SCDPH_Building_-_25034_Project_Manual_11-11-26.pdf

PDF 8 MB Posted

Attached to
SCDPH Building Renovation & Parking Improvements
Solicitation number
IFB121826
Issued by
Barnwell County, South Carolina

About this file

This is a Project Manual and specification document for the SCDPH Building Renovation project in Beaufort County, South Carolina, prepared by Beaufort Design Build, LLC for Project Number 25034.00. The project consists of interior and exterior renovation of an existing 13,958-square-foot single-story pre-engineered metal building located at 247 Robert Smalls Parkway, Beaufort, South Carolina to accommodate South Carolina Department of Public Health operations. The scope includes demolition, interior build-out with new patient restrooms, staff facilities, exam rooms, administrative offices, conference/training room, new suspended acoustical tile ceilings, LED lighting, updated mechanical/electrical/plumbing systems, fire sprinkler modifications, and exterior site improvements including clearing, grading, new parking area, stormwater infrastructure, utility work, landscaping, and paving. The contract utilizes Beaufort County's standard owner/contractor agreement and general conditions. The contractor must submit a Critical Path Method construction schedule within 30 days of contract execution, with the project duration specified as 238 calendar days from Notice to Proceed. All submittals, including fire sprinkler shop drawings requiring South Carolina Office of State Fire Marshall approval, must be completed and approved before work commences. Pre-construction conference must be scheduled within 14 days of contract execution.

The contractor is responsible for purchasing and maintaining payment and performance bonds for the full contract value and must act as project expediter coordinating all subcontractors, vendors, and suppliers. The contract documents incorporate the 2021 International Building Code, 2021 International Fire Code, 2021 International Mechanical Code, 2021 International Plumbing Code, 2021 International Energy Conservation Code, 2023 National Electrical Code, and 2022 National Fire Protection Association 13 standards. The contractor must provide all temporary facilities, security, erosion control, tree protection, traffic control, waste disposal, and utilities necessary for construction. Contract modifications follow formal procedures requiring written notice within 30 days and substantiation within 15 days, with profit and overhead not to exceed 10 percent of change costs. No owner-furnished products are specified, and all costs for material delivery, handling, storage, and installation are included in the bid price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

247 Robert Smalls Parkway Interior Renovation

Beaufort Design Build, LLC Project Number 25034.00

PROJECT MANUAL

INCLUDING SPECIFICATIONS FOR THE CONSTRUCTION OF

247 Robert Smalls Parkway Interior Renovation

BEAUFORT, SOUTH CAROLINA

Prepared by

BEAUFORT DESIGN BUILD

Date of Issue:

November 11, 2026

Beaufort Design Build Project Number 25034.00 Beaufort County IFB Number TBD

2 Fire Station Lane, Seabrook, South Carolina 29940 843-466-3664

Blank Page

This page intentionally left blank.

00.1 Two-Sided Printing Instructions Page 1 of 1

This document is setup to print double sided.

Blank pages are intentional.

Table of Contents Page 1 of 3

TABLE OF CONTENTS

I. FORMS AND CONTRACT DOCUMENTS

See Beaufort County Bid Documents Information for Bidders Document for forms and contract documents

II. TECHNICAL SPECIFICATIONS

Division 01 General Requirements 01 10 00 Summary

01 14 00 Work Restrictions

01 25 00 Contract Modification Procedures

01 31 00 Project Management and Coordination

01 32 00 Construction Progress Documentation

01 33 00 Submittal Procedures

01 50 00 Temporary Facilities and Controls

01 55 26 Traffic Control – Work Zone

01 56 39 Temporary Tree and Plant Protection

01 60 00 Product Requirements

01 70 00 Execution Requirements

01 73 00 Selective Demolition

01 73 29 Cutting and Patching

01 77 00 Closeout Procedures

01 78 10 Project Record Documents

01 78 39 Record Documents

Division 02 Existing Conditions 02 10 00 Existing Conditions

02 11 00 Limited Asbestos Bulk Sampling Report

02 40 00 Removal of Structures and Obstructions

Division 06 Wood and Plastics 06 10 00 Rough Carpentry 06 41 13 Plastic Laminate Countertops

Division 07 Thermal and Moisture Protection 07 21 13 Thermal and Acoustical Insulation

07 84 00 Fire Stopping

07 92 00 Sealants

Division 08 Openings 08 11 00 Hollow Metal Doors and Frames

Table of Contents Page 2 of 3

08 14 00 Solid Core Wood Doors

08 31 13 Access Doors and Frames

08 71 00 Door Hardware

08 71 10 Door Hardware Schedule

Division 09 Finishes 09 22 16 Non-Structural Metal Framing

09 29 00 Gypsum Board

09 30 00 Ceramic Wall and Floor Tile

09 51 00 Suspended Acoustical Tile Ceilings

09 65 13 Resilient Base

09 65 19 Resilient Tile Flooring

09 91 00 Painting

Division 10 Specialties 10 14 00 Interior Signage

10 21 13 Toilet Partitions

10 26 00 Corner Guards

10 28 00 Restroom Accessories

10 44 13 Fire Extinguisher Cabinets

Division 21 Fire Suppression On Drawings

Division 22 Plumbing On Drawings

Division 23 Heating, Ventilation and Air Conditioning On Drawings

Division 26 Electrical On Drawings

Division 31 Earthwork 31 10 00 Clearing and Grubbing 31 20 00 Site Excavation for Roadways, Drainage, and Sites 31 23 13 Subgrade 31 24 13 Shoulders and Slopes 31 25 00 Erosion and Sedimentation Control 31 37 00 Rip Rap and Slope Protection

Table of Contents Page 3 of 3

Division 32 Electrical 32 11 23 Graded Aggregate Base 32 12 16 Asphalt Surface Course 32 14 13 Permeable Interlocking Concrete Pavers 32 16 00 Concrete Sidewalk, Curbing, and Driveways 32 17 23.13 Permanent Pavement Markings – Fast Dry Waterborne Paint 32 17 23.33 Thermoplastic Pavement Markings 32 92 19 Seeding

Division 33 Electrical 33 10 00 Potable Water System 33 30 00 Sanitary Sewer System 33 42 11 Storm Sewers and Pipe Culverts 33 42 31 Storm Drainage Structures

END OF TABLE OF CONTENTS

00.4 List of Drawing Sheets Page 1 of 2

LIST OF DRAWING SHEETS

The drawings listed below accompany the Project Manual and are part of the contract. In the case of a conflict between information provided in the drawings and information provided in the specifications, the more restrictive shall take precedence.

GENERAL INFORMATION AND CODE DRAWINGS

G-101 COVER SHEET, SHEET INDEX AND SCOPE OF WORK

G-102 CONSTRUCTION NOTES AND DETAILS

G-103 SYMBOLS, ABBREV AND MATERIAL DESIGNATION

G-104 2021 INTERNATIONAL BUILDING CODE SUMMARY

G-105 LIFE SAFETY PLAN

G-106 TYPICAL ACCESSIBLE DETAILS

G-107 SUPPORTING DOCUMENTS

CIVIL DRAWINGS

C001 COVER SHEET

C002 GENERAL NOTES

C003 EXISTING CONDITIONS & DEMOLITION PLAN

C004 SITE PLAN

C005 GRADING PLAN

C006 DRAINAGE PLAN

C007 DRAINAGE PROFILE

C008 UTILITY PLAN & PROFILES

C009 SWPP NOTES

C010 SWPP PLAN

C011 SITE, GRADING, AND DRAINAGE DETAILS

C012 SITE, GRADING, AND DRAINAGE DETAILS

C013 SEWER DETAILS

C014 SWPP DETAILS

C015 SWPP DETAILS

C016 PLANTING PLAN

C017 PLANTING DETAILS

ARCHITECTURAL DRAWINGS

D-101 DEMOLITION FLOOR PLAN

D-102 DEMOLITION REFLECTED CEILING PLAN

D-103 INTERIOR DEMOLITION PHOTOGRAPHS

A-101 FLOOR PLAN

A-102 REFLECTED CEILING PLAN

00.4 List of Drawing Sheets Page 2 of 2

A-103 FLOOR FINISH PLAN

A-104 LOW VOLTAGE FLOOR PLAN

A-201 EXTERIOR ELEVATIONS

A-202 EXISTING CONDITIONS EXTERIOR PHOTOGRAPHS

A-301 BUILDING SECTIONS

A-302 TYPICAL WALL SECTIONS

A-401 ENLARGED FLOOR PLAN AND RESTROOM SCHEDULE

A-402 ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS

A-403 ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS

A-404 MILLWORK/CASEWORK SECTIONS AND DETAILS

A-501 PARTITION TYPES, CEILING AND MISCELLANEOUS DETAILS

A-601 ROOM FINISH, DOOR SCHEDULES AND DETAILS

A-602 SIGN SCHEDULE AND DETAILS

ASF-101 ARCHITECTURAL FIRE PROTECTION NOTES AND DETAILS

ASF-102 ARCHITECTURAL FIRE PROTECTION FLOOR PLAN

MECHANICAL DRAWINGS

M0-01 MECHANICAL TITLE SHEET

M1-01 OVERALL MECHANICAL PLAN

M2-01 ENLARGED MECHANICAL PLAN

M2-02 ENLARGED MECHANICAL PLAN

M2-03 ENLARGED MECHANICAL PLAN

M2-04 ENLARGED MECHANICAL PLAN

M5-01 MECHANICAL DETAILS

M6-01 MECHANICAL SCHEDULES

ELECTRICAL DRAWINGS

E001 ELECTRICAL NOTES AND LEGEND

E002 ELECTRICAL SWITCHING DETAILS

E003 ELECTRICAL PANELS & RISER

E100 POWER INSTALLATION PLAN

E200 LIGHTING INSTALLATION PLAN

PLUMBING DRAWINGS

P0-01 PLUMBING TITLE SHEET

P1-01 OVERALL PLUMBING PLAN

P1-02 OVERALL SANITARY WASTE AND VENT PLAN

P1-03 OVERALL PLUMBING DOMESTIC WATER PLAN

00.2 Professional Seals Page 1 of 2

Architect Daniel C. Saltrick, AIA Beaufort Design Build, LLC 2 Fire Station Lane Seabrook, South Carolina 29940 843-466-3664

01 10 00 Summary Page 1 of 3

SECTION 01 10 00

SUMMARY

PART 1 - GENERAL

1.1 SUMMARY OF WORK

A. This Summary is supplemental to the Drawings and the technical specifications.

B. The Project consists of an interior and exterior upfit and renovation of an existing 13,958 square foot single-story pre-engineered metal building located at 247 Robert Smalls Parkway, Beaufort, South Carolina 29906.

1. The project area will be vacant for the duration of the project.

2. This project does not include phased construction.

C. Project delivery method: Design - public bid - build.

D. Existing floor finishes and wall base will be removed and will be replaced with luxury vinyl tile with 4" rubber base.

E. Existing gypsum board walls will be patched and repaired, primed and painted.

F. Electrical work will utilize the existing electrical service and include new lighting fixtures and service outlets as required.

G. Existing suspended acoustical tile ceiling tiles and grid will be removed.

H. The existing fire sprinkler system will be modified as needed to accommodate the new layout and use.

I. Plumbing work will include new restroom and break room fixtures, utilizing existing domestic water and sanitary sewer service lines.

J. Mechanical work will include installation of all new systems required to support the new occupancy.

K. The project includes new patient restrooms (male and female), new staff restrooms, one (1) unisex lab restroom, multiple exam rooms, a break room with sink, administrative offices, and a conference/training room. This work includes new gypsum board and metal stud walls, solid core wood doors in hollow metal frames, new suspended acoustical tile ceilings, new LED light fixtures, new mechanical systems, and updated electrical and plumbing systems.

L. Additional Scope of Work items and General Construction Requirements are outlined on Drawing Sheet G-101, Cover Sheet, Sheet Index and Scope of Work.

M. The general contractor shall act as the project expediter and is responsible for coordinating the work of all subcontractors, vendors, suppliers, etc.

1.2 CONTRACT

01 10 00 Summary Page 2 of 3

A. Project will utilize Beaufort County's standard owner/contractor agreement and general conditions. These documents are included in the County’s Information for Bidders Documents.

B. The contractor shall purchase and maintain, for the life of the contract, payment and performance bonds for the full value of the contract.

1.3 WORK SEQUENCE

A. The contractor is responsible for scheduling, managing and conducting the work in a logical and expeditious manner so as to meet the requirements of the contract.

1.4 WORK UNDER OTHER CONTRACTS

A. Separate Contract: Owner reserves the right to award a separate contract for performance of certain construction operations at project site. Those operations may be conducted simultaneously with work under this Contract.

B. Contractor shall cooperate fully with separate contractors so work on other contracts may be carried out smoothly, without interfering with or delaying Work under this Contract.

1.5 SPECIFICATION FORMATS AND CONVENTIONS

A. Technical Specifications Format: The Specifications are organized into Divisions and Sections using the 48-division format and Construction Specifications Institute / Construction Specifications Canada (CSI/CSC's) 2004 "Master Format" numbering system.

1. Section Identification: The Technical Specifications use section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of sections in the Contract Documents.

B. Technical Specifications Content: The Technical Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Technical Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires.

Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Technical Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

1.6 APPLICABLE CODES AND STANDARDS

A. All new work shall comply with the codes and standards referenced below, on the Drawings and in other sections of the Project Manual.

01 10 00 Summary Page 3 of 3

B. 2021 International Building Code and other codes and standards referenced therein.

C. 2021 International Fire Code and other codes and standards referenced therein.

D. 2021 International Mechanical Code and other codes and standards referenced therein.

E. 2021 International Plumbing Code and other codes and standards referenced therein.

F. 2021 International Energy Conservation Code and other codes and standards referenced therein.

G. 2023 National Electrical Code and other codes and standards referenced therein.

H. 2022 National Fire Protection Association 13, Standard for the Installation of Fire Sprinkler Systems and other codes and standards referenced therein.

I. International Code Council A117.1 (accessibility).

J. Americans with Disabilities Act, Title III (accessibility).

PART 2 - PRODUCTS

2.1 PRODUCTS ORDERED IN ADVANCE

A. Unless otherwise stated in the Contract Documents, Costs for receiving, handling, storage if required, and installation of material and equipment shall be included in the Bid and Contract Sum.

2.2 OWNER-FURNISHED PRODUCTS

A. There are no Owner furnished construction products or equipment.

END OF SECTION 01 10 00

01 14 00 Work Restrictions Page 1 of 2

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

1.2 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated on the drawings. Do not disturb portions of building or site beyond areas in which the Work is indicated.

1. Construction Limits: Confine construction operations to those areas shown on the drawings.

a. Construction Limits shown on the drawings represent the limits of the area which will be made available to the contractor for excavation and grading and building construction work, laydown and storage of materials and equipment, and other construction activities. Construction fencing may be placed anywhere within the Construction Limits.

2. Driveways and Entrances: Keep driveways and entrances serving adjacent properties clear and accessible at all times. Do not block access to adjacent properties or roadways.

a. Schedule deliveries to minimize disruptions to adjacent properties and businesses.

b. The contractor shall document the condition of all driveways, sidewalks, curb and gutter and planting areas before starting work. Damage to existing conditions, caused by construction activities, will be repaired at the contractor’s expense. Repairs shall of the same materials, craftsmanship and design as the existing conditions.

3. Contractor's storage, staging and laydown area is identified on Drawing Sheet C004, Site Plan. It is the contractor's responsibility to provide fencing, secure storage, etc., as required for the protection of materials, equipment, etc.

a. Temporary facilities (restroom, storage containers, office, etc.) must be located within the designated storage. staging and laydown area.

b. At the completion of the project, the storage, staging and laydown area is to be left as it was found prior to the start of construction.

4. Storm Water Controls: Protect existing roadways, gutters and curb inlets from silt, mud and other contaminants. Provide silt fence and other erosion control measures as shown on the Drawings and as required to prevent silt, mud and other contaminants from leaving the site.

5. Construction work hours are not restricted but, it is the contractor’s responsibility to comply with all local restrictions regarding work hours and noise.

a. All work delineated within the contract documents is to take place outside of normal business hours shall be provided as such.

1) The contractor shall include all aspects of related work that will be required to complete work delineated to take place outside of normal business hours.

01 14 00 Work Restrictions Page 2 of 2

B. Use of Existing Building: Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations.

END OF SECTION 01 14 00

01 25 00 Contract Modification Procedures Page 1 of 4

SECTION 01 25 00

CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications whereas all parties agree to the following:

1. A modification in the Work or Contract Documents.

2. The amount of the adjustment in the Contract Sum, if any.

3. The extent of the adjustment in the Contract Time, if any.

1.3 NOTIFICATION TO SURETY

A. The Contractor shall notify the Surety of any modifications to the Work or provisions of the Contract Documents, including, but not limited to, the Contract Price or Contract Time.

1.4 MINOR CHANGES IN THE WORK

A. The Consultant shall have authority to order Minor Changes in the Work not involving adjustment to the Contract Sum or extension of the Contract Time, and consistent with the intent of the Contract Documents. Such changes shall be in a form of a written order and shall be binding for both the Owner and Contractor when fully executed.

1.5 CLAIMS FOR ADDITIONAL COST:

A. No claim for an adjustment in Contract Price or Contract Times will be valid if not submitted in accordance with the following:

1. Notice: Written notice stating the general nature of each claim shall be delivered by the claimant to the other party to the Contract promptly, but in no event later than thirty (30) days after the start of the event giving rise to the claim.

2. The responsibility to substantiate a claim shall rest with the party making the claim.

The amount or extent of the claim, with supporting data, shall be delivered to the other party to the Contract within f ifteen (15) days after the initial Notice of the Claim.

Each claim shall be accompanied by claimant's written statement that the adjustment claimed is the entire adjustment to which the claimant believes it is entitled as a result of said event. The opposing party shall submit any response to the claimant within thir ty (30) days after receipt of the claimant's last submittal. Prior notice is not required for Claims relating to an emergency endangering life or property.

B. The Contractor shall submit a claim if he believes additional cost is involved for reasons including but not limited to the following:

1. A written interpretation from the Consultant,

2. An order by the Owner to stop the Work where the Contractor was not at fault,

3. A written order for a minor change in the Work issued by the Consultant,

4. A change in the Scope of the Work by the Consultant.

01 25 00 Contract Modification Procedures Page 2 of 4

1.6 PROPOSAL REQUESTS

A. The Owner initiated Proposal Requests is generated by the Owner to modify the Work or Contract Documents. The Consultant will issue a detailed description of proposed modifications in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

The description is for information and shall be considered as a directive to automatically stop work or execute the proposed change.

1. Within ten 10-calendar days after receipt of the Proposal Request, the Contractor shall submit a Proposal Request Form with an estimate to adjust the Contract Sum and the Contract Time if necessary to execute the change. Proposal shall include support documents from Subcontractor, if applicable.

a. Include a list of quantities of (plus or minus) the materials and/or products required with unit prices, total amount of purchases, and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change, including social security, old age and unemployment insurance, fringe benefits, and workmen’s compensation insurance.

d. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start, and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

2. The Contractor may initiate proposals if latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to Consultant.

a. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change.

Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

b. Include a list of quantities of (plus or minus) the materials and/or products required with unit prices, total amount of purchases, and credits to be made. If requested, furnish survey data to substantiate quantities.

c. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

d. Include costs of labor and supervision directly attributable to the change, including social security, old age and unemployment insurance, fringe benefits, and workmen’s compensation insurance.

e. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

f. Comply with requirements in Division 1 Section, of the Technical Specifications "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.

B. An alternative method to price the changes in the work is to utilize current “Mean’s Cost Data”.

C. Profit and Overhead shall not exceed ten percent (10%) of the cost of the changes to the Work.

01 25 00 Contract Modification Procedures Page 3 of 4

D. Use Proposal Request Form provided by Owner. A Sample is included under Project Manual Heading VII - Forms. The Contractor shall prepare three copies, one for the Consultant, one for the Owner and one for himself and for all parties to sign. Each shall keep a copy.

E. The Contractor shall be responsible for keeping and updating a “Proposal Request Log”, listing all Proposal Requests and Minor Changes. The log shall also indicate the date of the Proposal Request, approval date, action taken, running balances, and a complete description of the change.

F. After all parties have signed “The Proposal Request Form”, it shall be the Contractor’s authorization to proceed with the changes to the Work.

G. If the Owner and Contractor do not agree with the requested adjustment in the Contract Sum, the Contract Time or the method of determining each, the provisions for Mediation shall be utilized.

1.7 CHANGE ORDER PROCEDURES

A. The Consultant shall issue a Change Order for signatures once all of the Proposal Request(s) amounts exceeds the contingency amount or at the end of the project.

B. The Contractor shall not invoice for the Change Order until it has been executed by all parties.

1.8 CONSTRUCTION CHANGE DIRECTIVE

A. The Consultant may issue a Construction Change Directive that has been signed by the Owner to the Contractor directing a change in the Work. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Upon receipt of a Construction Change Directive, the Contractor shall promptly proceed with the change in the Work involved. And the Contractor shall advise the Consultant of the Contractor’s agreement or disagreement with the method, if any, provided in the Construction Change Directive for determining the proposed adjustment in the Contract Sum or Contract Time.

C. The Contractor shall maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PROCESSING CHANGE ORDERS

A. The Change Order will be issued describing the change or changes to the Work and/or Contract Documents and will refer to the Proposal Requests.

B. The Consultant shall issue one copy of the Change Order to the Contractor. The Contractor shall promptly sign the copy and return the copy to the Consultant who will sign the Change Order and forward the Change Order to the Owner to execute.

C. Once the Change Order has been full executed, a copy shall be forwarded to the Consultant and to the Contractor for their files.

01 25 00 Contract Modification Procedures Page 4 of 4

END OF SECTION 01 25 00

01 31 00 Project Management and Coordination Page 1 of 5

SECTION 01 31 00

PROJECT MANAGEMENT AND COORDINATOR

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

1.2 SUMMARY

A. To enable orderly review during progress of the Work, and to provide for systematic discussion of problems, the Consultant will chair and conduct project meetings and compile an agenda for each meeting throughout the construction period.

B. This Section includes administrative provisions for coordinating construction operations on the Project including, but not limited to, the following:

1. General project coordination procedures.

2. Coordination Drawings.

3. Administrative and supervisory personnel.

4. Project meetings.

C. Related Sections: The following Sections contain requirements that relate to this Section:

1. Division 1, of the Technical Specifications Section "Construction Progress Documentation" for preparing and submitting the Contractor's Construction Schedule.

2. Division 1, of the Technical Specifications Section "Closeout Procedures" for coordinating Contract closeout.

1.3 COORDINATION

A. Coordination: Coordinate construction operations included in various Sections of the Technical Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. If necessary, the Consultant shall prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

01 31 00 Project Management and Coordination Page 2 of 5

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work.

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Indicate relationship of components shown on separate Shop Drawings.

2. Indicate required installation sequences.

3. Show structural elements that restrict installation of mechanical duct, sprinkler piping, etc.

B. Staff Names: Fourteen days prior to the Pre-Construction conference, submit a list of principal staff assignments, including superintendent and other personnel in attendance at Project site.

Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home and office telephone numbers. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project.

1. Post copies of list in Project meeting room, in temporary field office, and by each temporary telephone.

1.5 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. General: In addition to Project superintendent, provide other administrative and supervisory personnel as required for proper performance of the Work.

1.6 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting.

2. Agenda: The Architect shall prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes:

a. The Architect will compile minutes of each project meeting, and will distribute copies to the Contractor and required copies to the Owner.

b. Recipients of copies may make and distribute such other copies as they wish.

4. Attendance:

a. To the maximum extent practical, assign the same person or persons to represent the Contractor at the project meetings throughout progress of the

01 31 00 Project Management and Coordination Page 3 of 5

Work.

b. Subcontractors, materials suppliers, and others may be invited to attend those project meetings in which their aspect of the Work is involved.

5. Minimum agenda:

a. Review, revise as necessary, and approve minutes of previous meetings.

b. Review progress of the Work since last meeting, including status of submittals for approval.

c. Identify problems which impede planned progress.

d. Develop corrective measures and procedures to regain planned schedule.

e. Complete other current business.

B. Pre-construction Conference: Schedule a pre-construction conference before starting construction, at a time convenient to Owner and Consultant, but no later than 14 days after execution of the Construction Contract. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments.

1. Attendees: Authorized representatives of Owner, Consultant, and their consultants;

Contractor and its superintendent; major subcontractors and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing.

c. Critical work sequencing.

d. Designation of responsible personnel.

e. Procedures for processing field decisions and Change Orders.

f. Procedures for processing Applications for Payment.

g. Distribution of the Contract Documents.

h. Submittal procedures.

i. Preparation of Record Documents.

j. Use of the premises.

k. Responsibility for temporary facilities and controls.

l. Parking availability.

m. Office, work, and storage areas.

n. Equipment deliveries and priorities.

o. Security.

p. Working hours.

B. Pre-installation Conferences: Conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Consultant of scheduled meeting dates and times.

01 31 00 Project Management and Coordination Page 4 of 5

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related Change Orders.

d. Purchases.

e. Deliveries.

f. Submittals.

g. Review of mockups.

h. Possible conflicts.

i. Time schedules.

j. Weather limitations.

k. Manufacturer’s written recommendations.

l. Temporary facilities and controls.

m. Space and access limitations.

n. Regulations of authorities having jurisdiction.

o. Testing and inspecting requirements.

p. Required performance results.

q. Protection of construction and personnel.

r. Record significant conference discussions, agreements, and disagreements.

s. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

C. Progress Meetings: Conduct progress meetings at a minimum of once every two weeks.

Coordinate dates of meetings with preparation of payment requests.

1. Attendees: Representatives at the meeting shall be the Owner, Consultant, Subcontractors, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

01 31 00 Project Management and Coordination Page 5 of 5

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Access.

6) Work hours.

7) Hazards and risks.

8) Review of Record Drawings

9) Review of construction defects that has been identified by the Consultant

3. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report.

a. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

01 32 00 Construction Progress Documentation Page 1 of 2

SECTION 01 32 00

CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this 10

B. A representative project schedule is provided at the end of this specification section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor’s Construction Schedule.

2. Contractor's Construction Schedule shall graphically illustrate the Critical Path for completion of all tasks. Task durations shall be illustrated graphically.

3. Start and finish dates and duration shall be indicated for all tasks.

4. Contractor's Construction Schedule shall include Mobilization, Punch-List and Closeout tasks.

1.3 SUBMITTALS

A. Contractor’s Proposed Critical Path Method Construction Schedule: Submit in electronic PDF format utilizing an 11”x17” print layout.

B. Submit proposed schedule within 30 days of contract execution. Notice to proceed will not be issued until the contractor's schedule has been approved by the Architect and the Owner.

PART 2 - PRODUCTS

2.1 CRITICAL PATH CONSTRUCTION SCHEDULE

A. Workdays: Format schedule based on a 7-day week.

B. If required, indicate the time required for South Carolina Office of State Fire Marshall review and approval of fire sprinkler shop drawings.

C. Identify long lead items, systems and equipment.

D. Preparation: Indicate each significant construction activity separately. Identify start, finish and duration for each task.

E. Critical Path: Clearly indicate how critical path tasks are linked to each other and indicate dependencies.

F. Indicate float and slack time, as appropriate, for each task.

G. Show the current date as a vertical line.

H. Contract completion date shall not be changed unless specifically authorized by change order. Regardless of the completion date shown on the Contractors Proposed Construction Schedule, delays and associated costs will be based on the project duration as specified – two hundred and thirty-eight (238) calendar days from Notice to Proceed.

01 32 00 Construction Progress Documentation Page 2 of 2

I. As a minimum, show the following milestones;

1. Completion of submittals

2. OSFM approval of fire sprinkler shop drawings.

3. Mobilization and Security of Project Area.

4. Demolition.

5. Flooring Installation.

6. Base Installation.

7. Suspended Acoustical Tile Ceiling Modification and New Work.

8. New Partition Construction.

9. Doors, Frames and Hardware.

10. HVAC Duct and Device Modification.

11. Light Fixture Replacement.

12. Electrical Device Relocation and Associated Wiring.

13. Painting.

14. The Owner and the Architect reserve the right to request additional tasks and milestones as part of the submittal review process.

PART 3 - EXECUTION

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Contractor's Proposed Construction Schedule Updating: At regular intervals, update schedule to reflect actual construction progress and activities.

1. Schedule will be reviewed at each regular progress meeting.

END OF SECTION 01 32 00

01 33 00 Submittal Procedures Page 1 of 4

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.

B. All submittals are to be prepared, submitted and approved before notice to proceed with work is issued. No work is to begin until all submittals have been approved.

C. If required, fire sprinkler shop drawings are to be prepared, approved by the Owner, Architect and Engineer and approved by the South Carolina Office of the State Fire Marshall (SCOSFM) before notice to proceed with work is issued.

D. The contractor's schedule of values, critical path schedule, project directory and mobilization and storage, staging and laydown plan are to be prepared, submitted and approved before notice to proceed with work is issued. No work is to begin until these submittals have been approved.

1.3 SUBMITTAL PROCEDURES

A. The Contractor shall provide the submittals as required by the Contract Documents.

B. General: Electronic copies of CAD Drawings of the Contract Drawings will not be provided by Consultant for Contractor's use in preparing submittals.

C. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Consultant reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

D. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Consultant's receipt of submittal. Allow seven (7) calendar days for review of each submittal and seven (7) calendar days for review of each re-submittal.

E. Identification: Place a permanent label or title block on each submittal for identification. Indicate name of firm or entity that prepared each submittal.

F. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

G. Transmittal: Package each submittal individually and appropriately for transmittal and handling.

Transmit each submittal using a transmittal form. Consultant will return submittals, without review, received from sources other than Contractor.

01 33 00 Submittal Procedures Page 2 of 4

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

I. Use for Construction: Use only final submittals with mark indicating action taken by Consultant in connection with construction.

PART 2 - PRODUCTS

2.1 SUBMITTALS

A. General: Prepare and submit Submittals as required by individual Specification Sections.

1. Send all submittals to the Architect. Do not send submittals directly to consulting engineers.

2. To the greatest extent possible, submit in electronic PDF format. Email submittals to Margaret@beaufortdesignbuild.com.

3. Provide three (3) sets of all samples.

4. Submittals that have not been reviewed and approved by the general contractor will be returned without review. Submittals are to be stamped or shall have a cover letter indicating the general contractor's approval.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. Mark each copy of each submittal to show which products and options are applicable.

2. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Standard color charts.

e. Manufacturer's catalog cuts.

f. Wiring diagrams showing factory-installed wiring.

g. Printed performance curves.

h. Operational range diagrams.

i. Mill reports.

j. Standard product operating and maintenance manuals.

k. Compliance with recognized trade association standards.

l. Compliance with recognized testing agency standards.

m. Application of testing agency labels and seals.

n. Notation of coordination requirements.

o. Manufacturer’s location.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

01 33 00 Submittal Procedures Page 3 of 4

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams and existing conditions.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Shopwork manufacturing instructions.

g. Templates and patterns.

h. Schedules.

i. Design calculations.

j. Compliance with specified standards.

k. Notation of coordination requirements.

l. Notation of dimensions established by field measurement.

D. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts showing the full range of colors, textures, and patterns available.

2. Preparation: Mount, display, or package Samples in manner specified to facilitate review of qualities indicated. Prepare Samples to match Consultant's sample where so indicated. Attach label on unexposed side that includes the following:

a. Generic description of Sample.

b. Product name or name of manufacturer.

c. Sample source.

3. Submit Samples for review of kind, color, pattern, and texture for a final check of these characteristics with other elements and for a comparison of these characteristics between final submittal and actual component as delivered and installed.

a. If variation in color, pattern, texture, or other characteristic is inherent in the product represented by a Sample, submit at least three sets of paired units that show approximate limits of the variations. The consultant will return submittal with the option selected.

b. Refer to individual Specification Sections for requirements for Samples that illustrate workmanship, fabrication techniques, details of assembly, connections, operation, and similar construction characteristics.

PART 3 - EXECUTION

3.1 CONTRACTOR'S REVIEW

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Consultant.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

01 33 00 Submittal Procedures Page 4 of 4

3.2 ARCHITECT'S ACTION

A. General: The Architect will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. The Architect will review each submittal, make marks or otherwise indicate corrections or modifications required, and return it. Consultant will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:

C. At the Architect’s discretion, Submittals not required by the Contract Documents might not be reviewed and may be discarded.

D. When a submittal is returned “approved as noted” (or similar), the Contractor must provide written response to all comments within 7 calendar days. Failure to do so will result in the submittal status being changed to “Rejected.”

END OF SECTION 01 33 00

01 50 00 Temporary Facilities and Controls Page 1 of 5

SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

1.2 SUMMARY

A. This Section includes requirements for temporary facilities and controls, including temporary utilities, support facilities, and security and protection facilities.

B. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

C. Utilities: The contractor will have access to and use of existing water, sewer and power at the existing building.

D. Support facilities include, but are not limited to, the following:

1. Waste disposal.

2. Lifts and hoists.

3. Temporary restrooms / toilets.

4. Drinking water.

5. Construction aids and miscellaneous services and facilities.

E. Security and protection facilities include, but are not limited to, the following:

1. Environmental protection.

2. Storm water control.

3. Tree and plant protection.

4. Pest control.

5. Security enclosure and lockup at contractor's storage, staging and laydown area.

6. Barricades, warning signs, and lights.

7. Temporary enclosures.

8. Temporary partitions.

9. Fire protection.

1.3 CODES AND STANDARDS

A. Comply with all applicable requirements of the Occupational Safety and Health Administration, Standards for the Construction Industry.

B. Comply with the applicable requirements of the codes and standards referenced on Drawing Sheet G-101, Cover Sheet, Sheet Index and Scope of work and in Project Manual Section 01 10 00, Summary.

PART 2 - PRODUCTS:

01 50 00 Temporary Facilities and Controls Page 2 of 5

2.1 MATERIALS

A. General: Provide new materials. Undamaged, previously used materials in serviceable condition may be used if indicated on the plans and/or specifications. Provide materials suitable for use intended.

B. Chain-Link Fencing: Minimum 2-inch , 0.148-inch- thick, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top rails.

C. Portable Chain-Link Fencing: Minimum 2-inch 9-gage, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails.

Provide concrete or galvanized steel bases for supporting posts.

D. Lumber and Plywood: Comply with the applicable requirements in Division 6.

E. Gypsum Board: Minimum 1/2 inch thick by 48 inches wide by maximum available lengths;

regular-type panels with tapered edges. Comply with ASTM C 36.

F. Insulation: Unfaced mineral-fiber blanket, manufactured from glass, slag wool, or rock wool;

with maximum flame-spread and smoke-developed indices of 25 and 50, respectively.

G. Tarpaulins: Fire-resistive labeled with flame-spread rating of 15 or less.

H. Water: Potable.

2.2 EQUIPMENT

A. General: Provide equipment suitable for use intended.

B. Field Offices: A field office is not required however, the contractor’s on-site superintendent shall have immediate access to email and shall maintain a set of record drawings on site where they are immediately accessible to the Architect.

C. Fire Extinguishers: Hand carried, portable, UL rated. Provide class and extinguishing agent as indicated or a combination of extinguishers of NFPA-recommended classes for exposures.

1. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and size required by location and class of fire exposure and the requirements of the local Governing agency.

D. Self-Contained Toilet Units: Single-occupant units of chemical…

This is the start of the file's text. The full file is on GovTribe.