AND LIQUIDATED DAMAGES
Contractor shall complete the Work in accordance with the milestones set forth in Exhibit A.3 of the Agreement. Time is of the essence under this Agreement. The Failure to meet any milestone or substantial completion deadline, without prior written approval from the City, may subject Contractor to liquidated damages.
Liquidated damages in the amount of $500.00 per calendar day shall apply for reach calendar day that Substantial Completion is delayed beyond the date established in Exhibit A.3, unless otherwise approved in writing by the City.
3.0 UNIT & LUMP SUM PRICES
Unit and Lump Sum prices quoted in the Schedule of Unit & Lump Sum Prices shall be firm all-inclusive prices. Payment of the Unit and/or Lump Sum prices shall constitute full payment for performance of the corresponding work and shall cover all costs of whatever nature incurred by the Contractor in accomplishing the Work by the provisions of this Contract.
4.0 QUANTITIES
The quantities noted in the Schedule of Unit & Lump Sum Prices, are approximations subject to variations as stated in 5.0 and no claim shall be made for deficiency or over-run, actual or relative.
Payment will be made for the actual quantities of each Schedule of Unit Prices item incorporated into the Work in accordance with the Contract requirements based on the unit prices established in the Schedule.
5.0 PERFORMANCE AND PAYMENT SECURITIES
The cost of the Performance and Payment Bonds is to be distributed through the various items of work.
6.0 DEPARTMENT SUBMITTALS
Within fifteen (15) days of Contract award but before site mobilization, whichever is earlier, the following documents shall be submitted:
1. Contract Schedule.
2. Materials Submittals
Throughout the life of the project, the following documents shall be submitted:
1. Schedule updates.
2. Applications for sidewalk and lane closures 2 weeks prior to commencement of any closure, follow “City of Atlanta, Department of Public Works, City’s Public Right-of-Way Manual” for additional requirements.
3. All permit fees and responsibilities can be found here https://app.apply4.com/worksapp/usa/atlanta
6.0 Georgia Department of Transportation (GDOT) Standard Specifications
Unless otherwise directed, all work performed under this contract shall be in accordance with the Georgia Department of Transportation (GDOT) Standard Specifications, Construction of Transportation Systems, Current Edition, and applicable Georgia Department of Transportation and any Supplemental Specifications and Special Provisions modifying them. Work must also conform with any City of Atlanta Department of Public Works Details and Specifications. All documents are incorporated herein by reference as if fully set forth. On all CIP Projects, the City provide testing, Unless it is set up in the Schedule of Values.
All references to GDOT Standard Specifications and Special Provisions can be found at http://mydocs.dot.ga.gov/info/gdotpubs/ConstructionStandardsAndDetails/Forms/AllItems.aspx
7.0 MODIFICATIONS
The Following Modifications to the Contract take precedence in the following order:
Change Orders Addenda Bid Form Special Conditions Special Provisions City – Contractor Agreement Modification of Standard Specifications Specifications Plans General Conditions
All prices are fixed for the duration of this Agreement and are not subject to escalation for any cause.
Payment of the Total Contract Price shall constitute full payment for performance of the Work and covers all costs of whatever nature incurred by Contractor in accomplishing the Work in accordance with the provisions of the Agreement.
The City reserves and shall have the right to make such adjustments in the Work as may be necessary or desirable to complete the Work originally intended in an acceptable manner. Unless otherwise specified herein, the City may make such adjustments in the Work which may increase or decrease the originally awarded quantities. S u c h Adjustments shall not invalidate the Agreement nor release the Surety, and the Contractor agrees to accept payment for such adjustments as if the altered Work had been a part of the original Agreement.
Adjustments that are within the General Scope of Work shall be covered by Change Order issued by the Eng ineer . Change Orders for altered Work shall include extensions of Contract time where, in the Engineer’s opinion, such extensions are commensurate with the amount and difficulty of added Work.
If the City and the Contractor are unable to agree on a unit price adjustment for any item that requires a Change Order, the City reserves the right to procure the item s e p a r a t e l y and/or make other arrangements for its completion.
All Change Orders shall require consent of the Contractor’s Surety and an increase of the Performance and Payment Bonds, if applicable. Adjustments shall not increase the total cost of the Project, based on the originally estimated quantities and the unit prices bid. Should it become necessary for the best interest of the City to make changes in excess of those herein specified, the same shall be covered by Change Order.
MODIFICATIONS OF STANDARD SPECIFICATIONS
See Attachment named ATLDOT Supplemental General Conditions to GDOT Standards.
8.0 MISCELLANEOUS MODIFICATIONS AND CLARIFICATIONS
1. Contractor is responsible for scheduling his own work; however, from time to time, the City reserves the right to add, delete, delay, or expedite any street at no additional compensation to the Contractor.
2. Milling items to include unforeseen concrete areas. No additional compensation will be paid.
Milling is variable depth.
3. Pay Requests – Quantities will be reviewed with the inspector by the last day of each month. The draft pay request should be submitted for review by the 5th of the following month. After receiving approval of the draft invoice, the official signed, and sealed pay application should be submitted to Renew Atlanta Finance.
4. Mailboxes and access to driveways must be maintained.
5. Heavy equipment operating in the right-of-way must yield to all traffic and define their work area with approved channeling devices.
6. Off duty Police Officers are required at all signalized intersections.
7. All signs that are temporarily removed must be put back in place before the end of the day.
8. Proposals may be rejected if any of the Unit Prices are obviously unbalanced. The city will decide whether any Unit Prices are unbalanced either excessively above or below a reasonable cost analysis value determined by the Engineer, particularly if these unbalanced amounts are substantial and contrary to the interest on the city. The low bid will be determined based on the sum of the base bid and any alternates selected by the city.
9. Temporary Pavement Markings – All temporary pavement markings shall conform with MUTCD and Special Provision 150. These markings will be covered in the cost for Traffic Control.
10. Debris Clean Up - Once the contractor has been notified to clean up debris associated from patching, milling, resurfacing, or shoulder reconstruction this will be completed within seven (7) working days and approved by the Engineer. If not completed within that time and the city has this done by in house forces or others the cost will be deducted from payment to the contractor. If done by an outside contractor a copy of the invoice will be provided to the resurfacing contractor. If done by in house forces a flat rate of $100 per hour will be accessed.
11. A mandatory preconstruction conference will be held with the lowest response, responsible bidder with, the city, Contractor, selected DBE firms.
12. All testing is to meet the requirements outlined in the GDOT Sampling, Testing, and Inspection Guide.
9.0 ADA RAMPS
The Federal Highway Administration’s (FHWA) Americans with Disabilities Act (ADA) Section 504 provides certain requirements for construction of ADA Ramps, and the removal / repair/ replacement of non-compliant ADA Ramps when certain construction activities are undertaken.
The City of Atlanta will inspect all sidewalks that abut street resurfacing projects and review for compliance existing ADA Ramp and provide for the construction of ADA Ramps where none presently exist. All ADA Ramp construction will comply with the Americans with Disabilities Act Program/Section 504 of the Rehabilitation Act of 1973. All standards are located on the City’s website here:
http://www.atlantaga.gov/index.aspx?page=895
The following typical standards used are as shown below:
s
11.0 Speed Humps
The Contractor will be required to replace speed humps in kind. These will be paid for per linear foot for a 24-foot section as per the City of Atlanta Speed Hump Detail.