About this file
This is a Notice of Contractor's Settlement issued by the State of Colorado, Office of the State Architect, State Buildings Program, involving Morgan Community College and the contractor Denver Fire Alarm. The settlement pertains to Project 2024-112M23, titled "Campuswide Safety and Security Updates." Final settlement for the construction project will be executed on May 22nd, 2026, at 920 Barlow Road, Fort Morgan, Colorado. The notice was published on May 22nd and May 23rd, 2026.
Any party with unpaid claims against the project for labor, materials, equipment rental, tools, or supplies provided to the contractor or its subcontractors must file a verified statement of the amount due with Morgan Community College by the final settlement date. Failure to submit claims prior to the settlement will release the State of Colorado from all liability for such claims. The authorized facility manager is Chloe Hirschfeld, Director of Purchasing & Capital Projects at Morgan Community College, who can be contacted at 970-542-3126 or chloe.hirschfeld@morgancc.edu.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SBP-6.271
07/2025
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
NOTICE OF CONTRACTOR’S SETTLEMENT
Notice Number: 2026000225 Institution or Agency: Morgan Community College Project No./Project Name: 2024-112M23/Campuswide Safety and Security Updates
Notice is hereby given that on May 22nd, 2026, at 920 Barlow Road Fort Morgan, Colorado, final settlement will be made by the STATE OF COLORADO with Denver Fire Alarm, hereinafter called the "CONTRACTOR", for and on account of the contract for the construction of a PROJECT as referenced above.
1. Any person, co-partnership, association or corporation who has an unpaid claim against the said project, for or on account of the furnishing of labor, materials, team hire, sustenance, provisions, provender, rental machinery, tools, or equipment and other supplies used or consumed by such Contractor or any of his subcontractors in or about the performance of said work, may at any time up to and including said time of such final settlement, file a verified statement of the amount due and unpaid on account of such claim
2. All such claims shall be filed with the Authority for College, Institution, Department or Agency.
3. Failure on the part of a creditor to file such statement prior to such final settlement will relieve the State of Colorado from any and all liability for such claim
Authorized Facility Manager or Authorized Individual
Name: Chloe Hirschfeld, Director of Purchasing & Capital Projects Approved Date: May 22nd, 2026 Agency: Morgan Community College Phone: 970-542-3126 Email: chloe.hirschfeld@morgancc.edu
PUBLICATION DATES:
First: May 22nd, 2026 Second: May 23rd, 2026