Schedule of Values
88 KB Posted
- Attached to
- LAGRANGE BIKE PARK
- Solicitation number
- FY24-003
- Issued by
- Terrell County, Georgia
About this file
This is a Schedule of Values for the LaGrange Bike Park project administered by the City of LaGrange, Georgia. The project encompasses the construction of a bicycle playground and associated trail and roadway infrastructure with work organized into five major sections. Section A includes trail and roadway construction elements such as concrete trail installation (1,400 square yards of 5-inch concrete), grading and demolition, traffic control, mobilization, curb and gutter work, sawed joints, brick pavers, tree protection barriers, pavement markings, wood fencing, and steel bollards. Section B covers structural items including concrete structural slabs, metal post cable railings, and tubular metal handrails designed by structural engineers. Section C addresses erosion control and storm drainage requirements including construction exits, sediment barriers, inlet sediment traps, erosion control inspections for 12 months, water quality monitoring, grassing, and storm drain pipe installation. Section D specifies landscape and park amenities featuring custom metal fabricated structures including an aluminum bike channel, a railroad track structure, and a tunnel structure, with landscape and tree planting noted as city responsibility. Section E includes a 10 percent construction contingency allowance. The document was last updated on August 17, 2023, and indicates that a mandatory pre-bid meeting will be held in-person at City Hall in LaGrange, Georgia.
The Schedule of Values document presents line items with quantities and unit descriptions but does not include completed unit prices or cost figures, as all subtotals and the total project cost are listed as $0.00. Unit costs for individual items were not provided in this bid form proposal. The document notes that certain items including landscape maintenance, benches, trash receptacles, and bike racks are identified as the city's responsibility rather than contractor responsibility. The work encompasses various construction trades and materials including concrete, asphalt, metal fabrication, pavement markings, fencing, and drainage infrastructure, suggesting a comprehensive capital improvement project requiring coordinated specialty work and design professional oversight for structural and architectural elements.
Text of this file
DATE Update 8/17/2023
Item Number Quantity Units Item Description Unit Price Cost
140-1000 1 LS MOBILIZATION
150-1000 1 LS TRAFFIC CONTROL
210-0100 1 LS GRADING COMPLETE (INCLUDING DEMOLITION & TREE REMOVAL)
441-5001 65 LF CONC HEADER CURB, 6IN TP2, (Labor, Form, Finish Only)
402-3910 5 TN
RECY. ASPH. CONC. 12.5MM SUPERPAVE GP2 ONLY, INCL BITUM, MTL, & H LIME, PER PAVEMENT OVER GUTTER DETAIL.
DEPTH VARIES
432-0200 47 SY MILL EXIST. ASPH. SURFACE PER PAVEMENT OVER GUTTER DETAIL. MILL DEPTH VARIES
441-0105 1400 SY CONCRETE TRAIL, 5IN, 3000 PSI, MED BROOM FINISH, INCL ADA RAMPS, BENCH & BIKE PADS (Labor, Form, Finish Only)
441-6012 72 LF CONC. CURB & GUTTER, 6IN X 24IN TP2 (Labor, Form , Finish Only)
444-1000 1400 LF SAWED JOINTS IN CONCRETE TRAIL & SIDEWALK PAVEMENTS @ 10' O.C.
444-1001 160 LF SAWED JOINTS IN CONCRETE TRAIL (SCORED CONC. PAVEMENT)
500-3101 6 CY CLASS A CONC STAIRS INCL. REINF & CONC (10FT WIDE)
500-3102 25 SY CLASS A CONCRETE, SPEED HUMP, PER PLANS, (Labor, Form, Finish Only)
900-0039 200 SF BRICK PAVERS: PINE HALL, MIXED COLOR PER PLANS (CITY APPROVAL), 4IN X 8IN
999-5200 48 SF BRICK PAVERS: PAVESTONE, RED ADA 4IN X 8IN
222-1002 380 SY #57 STONE (CLEAN), 6 IN, (ROOT BRIDGING AREAS)
603-7000 380 SY PLASTIC FILTER FABRIC (ROOT BRIDGING AREAS)
643-8200 600 LF BARRIER TREE FENCE (ORANGE), 4 FT
636-1036 28 SF HIGHWAY SIGNS TP1 MATL., REFL. SHEETING TP1
636-1042 LS THREAD TRAIL SQUARE MATL 0.125 ALUM, DIRECT PRINT & THREAD TRAIL SQUARE POST not in contract- city responsibility
636-2070 56 LF GALV STEEL POSTS TP7
652-0091 18 SF MMA PAVEMENT MARKING, WHITE, YIELD SYMBOL
652-5301 215 LF THERMO SOLID TRAF STRIPE, 8 IN, WHITE (GDOT CROSSWALK)
652-6501 920 LF MMA SKIP TRAF STRIPE, 4 IN, YELLOW (TRAIL CL)
652-6502 144 LF MMA SOLID TRAF STRIPE, 12 IN, WHITE (TRAIL STOP BAR)
652-6503 12 EA MMA PVMNT MARKING 'STOP' WHITE, PER TRAIL DETAIL
653-0110 6 EA MMA ARROW MARKING, TP 1
653-0120 1 EA MMA ARROW MARKING, TP 3
653-0150 1 EA MMA ARROW MARKING, TP 5
653-1804 272 LF MMA SOLID TRAF STRIPE, 8 IN, WHITE (CROSSWALK)
653-1501 20 LF MMA SOLID TRAF STRIPE, 4 IN, WHITE
653-1502 136 LF MMA SOLID TRAF STRIPE, 4 IN, YELLOW
653-1503 38 LF MMA SKIP TRAF STRIPE, 4 IN, WHITE
653-1504 80 LF MMA SOLID STRIPE, 4 IN TO 8 IN, CITY APPROVED COLOR, PER PLANS (SPEED TABLE & RAILROAD CROSSING DETAILS)
643-8400 560 LF 2 PANEL WOOD FENCE (INC. POSTS, RAILS, & ATTACHMENTS)
900-0527 3 EA REMOVABLE STEEL BOLLARDS, INCL ALL ATTACHMENTS
900-0528 EA BENCH
not in contract- city responsibility
900-0529 EA TRASH RECEPTACLE
not in contract- city responsibility
900-0533 EA BIKE RACK
not in contract- city responsibility
Section A Subtotal
Item Number Quantity Units Item Description Unit Price Cost
500-3101 5 CY CONCRETE STRUCTURAL SLAB, (10 FT) INCL. REINFORCING (Designed by Structural Engineer)
515-1000 40 LF METAL POST CABLE RAIL, AT STRUCTURAL SLAB (Designed by Structural Engineer)
516-0001 25 LF TUBULAR METAL POST & HANDRAIL, POWDER COATED BLACK, PER STAIR DETAIL
Section B Subtotal
SECTION C: EROSION CONTROL/STORM DRAINAGE
Item Number Quantity Units Item Description Unit Price Cost
163-0300 1 EA CONSTRUCTION EXIT
163-0301 12 MO EROSION CONTROL INSPECTIONS, WEEKLY AND MONTHLY
163-0402 1 LS TEMPORARY CONC. WASHDOWN
163-0528 740 LF CONSTRUCT AND REMOVE TEMPORARY SEDIMENT BARRIER, TYPE NS
163-0550 2 EA CONSTRUCT AND REMOVE INLET SEDIMENT TRAP, TYPE F
165-0030 740 LF MAINTENANCE OF EROSION CONTROL FENCE
165-0101 1 EA MAINTENANCE OF CONSTRUCTION EXIT
165-0105 2 EA MAINTENANCE OF INLET SEDIMENT TRAP
167-1000 12 MO WATER QUALITY MONITORING AND SAMPLING
700-6910 1 AC PERMANENT GRASSING
700-8000 1 AC FERTILIZER MIX GRADE
SIGNAGE
STRIPING & MARKINGS
SITE FURNISHINGS
$0.00
SECTION B: STRUCTURAL ITEMS
TREE PROTECTION
Bid Form Proposal
City of LaGrange
LaGrange Bicycle Playground
LaGrange THREAD - Kid's Bicycle Playground Bid Form Proposal
SECTION A: TRAIL AND ROADWAY
GENERAL
TRAIL AND ROADWAY CONSTRUCTION
$0.00
EROSION CONTROL
668-2100 1 EA GRATE INLET (6500 GRATE)
550-1180 92 LF STORM DRAIN PIPE, 18 IN, HDPE, H 1-10
603-1300 35 SY GDOT TYPE 3 EQUIVALENT RIVER ROCK (12 IN. THICK)
603-2997 35 SY FILTER BLANKET
Section C Subtotal
SECTION D: LANDSCAPE AND PARK AMENITIES
Item Number Quantity Units Item Description Unit Price Cost
700-9900 LS LANDSCAPE (TREES, PLANTS, + 1 YR MAINT)
not in contract- city responsibility
900-0001 1 LS ALUM. BIKE CHANNEL, INCL ALL MOUNTING & HARDWARE, & DIRECT PRINT GRAPHIC (CITY APPROVED), PER PLANS
900-0002 1 LS
CUSTOM METAL FABRICATED RAILROAD TRACK STRUCTURE, INCL. ALL METAL & WOOD MEMBERS, FASTENERS & ATTACHMENTS, BALLAST & EDGE RESTRAINT, BASIS OF DESIGN PER PLANS (Designed by Architect)
900-0003 1 LS CUSTOM METAL FABRICATED TUNNEL STRUCTURE, BASIS OF DESIGN PER PLANS (Designed by Structural Engineer)
Section D Subtotal
SECTION E: CONTINGENCY
Item Number Quantity Units Item Description Unit Price Cost
999-1000 1 ALLOW CONSTRUCTION CONTINGENCY 10% $0.00 $0.00
Section E Subtotal
LS LUMP SUM
SY SQUARE YARD
CY CUBIC YARD
LF LINEAR FOOT
EA EACH
ALLOW ALLOWANCE
SF SQUARE FOOT
GLF GALLON PER LINEAR FOOT
GAL GALLON
TN TON
AC ACRE
LB POUND
SECTION D SUB TOTAL: LANDSCAPE AND PARK AMENITIES $0.00
TOTAL: $0.00
SECTION B SUBTOTAL: STRUCTURAL ITEMS $0.00
SECTION C SUB TOTAL:EROSION CONTROL/STORM DRAINAGE $0.00
SECTION E: CONTINGENCY $0.00
DRAINAGE
$0.00
SECTION A SUB TOTAL: ROADWAY AND TRAIL $0.00
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1 | — | |
| Addendum 2 | — | |
| SOV-Excel Format | — | |
| Additional Docs for Bid Pac | — | |
| Bid Doc | — | |
| IFB Plans | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .