About this file

This document is a Notice to Bidders for a state and local contract opportunity issued by the North Carolina Department of Natural and Cultural Resources Division of Parks and Recreation. The project involves fire protection improvements at the Sky Lounge in Chimney Rock State Park, located in Rutherford County and Cleveland Town. The work includes removing the existing fire alarm and detection system, providing a new fire alarm and detection system, a new very early warning fire detection system, and a hybrid extinguishing system. Sealed proposals are due by 1:00 pm on April 1, 2024, and will be publicly opened and read. Complete plans and specifications are available for inspection and can be obtained by qualified prime bidders upon a $250 deposit. Bidders must have the proper North Carolina general contractor's license classification for fire protection.

The bid must include the Identification of Minority Business Participation form and either Affidavit A or B. A 5% bid bond or deposit is required. A 100% performance and payment bond will be needed. Payment will be 95% of monthly estimates with final payment upon completion and acceptance. The owner reserves the right to reject any or all bids.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCO-Notice To Bidders 2010 – (Updated Dec. 2010)

N O T I C E TO B I D D E R S

THIRD REBID

Sealed proposals will be received by the North Carolina Department of Natural and Cultural Resources Division of Parks and Recreation in Chimney Rock, NC, in the classroom on the Meadows, Chimney Rock State Park, 831 Chimney Rock Road, Chimney Rock NC 28720 up to 1:00 pm on April 1, 2024 and immediately thereafter publicly opened and read for the furnishing of labor, material and equipment entering into the construction of:

Fire Protection Improvements at the Sky Lounge at Chimney Rock State Park

The Work of Project is defined by the Contract Documents and consists of the following:

1. Removal of the existing fire alarm and detection system.

2. Providing a new fire alarm and detection system.

3. Providing a new very early warning (air sampling) fire detection system.

4. Providing a hybrid extinguishing system including a new room to contain the system cylinders, water supply tank, control panels, etc.

Bids will be received for Contract type – (single prime). All proposals shall be lump sum.

Complete plans, specifications and contract documents will be open for inspection in the offices of GHD Consulting Services Inc. 222 South Church Street Suite 400 Charlotte, NC 28202 and Mark Lyons - Project Manager 121 West Jones Street (3rd floor plan room 3509) Raleigh, NC 27603 and in the plan rooms of the Associated General Contractors, Carolinas Branch, in the local North Carolina offices of McGraw-Hill Dodge Corporation, and in the Eastern Regional Office of Reed Construction Data in Norcross, GA and in Minority Plan Rooms in

NCIMED Plan & Resource Center, 114 West Parrish Street, 6th Floor, Durham, NC 27701, 919-956-8889 or 919-287-3036 or may be obtained by those qualified as prime bidders, upon deposit of 250 dollars ($250.00) in cash or certified check. The full plan deposit will be returned to those bidders provided all documents are returned in good, usable condition within ten (10) days after the bid date.

If a contractor is bidding under the dual system both as a single prime contractor and as a separate prime contractor, he must submit the bids on separate forms and in separate envelopes. Bidders should clearly indicate on the outside of the bid envelope which contract(s) they are bidding.

NOTE: The bidder shall include with the bid proposal the form Identification of Minority Business Participation identifying the minority business participation it will use on the project and shall include either Affidavit A or Affidavit B as applicable. Forms and instructions are included within the Proposal Form in the bid documents. Failure to complete these forms is grounds for rejection of the bid. (GS143-128.2c Effective 1/1/2002.)

All contractors are hereby notified that they must have proper license as required under the state laws governing their respective trades.

General contractors are notified that Chapter 87, Article 1, General Statutes of North Carolina, will be observed in receiving and awarding general contracts. General contractors submitting bids on this project must have license classification for fire protection.

NOTE--SINGLE PRIME CONTRACTS: Under GS 87-1, a contractor that superintends or manages construction of any building, highway, public utility, grading, structure or improvement shall be deemed a “general contractor” and shall be so licensed. Therefore a single prime project that involves other trades will

SCO-Notice To Bidders 2010 (Updated Dec. 2010) require the single prime contractor to hold a proper General Contractors license. EXCEPT: On public buildings being bid single prime, where the total value of the general construction does not exceed 25% of the total construction value, contractors under GS87- Arts 2 and 4 (Plumbing, Mechanical & Electrical) may bid and contract directly with the Owner as the SINGLE PRIME CONTRACTOR and may subcontract to other properly licensed trades. GS87-1.1- Rules .0210

Each proposal shall be accompanied by a cash deposit or a certified check drawn on some bank or trust company, insured by the Federal Deposit Insurance Corporation, of an amount equal to not less than five percent (5%) of the proposal, or in lieu thereof a bidder may offer a bid bond of five percent (5%) of the bid executed by a surety company licensed under the laws of North Carolina to execute the contract in accordance with the bid bond. Said deposit shall be retained by the owner as liquidated damages in event of failure of the successful bidder to execute the contract within ten days after the award or to give satisfactory surety as required by law.

A performance bond and a payment bond will be required for one hundred percent (100%) of the contract price.

Payment will be made based on ninety-five percent (95%) of monthly estimates and final payment made upon completion and acceptance of work.

No bid may be withdrawn after the scheduled closing time for the receipt of bids for a period of 30 days.

The owner reserves the right to reject any or all bids and to waive informalities.

Designer: Owner:

GHD Consulting Services Inc. Mark Lyons – Project Manager 222 South Church Street Suite 400 Design Engineering & Construction Charlotte, NC 28202 North Carolina Department of Natural and

908.221.8033 Cultural Resources

Division of Parks and Recreation 1615 Mail Service Center Raleigh, NC 27699-1615 http://www.nclbgc.org/pages/LawNReg.pdf