Schedule_of_Work_Items_1.docx

DOCX document 32 KB Posted

Attached to
Haulout, inspection, maint, repair of RV KAHO
Solicitation number
140G0122Q0068
Issued by

About this file

This document contains a schedule of work items and pricing for the haulout, inspection, maintenance, and repair of the Research Vessel KAHO owned by the U.S. Geological Survey. Services required include hull cleaning and inspection, underwater hull coating inspection and repair, rudder and shaft seal inspection and replacement, tank cleaning and inspection, various structural upgrades and modifications, and electrical, mechanical, and systems maintenance and replacements. The solicitation will be issued on March 3rd 2022 as Request for Quotes number 140G0122Q0068 with quotations due on March 29th 2022. Anticipated award is a firm fixed price contract to be issued on April 12th 2022 and set aside for small businesses. The work must be performed between mid-May and mid-July 2022 to meet the vessel's science mission timelines. A non-mandatory site visit will be held on March 10th 2022 at the Lake Ontario Biological Station in Oswego, New York, with interested parties confirming attendance by March 8th.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 10, 2014, Rev 3 Schedule of Pricing Maintenance and Repair of Research Vessel KAHO

Spec. Ref. *

WORK ITEM
PRICE
4.1
Hauling, Blocking and Launching
6.01
Hull High Pressure Wash and Visual Inspection
6.02
Hull Appendage Leak Test
6.03
Underwater Hull Coating Inspection
Option
6.04
Repair Underwater Hull Coating
Option
6.05
Repair Deck Coating
7.01
Valve Repair
7.02
Inspect Rudders, Bearings and Seals
7.03
Inspect Propulsion Shafts
Option
7.04
Renew Propulsion Shaft Seals
Option
7.05
Renew Shaft Bearings
7.06
Inspect, Clean, and Refurbish Propellers
7.07
Inspect Bow Thruster
8.01
Open, Clean and Inspect Tanks
8.02
Load Test Lifting Gear
8.03
Install Vibration Dampening Material in Lazarette
8.04
Strengthen Steering Cylinder Mounting
8.05
Reinforce Structure Around Prop Tunnels
8.06
Upgrade Wire Rope on Center Winch
8.07
Replace Trawl Winch Wire Rope
8.08
Resiliently Mount Exhaust
8.09
Modify HVAC System
8.10
Relocate Pilothouse Battery Bank
8.11
Install New Pilot House Door
8.12
Upgrade Weather Instrumentation
8.13
Upgrade Pilothouse Roof Cableways
8.14
Upgrade Navigation Electronics
8.15
Extend Yardarms On Mast
8.16
Install New Air Horn.
8.17
Relocate the Magnetic Compass
8.18
Install Marport net monitoring system
8.19
Upgrade Hydraulic Pipe Hangers
8.20
Replace Hydraulic Tank
8.21
Service Steering Gear Hydraulic Tank
8.22
Upgrade Hydraulic Silencers
8.23
Replace Berths
8.24
Modify Interior Joiner Panels
8.25
Modify Engine Room to Accommodations Bulkhead Lining
8.26
Move Aft Draft Marks
8.27
Modify Auxiliary Cooling Water System
8.28
Repair Deck Plating and Support Structure in Engine Room
8.29
Modify Diesel Fuel Piping
8.30
Clean and Degrease all Bilge Surfaces
8.31
Modify Electrical Switchboard Gauges
8.32
Inspect Wash Down Pump System
8.33
Install Battery Switches on Battery Banks
8.34
Relocate Shore Power Receptacle
8.35
Replace Aft Stack Louvers With Metal Louvers
Option
8.36
Repair Insulation on Exhaust Piping
Option
8.37
Replace Insulation on Exhaust Piping
8.38
Upgrade Fire Suppression System
8.39
Install Noise Treatments in Intake Fan Space
8.40
Install 02 Deck Intake Trunk

TOTAL

LABOR RATES

Shipyard Labor
$/hr
Crane/forklift
$/hr
Material Markup
%
Subcontractor Markup
%

Shipyard Labor: The Contractor’s fully loaded man-hour rate will be used for negotiating change orders, if necessary. The contractor agrees that the number of man hours included in its price proposal for such modifications shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the journeyman level expended in direct production, inspection, repair, or installation as exemplified by the following functions:

Foremen and Shop Supervisors General Labor Rigging Staging/scaffolding Welding Machinists (inside and outside) Fire Watch Burning Brazing Abrasive cleaning/blasting Tank cleaning Carpentry Electrical Work Lagging Ship-fitting Painting Sheet-metal Work Pipefitting Diesel Mechanics Marine Chemist Nondestructive Testing Navigation/Communications Electronics Hydraulic Crane and winch inspection and maintenance Material handling & Warehousing

Project Management & Engineering: Project Management & Engineering support functions shall be considered to be included in the Offeror’s fully loaded rate for direct production man-hours. Examples of support functions include:

Planning Quality Assurance Testing Engineering Design Lofting

G14PS00428
Attachment D Schedule of Pricing

Amendment 0002