SCOPE_-_8207_N_Palafox_St_-_F_Wilson_-_NED.docx
DOCX document 34 KB Posted
- Attached to
- NED Home Rehab - 8207 N Palafox St
- Solicitation number
- NED-S-8207-102425
- Issued by
- Escambia County, Florida
About this file
This document is a Scope of Work for a Housing Repair Project issued by the Escambia County Neighborhood Enterprise Division (NED) in Pensacola, Florida. The project involves rehabilitation of a single-family residence located at 8207 N. Palafox St., owned by Frances Wilson, with a mandatory on-site walk-through scheduled for November 4, 2025, and quotes due by November 12, 2025. The rehabilitation aims to make the home safer, more energy efficient, and more accessible, with a 60-day project completion timeline and potential liquidated damages of $150 per day for delays. The scope includes electrical work, drywall repairs, and optional mechanical system upgrades, with quotes to be submitted through the OpenGov portal.
Funding for the project is through the State Housing Initiatives Partnership (SHIP) Housing Repair Program, with no federal funding involved. The contract will be awarded to the lowest, most responsive, and most responsible bidder, with payment structured as a lump sum for projects under $15,000 and a phased payment schedule for larger projects. Contractors must meet specific requirements, including current licensing, insurance, and certifications, with a 100% Performance and Payment Bond required for projects valued at $25,000 or higher. The project emphasizes compliance with state and local building codes, with a focus on improving the home's safety, energy efficiency, and accessibility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NED_Home_Rehab_-_8207_N_Palafox_St.pdf | ||
| Bid_Scope_Materials_List.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ESCAMBIA COUNTY NEIGHBORHOOD ENTERPRISE DIVISION
SHIP Housing Repair – SCOPE OF WORK
| OWNER: |
| Frances Wilson |
| JOB NUMBER: |
| NED-S-8207-102425 |
| ADDRESS: |
| 8207 N. Palafox St. |
| DATE PREPARED: |
| 10-24-2025 |
Pensacola, FL 32534
| WALK DATE: |
| 11-04-2025 10:00 am |
| PHONE: |
| 850.476.3333 |
| QUOTES DUE: |
| 11-12-2025 1:00 pm |
| QUOTE REVIEW: |
| 11-13-2025 11:30 am |
I/(we) certify that I/(we) have carefully examined the Housing Repair Specifications and Contractor Requirements related to the above referenced job, as furnished by Escambia County, and I/(we) have also examined the site on which the proposed work is to be performed. Based on these examinations, I propose to furnish all materials, tools, machinery and labor necessary to complete the work in a professional, workmanship manner and to complete the work at the prices listed.
TOTAL JOB COST
CONTRACTOR’S SIGNATURE
TITLE
QUOTE REVIEW:
FIRM
| |_| ACCEPTED |
| |_| REJECTED |
FIRM PHONE NUMBER
QUOTE REPRESENTATIVE
Escambia County Building Code
REQUIRED PERMITS AND INSPECTIONS:
By signing this document, you are certifying that your firm is not currently suspended, debarred, or in any way disqualified from participating in any state or federal funded housing rehabilitation programs.
All measurements are for reference only and should be confirmed by the bidder.
Mandatory ON-SITE walk-through: November 4, 2025, at 10AM
INSTRUCTIONS TO BIDDERS
Complete and submit the cover sheet and all numbered pages on this Scope of Work with a signature of the contractor, the total cost, and the completed itemized pricing table. Quote submissions will only be accepted online, via the OpenGov portal. Hand delivered email or fax submissions will NOT be accepted. All quotes must be received by the published “Quotes Due” deadline.
The quotes will be opened by a quote committee and awarded to the lowest, most responsive, and most responsible quoter. The opening of these quotes or the “Quote Review” will be held at 221 Palafox Place, Pensacola, FL 32502 on November 13, 2025, at 1130A. All interested members of the public are invited to attend. Should the total cost of this project exceed the funds available, then a removal of one or more of the pricing tables line items may be deleted in order to maintain the program’s budgetary restrictions.
CONTRACTOR’S RESPONSIBILITIES AND OBLIGATIONS
All repair work performed must be inspected, rough-ins and finals, and conform to state laws, and the Escambia County building codes and ordinances. The contractor is responsible for proper reattachment/hook-up of any/all of the following that apply, appliances, existing coaxial cable, telephone and interface, electric, water, and sewage. The contractor will only assist in moving the larger furniture and the contractor is not responsible for the removal of the homeowner’s trash, discarded belongings or furnishings. Labor, overhead, permits, insurance, and profit must be included into each itemized price and not listed as a separate itemized price or listed under “miscellaneous.” Non-compliance will result in rejection of bid. Review the “Bid Scope Materials List” for product lines and or their equivalents.
HOMEOWNER’S RESPONSIBILITIES AND OBLIGATIONS
The homeowner is responsible for maintaining existing utilities for the Contractor’s use during the rehabilitation period and for the removal of all belongings of furnishings from the designated work areas prior to the start date. The homeowner is also to be given options when selecting colors and styles of the products being replaced.
PAYMENT SCHEDULE
The payment will be lump sum payment at the project completion for bids and under $15,000. For bids over $15,000, the contractor will be eligible for a 40% draw once the NED confirms that 50% of the work has been completed as determined by line-item costs. Within 20 business days after the initial draw the contractor will be eligible for a substantial completion draw which is to be 150% less of any line-item costs that are not complete. The contractor will be eligible for final payment after the following conditions have been fulfilled:
*Completion of the Scope of Work
| *Inspection/Sign-off by Building Inspections and/or Health Department |
| *Acceptance by the Homeowner (Homeowner’s Release & Warranty) |
| *Contractor’s Final Affidavit |
| *Warranty Paper provided to the Homeowner |
| *Premises free from all construction debris |
| *Submission of RRP Checklist Form |
| *Original Invoice from Contractor |
*Surety’s Consent to Final Payment (if applicable)
COMPLETION DATE
There is a 60-day time limit on this rehabilitation project. For every day worked more than the contract period, liquidated damages of ONE HUNDRED and FIFTY DOLLAR ($150.00) per day will be assessed. During this timeline the homeowner is not to begin any new rehabilitation projects.
ESCAMBIA COUNTY NEIGHBORHOOD ENTERPRISE DIVISION
HOUSING REPAIR PROGRAMS
CONTRACTOR REQUIREMENTS
If your firm is awarded the bid for housing repair (SHIP or HUD programs), the following items must be current and on file to issue a Purchase Order.
| *Current W9 and Sunbiz registration (less than one year old). |
| *County Vendor Information sheet (less than one year old). |
| *Worker’s Compensation as required by State Law OR exemption form. |
| *Commercial General Liability, Automobile Liability and Pollution Liability at |
($1,000,000 coverage) listing Escambia County as a certificate holder and additional insured.
*Commercial General Liability, Automobile Liability and Pollution Liability certificates must state the following under additional Interest:
Escambia County C/O Neighborhood Enterprise Division 221 Palafox Place Suite 304 Pensacola, FL 32502-5844
All correspondence should be directed to the Neighborhood Enterprise Division, 221 Palafox Place, Suite 304, Pensacola, FL 32502 for review.
*For jobs valued at $25,000 or higher, a 100% Performance and Payment Bonds will be needed prior to the Notice to Proceed date. If the Bond is not filed within 10 days after the contract is signed, then a letter of insurability will be required. A Consent of Surety will be required before final payment. The contractor will be responsible for the recording of all bonds with Pam Childers, Clerk of The Circuit Court of Escambia County Florida.
Refer to BCC Office of Purchasing Risk Management Guidelines Procedure No: PP-180 (Performance and Payment Bonds) and PP-185 (Risk Management Guidelines) for further details. [http://www.myescambia.com/business/purchasing-policies-and-procedures]
Additionally, the Neighborhood Enterprise Division will maintain the following info in the contractor’s file:
*www.sam.gov Contractor may not be federally debarred and participate in this program
| *State registered or State Certified Contractor License |
| *Escambia County Competency Board License |
| *Escambia County Business/Occupational License |
| *EPA RRP Renovator and Firm Certifications |
Firms quoting Lead Based Paint Abatement jobs must also submit proof of Lead Abatement firm certification.
All information must be current at the time of the award. IF INFORMATION CANNOT BE PRODUCED IN A TIMELY MANNER, THE COUNTY RESERVES THE RIGHT TO AWARD THE BID TO THE NEXT MOST RESPONSIVE BIDDER.
SHIP Housing Repair Program Specifications PAGE 1
Frances Wilson
8207 N. Palafox St.
Pensacola, FL 32534
850.476.3333
SCOPE OF WORK
The rehabilitation of this owner-occupied, single-family, residence is to make the home safer, more energy efficient, and easier to access within the provisions of federal, state, and county laws and ordinances and the SHIP repair program. The rehabilitation of this home will include the following tasks as outlined below and the repaired areas are to match as close as possible to their existing surroundings. If additional tasks beyond those included in this scope are discovered, then additional funds may be allocated. Before any additional work is performed, written county approval will be needed. There is no federal funding for this project.
1.ELECTRICAL:
Re-wire as needed or required to conform to the national electrical code as per the Escambia County Building Code. This may require additional switches and outlets to be added if the existing space does not meet code requirements. A new meter base/power pack and riser may be required. A new breaker panel may also be required. Install disconnects at equipment and appliances. All smoke detectors should be hardwired with battery back-up. All receptacles, switches and cover plates shall be new devices. All existing and new appliances will have new pigtails installed to match new receptacles. All fixtures shall be LED or have led light bulbs installed. Repair drywall damage from rewiring and paint to match as close as possible. Blocking for ceiling fans will be required and a separate switch is required to operate the fan and light kit at all locations where the fans are installed. Install a new doorbell at entry.
Electrical total $_______________
2.DRYWALL:
Repair all drywall and ceiling surfaces that are damaged or incomplete. Repaired areas are to match as close as possible to existing surrounding areas.
Drywall Repairs total $______________
OPTIOINAL - SCOPE & PRICING TABLE
3.MECHANICAL:
Install a new matching HVAC system, to include the condenser and handler as per the Escambia County Building Code. Repair/Replace the existing ductwork as needed. Repair/Replace the return air grill/registers. It is to be a removable filter with a new filter installed. This unit must meet state energy efficiency rating guidelines. Install a new digital thermostat control. Mechanical Contractor to provide NED with a Manual J to support unit size installed. Correct any issues with the HVAC closet.
Mechanical total $______________
Review the “Bid Scope Materials List” for product lines and or their equivalents.