This document is a Schedule A - Statement of Work for a Request for Proposal (RFP) issued by the Michigan Department of Natural Resources (DNR) for a factory rebuilt or factory overhauled Lycoming IO-540-AB1A5 aircraft engine. The engine is required to replace the current engine on a 2000 Cessna 182S aircraft that is approaching its Time Between Overhaul (TBO) limit. The engine must be delivered to the Roscommon Forest Fire Experiment Station in Roscommon, Michigan. The RFP requires the contractor to provide detailed information on product specifications, warranties, recall procedures, quality assurance programs, delivery timelines, security measures, and other requirements. Responses to the RFP must be submitted, and a virtual meeting will be held within 15 business days of contract award to discuss shipping and return of the core engine.
The RFP specifies that pricing must be firm for the entire length of the contract. It also outlines acceptance and inspection procedures, invoice requirements, and payment methods. Additional requirements include the provision of a Material Safety Data Sheet for any hazardous chemicals, disclosure of mercury content, brominated flame retardants, and per- and polyfluoroalkyl substances (PFAS) in the products. The contract will be awarded as a Purchase Order, and the successful contractor must appoint a dedicated representative to handle State of Michigan accounts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| proposal-instructions.docx | DOCX document | |
| schedule_b_pricing.docx | DOCX document | |
| standard-contract-terms-short-form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement
Michigan.gov/MiProcurement Schedule a – statement of work contract activities Request for Proposal (RFP) No. 240000001379 Factory Remanufactured or Factory Overhauled Aircraft Engine This schedule identifies the anticipated requirements of any Contract resulting from this RFP. The term “Contractor” in this document refers to a bidder responding to this RFP, as well as the Contractor who is awarded the contract. The term “bidder” is used to identify where specific responses to the RFP are required.
The Contractor must respond to each requirement or question and explain how it will fulfill each requirement. Attach any supplemental information and appropriately reference within your response.
IMPORTANT NOTE TO CONTRACTORS/BIDDERS: There are specific requirements for which acceptance must be simply acknowledged through a checkbox(es), and others that require further explanation. Click one checkbox and complete the entries as identified.
BACKGROUND
The DNR flies multiple aircraft across the state to provide fire surveillance and other necessary assignments to further the DNR’s mission. These flights are necessary to help detect and inform of wildland fires. Currently one of the DNR’s planes has an engine that is approaching its Time Between Overhaul dates, and if not replaced, the aircraft will be grounded.
SCOPE
The DNR is soliciting a factory rebuilt aircraft engine to be delivered to Roscommon. This engine will replace the current engine that is approaching the Time Between Overhaul (TBO) set by the manufacturer.
REQUIREMENTS
1. General Requirements
1.1. Product Specifications
The Contractor must provide the following:
Remanufactured or Factory Overhauled Lycoming IO-540-AB1A5 for 2000 Cessna 182S, S/N 18280854. N357ME.
Return: Core engine IO-540-AB1A5, S/N RL-1481-48E, Total Time approximately 2200 hours.
Remanufactured Or Factory Overhauled engine to be shipped to:
Michigan Department of Natural Resources.
Roscommon Forest Fire Experiment Station.
1337 E. Robinson Lake Road.
Roscommon, MI 48653
Bid to include shipping cost and approximate delivery time frame.
Delivery must be between 8:00A and 3:00P Monday-Friday.
Bids on alternate brand or manufacturer lines will not be considered.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
1.2. Warranties
Describe any warranties included in the bid – add additional rows as needed. Explain the process for reporting warranty issues and how the Contractor will handle any repairs or replacements.
The State reserves the right to require additional warranties other than those identified by the Contractor in its response to this RFP.
Bidder must provide detailed information requested below:
Describe any warranties included in the bid (if none, write N/A):
Provide the length of the warranty:
Explain the process for reporting warranty issues:
Explain how any repairs or replacements are made, including timing, etc.:
If the warranty is provided through a third-party or manufacturer, the Contractor must confirm that the manufacturer’s warranty passes through to the State.
Provide the name, address, contact name, phone number and email address of the party responsible for the warranty:
1.3. Recall Requirements and Procedures
The Contractor must describe any recall procedures.
Bidder must provide detailed information as requested in the above requirement(s). If none, enter N/A.
1.4. Quality Assurance Program
Explain your Quality Assurance Program(s).
Bidder must provide detailed information as requested in the above requirement(s):
2. Service Requirements
2.1. Meetings
Virtual meeting must take place within 15 business days after award to discuss shipping and return of core engine.
2.2. Delivery
Delivery will be expected within 120 calendar days upon date of order between the hours of 8:00 a.m. and 3:00 p.m. EST Monday through Friday. Delivery will be made at (See Section 1.1 Product Specifications for delivery location.)
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they comply with the above requirement(s):
3. Staffing
3.1. Contractor Representative
The Contractor must appoint one individual specifically assigned to State of Michigan accounts who will respond to State inquiries regarding the Contract Activities, answer questions related to ordering and delivery, etc. (the “Contractor Representative”).
The Contractor must notify the Contract Administrator at least 7 calendar days before removing or assigning a new Contractor Representative.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
3.2. Customer Service Toll-Free Number
The Contractor must specify its toll-free number for the State to contact the Contractor Representative who must be available for calls during the hours of 8 am to 5 pm EST Monday through Friday, at a minimum. Identify customer service availability for this proposal by hours and days of the week.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
The Bidder must specify its toll-free number for the State to make contact with the Contractor Representative.
Identify customer service availability for this proposal by hours and days of the week.
3.3. Security
The Contractor will be subject the following security procedures:
The Contractor must explain any additional security measures in place to ensure the security of State facilities.
The Contractor’s staff may be required to make deliveries to or enter State facilities. The State may require the Contractor’s personnel to wear State issued identification badges.
The Contractor must: (a) explain how it intends to ensure the security of State facilities, (b) whether it uses uniforms and ID badges, etc., (c) identify the company that will perform background checks, and (d) the scope of the background checks.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they comply with the above requirement(s):
4. Pricing
4.1. Price Term
Pricing is firm for the entire length of the Contract.
5. Ordering
5.1. Authorizing Document
The appropriate authorizing document for the Contract will be a Purchase Order
6. Delivery
6.1. Delivery Programs
The Contractor must explain in detail its delivery programs (e.g., standard delivery and quick-ship), including any limitations such as quantity.
The Contractor must explain the transportation method (e.g., UPS, FedEx, Contractor fleet, or other third-party carrier) it intends on utilizing in delivery of the Contract Activities.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they comply with the above requirement(s):
6.2. Packaging and Palletizing
Packaging must be optimized to permit the lowest freight rate. Shipments must be palletized whenever possible using manufacturer's standard 4-way shipping pallets.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
Bidder must describe how they comply with the above requirement(s):
7. Acceptance
7.1. Acceptance, Inspection and Testing
Contract Activities are subject to inspection and testing by the State within 30 calendar days of the State’s receipt of them (“State Review Period”), unless otherwise provided in a Statement of Work. If the Contract Activities are not fully accepted by the State, the State will notify Contractor by the end of the State Review Period that either: (a) the Contract Activities are accepted but noted deficiencies must be corrected; or (b) the Contract Activities are rejected. If the State finds material deficiencies, it may: (i) reject the Contract Activities without performing any further inspections; (ii) demand performance at no additional cost; or (iii) terminate this Contract in accordance with Section 24, Termination for Cause.
Within 10 business days from the date of Contractor’s receipt of notification of acceptance with deficiencies or rejection of any Contract Activities, Contractor must cure, at no additional cost, the deficiency and deliver unequivocally acceptable Contract Activities to the State. If acceptance with deficiencies or rejection of the Contract Activities impacts the content or delivery of other non-completed Contract Activities, the parties’ respective Program Managers must determine an agreed to number of days for re-submission that minimizes the overall impact to the Contract. However, nothing herein affects, alters, or relieves Contractor of its obligations to correct deficiencies in accordance with the time response standards set forth in this Contract.
If Contractor is unable or refuses to correct the deficiency within the time response standards set forth in this Contract, the State may cancel the order in whole or in part. The State, or a third party identified by the State, may perform the Contract Activities and recover the difference between the cost to cure and the Contract price plus an additional 10% administrative fee.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
8. Invoice and Payment
8.1. Invoice Requirements
All invoices submitted to the State must include: (a) date; (b) purchase order; (c) quantity; (d) description of the Contract Activities; (e) unit price; (f) shipping cost (if any); (g) vendor-generated invoice number and (h) total price.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
8.2. Payment Methods
The State will make payment for Contract Activities via EFT.
| ☐ |
| I have reviewed the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s):
9. Licensing Agreement The Contractor must provide a copy of any applicable licensing agreement.
Bidder must provide a copy of any applicable licensing agreement either in this response box or identified here as an attachment to this RFP.
10. Additional Requirements
10.1. Hazardous Chemical Identification
In accordance with the federal Emergency Planning and Community Right-to-Know Act, 42 USC 11001, et seq., as amended, the Contractor must provide a Material Safety Data Sheet listing any hazardous chemicals as defined in 40 CFR §370.2, to be delivered. Each hazardous chemical must be properly identified, including any applicable identification number, such as a National Stock Number or Special Item Number.
The Contractor must identify any hazardous chemicals that will be provided under any resulting contract.
| ☐ |
| I confirm the above requirement and agree with no exception. |
10.2. Mercury Content
Pursuant to MCL 18.1261d, mercury-free products must be procured when possible. The Contractor must explain if it intends to provide products containing mercury, the amount or concentration of mercury, and whether cost competitive alternatives exist. If a cost competitive alternative does exist, the Contractor must provide justification as to why the particular product is essential. All products containing mercury must be labeled as containing mercury.
| ☐ |
| I confirm the above requirement and agree with no exception. |
10.3. Brominated Flame Retardants
The State prefers to purchase products that do not contain brominated flame retardants (BFRs) whenever possible. The Contractor must disclose whether the products contain BFRs. Contractor must describe how products that meet these requirements are identified or otherwise labelled.
| ☐ |
| I confirm the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s): (Add rows as necessary.)
| Item #: |
| Response: |
12.5 Perfluoroalkyl and Polyfluoroalkyl Substances (PFAS)
The Contractor must disclose whether a product or its components contain intentionally added PFAS. If the product or its components contain intentionally added PFAS the Contractor must:
a. provide an explanation with respect to the intentionally added PFAS contents, including the purpose for which PFAS are used in the product or its components, the types of PFAS used in the product or its components, and the amount of each PFAS used in the product or its components.
b. indicate whether the product will be labeled or packaged with information about the intentionally added PFAS contents.
c. identify any alternative products that do not contain intentionally added PFAS.
d. provide any additional information that would further the Department’s implementation of ED 2021-08.
| ☐ |
| I confirm the above requirement and agree with no exception. |
| ☐ |
| I have reviewed the above requirement and have noted all exception(s) below. |
List all exception(s): (Add rows as necessary.)
| Item #: |
| Response: |
Bidder must provide detailed information as required above – either in this response box or identified here as an attachment to this RFP.
Version 2021-1 1 of 21
Version 2024-1 1 of 24 image1.png
File details come from the government source that posted it. Updated .