Amendment_0001_Site_Visit_Change.pdf

PDF 5 MB Posted

Attached to
SB1341-17-RP-0028 remove & replace lift station pumps
Solicitation number
SB1341-17-RP-0028
Issued by

About this file

AMENDMENT TO REFLECT SITE VISIT DATE CHANGE to AUGUST 3, 2017.

View the file

Other files

File Type Posted
Request_for_Information.pdf PDF
Solicitation_SB1341-17-RP-0028.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

11. The contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

NSN 7540-01-155-3212

calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

This procurement is a 100% Historically Underutilized Business Zone (HUBZone) small business set aside, see FAR Clause 52.219-3 herein. The North American Industry Classification System (NAICS) Code for this acquisition 237110.

In accordance with FAR 36.204 – Disclosure of the Magnitude of Construction Projects, the amount for this project is between $100,000.00 and $250,000.00.

All offerors must complete and return the standard form 1442: OFFER Section blocks 14-20c, and SCHEDULE Item No. section. Offerors must comply with the FAR requirements of 52.204-7, 52.204-8, 52.232-33, and any other CCR/ORCA requirements.

Funds for Line Item 0001 are presently available for this acquisition.

A site visit will be conducted on August 03, 2017. See FAR 52.236-27, for details. Request for Information (RFI) shall be due shortly afterwards, with a submittal deadline of August 9, 2017, 1pm. MST.

A bid guarantee is required.

STANDARD FORM 1442 (REV. )

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( )

20b. SIGNATURE 20c. OFFER DATE

STANDARD FORM 1442 (REV. ) BACK

SCHEDULE Continued

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

PAGE 3 OF 70 SB134117RP0028

0001 Remove and replace 2 lift station sewage pumps in Bldg. 1, room 1049, in accordance with attached Performance Work Statement, and associated attachments. Reference attached Wage determination, dated 06.09.2017.

DELIVERY DATE: 12/22/2017

FOB : Destination

1.00 JB

0002 Optional Line Item: Remove and replace one lift station sewage pump in Bldg. 2 mechanical room, in accordance with attached Performance Work Statement, and associated attachments. Reference attached Wage determination, dated 06.09.2017.

DELIVERY DATE: 12/22/2017

FOB : Destination

1.00 JB

Table of Contents

PAGE 4 OF 70 SB134117RP0028

SECTION C DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C. 1 Performance Work Statement

C. 2 Attachment 1

C. 3 Attachment 2

SECTION E INSPECTION AND ACCEPTANCE

E. 1 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)

E. 2 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

E. 3 52.246-13 INSPECTION--DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS (AUG 1996)

E. 4 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

E. 5 1352.271-83 GOVERNMENT REVIEW, COMMENT, ACCEPTANCE AND APPROVAL (APR 2010)

E. 6 1352.246-70 PLACE OF ACCEPTANCE (APR 2010)

SECTION F DELIVERIES OR PERFORMANCE

F. 1 52.236-2 DIFFERING SITE CONDITIONS (APR 1984)

F. 2 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)

F. 3 52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)

F. 4 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

F. 5 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)

F. 6 52.236-8 OTHER CONTRACTS (APR 1984)

F. 7 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS (APR 1984)

F. 8 52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)

F. 9 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)

F. 10 52.236-12 CLEANING UP (APR 1984)

F. 11 52.236-13 ACCIDENT PREVENTION (NOV 1991)

F. 12 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)

F. 13 52.236-21 I SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)--ALTERNATE I (APR

1984)

F. 14 52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)

F. 15 52.242-14 SUSPENSION OF WORK (APR 1984)

F. 16 52.242-17 GOVERNMENT DELAY OF WORK (APR 1984)

F. 17 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

F. 18 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)

SECTION G CONTRACT ADMINISTRATION DATA

G. 1 Wage Determination

G. 2 1352.201-70 CONTRACTING OFFICER?s AUTHORITY (APR 2010)

G. 3 1352.201-72 CONTRACTING OFFICER`S REPRESENTATIVE (COR) (APR 2010)

G. 4 NIST LOCAL-04 BILLING INSTRUCTIONS

SECTION H SPECIAL CONTRACT REQUIREMENTS

H. 1 1352.208-70 RESTRICTIONS ON PRINTING AND DUPLICATING (APR 2010)

H. 2 1352.209-73 COMPLIANCE WITH THE LAWS (APR 2010)

H. 3 1352.209-74 ORGANIZATIONAL CONFLICT OF INTEREST (APR 2010)

H. 4 1352.228-72 DEDUCTIBLES UNDER REQUIRED INSURANCE COVERAGE- FIXED PRICE (APR 2010)

H. 5 1352.209-72 RESTRICTIONS AGAINST DISCLOSURE (APR 2010)

H. 6 1352.228-70 INSURANCE COVERAGE (APR 2010)

SECTION I CONTRACT CLAUSES

I. 1 52.202-1 DEFINITIONS (NOV 2013)

PAGE 5 OF 70 SB134117RP0028

I. 2 52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

I. 3 52.203-3 GRATUITIES (APR 1984)

I. 4 52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)

I. 5 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006)

I. 6 52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)

I. 7 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY

(MAY 2014)

I. 8 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)

I. 9 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT 2010)

I. 10 52.203-16 PREVENTING PERSONAL CONFLICTS OF INTEREST (DEC 2011)

I. 11 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF

WHISTLEBLOWER RIGHTS (APR 2014)

I. 12 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011)... 25

I. 13 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (OCT 2016).. 25

I. 14 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016)

I. 15 52.204-17 OWNERSHIP OR CONTROL OF OFFEROR (JUL 2016)

I. 16 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MANAGEMENT (JUL 2016)

I. 17 52.209-6 PROTECTING THE GOVERNMENT`S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS

DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (OCT 2015)

I. 18 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)

I. 19 52.215-2 AUDIT AND RECORDS--NEGOTIATION (OCT 2010)

I. 20 52.215-8 ORDER OF PRECEDENCE--UNIFORM CONTRACT FORMAT (OCT 1997)

I. 21 52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN CERTIFIED

COST OR PRICING DATA--MODIFICATIONS (OCT 2010)

I. 22 52.219-3 NOTICE OF HUBZONE SET-ASIDE OR SOLE SOURCE AWARD (NOV 2011)

I. 23 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)

I. 24 52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017)

I. 25 52.222-3 CONVICT LABOR (JUN 2003)

I. 26 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS --OVERTIME COMPENSATION (MAY 2014)

I. 27 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014)

I. 28 52.222-7 WITHHOLDING OF FUNDS (MAY 2014)

I. 29 52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)

I. 30 52.222-9 APPRENTICES AND TRAINEES (JUL 2005)

I. 31 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)

I. 32 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)

I. 33 52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014)

I. 34 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS (MAY

2014)

I. 35 52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)

I. 36 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2104)

I. 37 52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)

I. 38 52.222-26 EQUAL OPPORTUNITY (SEPT 2016)

I. 39 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR 2015)

I. 40 52.222-37 EMPLOYMENT REPORTS ON VETERANS (FEB 2016)

I. 41 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC

2010)

I. 42 52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015)

I. 43 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)

I. 44 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015)

I. 45 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION

CONTRACTS (SEP 2013)

PAGE 6 OF 70 SB134117RP0028

I. 46 52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN 1997)

I. 47 52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)

I. 48 52.223-5 I POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)--ALTERNATE I (MAY

2011)

I. 49 52.223-6 DRUG-FREE WORKPLACE (MAY 2001)

I. 50 52.223-15 ENERGY EFFICIENCY IN ENERGY-CONSUMING PRODUCTS (DEC 2007)

I. 51 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (AUG 2011). 28

I. 52 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)

I. 53 52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)

I. 54 52.227-4 PATENT INDEMNITY--CONSTRUCTION CONTRACTS (DEC 2007)

I. 55 52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)

I. 56 52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)

I. 57 52.228-11 PLEDGES OF ASSETS (JAN 2012)

I. 58 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (MAY 2014)

I. 59 52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)

I. 60 52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)

I. 61 52.229-4 FEDERAL, STATE, AND LOCAL TAXES (STATE AND LOCAL ADJUSTMENTS)(FEB 2013)

I. 62 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)

I. 63 52.232-16 I PROGRESS PAYMENTS (APR 2012)--ALTERNATE I (MAR 2000)

I. 64 52.232-17 INTEREST (MAY 2014)

I. 65 52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)

I. 66 52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUNE 2013)

I. 67 52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (DEC 2013)

I. 68 52.233-1 DISPUTES (MAY 2014)

I. 69 52.233-3 PROTEST AFTER AWARD (AUG 1996)

I. 70 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)

I. 71 52.242-13 BANKRUPTCY (JUL 1995)

I. 72 52.242-14 SUSPENSION OF WORK (APR 1984)

I. 73 52.243-4 CHANGES (JUN 2007)

I. 74 52.244-5 COMPETITION IN SUBCONTRACTING (DEC 1996)

I. 75 52.248-3 VALUE ENGINEERING--CONSTRUCTION (OCT 2015)

I. 76 52.249-2 I TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012)--

ALTERNATE I (SEP 1996)

I. 77 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)

I. 78 52.253-1 COMPUTER GENERATED FORMS (JAN 1991)

I. 79 52.203-14 DISPLAY OF HOTLINE POSTER(S) (OCT 2015)

I. 80 52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999)

I. 81 52.222-35 EQUAL OPPORTUNITY FOR VETERANS. [OCT 2015]

I. 82 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)

I. 83 52.225-9 BUY AMERICAN--CONSTRUCTION MATERIALS (MAY 2014)

I. 84 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)

I. 85 52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (OCT 2010)

I. 86 52.233-2 SERVICE OF PROTEST (SEP 2006)

I. 87 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

I. 88 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

I. 89 1352.237-74 PROGRESS REPORTS (APR 2010)

I. 90 52.217-5 EVALUATION OF OPTIONS (JUL 1990)

SECTION J LIST OF ATTACHMENTS

J. 1 General Instructions for working at NIST

J. 3 Safety Checklist

PAGE 7 OF 70 SB134117RP0028

SECTION K REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS

K. 1 52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2016)

K. 2 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2016)

K. 3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REPRESENTATION (OCT 2014)

K. 4 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER--SYSTEM FOR AWARD MANAGEMENT (JUL 2013)

K. 5 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2017)

SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

L. 1 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

L. 2 52.232-13 NOTICE OF PROGRESS PAYMENTS (APR 1984)

L. 3 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)

L. 4 1352.242-70 POSTAWARD CONFERENCE (APR 2010)

L. 5 52.216-1 TYPE OF CONTRACT (APR 1984)

L. 6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

L. 7 Proposal Preperation Instructions

L. 8 52.219-3 NOTICE OF HUBZONE SET-ASIDE OR SOLE SOURCE AWARD (NOV 2011)

SECTION M EVALUATION FACTORS FOR AWARD

M. 1 Evaluation Criteria

PAGE 8 OF 70 SB134117RP0028

SECTION C

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C. 1 Performance Work Statement

PERFORMANCE WORK STATEMENT

Above Ground Pumps

1.1 DESCRIPTION

Provide all labor, equipment, and materials to remove and replace lift station pumps in select buildings to comply with current standards on the National Institute of Standards and Technology (NIST) site cited here in this document.

1.2 PURPOSE

The purpose of this project is to remove and replace lift station pumps in select buildings. The work will consist of the following:

Mechanical

The work will be described in detail in the following section 1.4, “Summary of the Work” and must be code compliant as described in section 1.5 “Reference Standards,” safe, accessible, and easily maintainable.

The contractor is responsible for the following:

Performing the work as described in this Performance Work Statement (PWS).

Preparing and following a site-specific safety plan to be reviewed and accepted by NIST Safety Staff.

Performing a daily Job Hazards Analysis (JHA) for construction activities.

Performing all utility locates.

Coordinating all work with the Contracting Officer’s Representative (COR).

1.3 SPECIAL REQUIREMENTS

Weekly progress meetings required on site.

Pre-construction meeting required.

1.4 SUMMARY OF THE WORK

A. General

Construction and installation shall include, but is not limited to the following:

1. Provide all labor, furnish and install materials, equipment and supplies.

2. Delivery Schedule: This project must be completed 90 calendar days after issuance of a Notice to Proceed

(NTP). With initial proposal and prior to commencement of work the contractor must provide detailed project schedule in Microsoft Project to the COR for acceptance. Final schedule shall be agreed at post-award meeting.

3. Provide construction management and field supervision throughout the project duration.

4. Contractor must be familiar with the work required and local conditions affecting the work.

5. Ensure that the safety of the project is a top priority. Submit a site-specific safety plan with project proposal prior to commencement of construction to the COR for acceptance.

6. Ensure due diligence and timely delivery of the project.

7. Correct errors and deficiencies in the services provided.

8. Cooperate with NIST Police and Security regarding site security. Contractor is responsible for ensuring its personnel meet all site access requirements. Provide a list of all anticipated employees at least two weeks in advance of their arrival. All employees must fill out specified background check forms for review by NIST

Security before security badges will be issued. These forms will be typed.

9. Maintain a record set of all inspections, or other authorizations necessary for the work to proceed.

10. If “Hot Work” will be performed the Contractor must pull a hot work permit through the COR twenty-four hours in advance of beginning associated work.

11. An “Impairment Permit” is required when project work produces: Smoke; Sparks; Steam; Flames; Fumes;

and/or Dust; or other particulates within the buildings when working around fire detection devices. The

Contractor must pull a permit through the COR twenty-four hours in advance of beginning associated work.

PAGE 9 OF 70 SB134117RP0028

12. Notify the COR of the work progress and any required inspections twenty-four hours in advance of all inspections.

13. The contractor is responsible for correcting any damage caused to the NIST Boulder site and field sites as a result of their construction work and returning the site to previous conditions at no cost to the Government.

14. The Contractor shall perform final cleaning and detailing of work areas.

15. Upon substantial completion, notify the COR for the performance of a punch list inspection. Submit a written list of items requiring completion or correction accompanied by an anticipated schedule.

16. Contractor is responsible for determining order of work.

17. See COR for any conflicts associated with this Statement of work, drawings and any appendixes.

18. Demobilize all elements of the Project.

B. Specification Section

1. Mechanical includes the following:

Required Contract Line Item 0001 – Building 1, Room 1049:

1) Remove two (2) lift station sewage ejector pumps. See as built drawings (Attachment 1).

Contractor to verify existing conditions for verification of new pump compatibility.

2) Lift station basin to be cleaned per industry standards prior to the installation of new pumps. If entry to pit is necessary, contractor must conform to new OSHA confined space permit required regulation 29 CFR 1926 Subpart AA.

3) Install two (2) new vertical sewage pumps:

a) Weil pump Model 2224-17-7.5 (or equivalent)

b) Pump size – 4” discharge, 1750 RPM, Vertical Sewage Pump.

c) HP, Voltage – 3 HP, 3/60/208V

d) Pump Adder – 416 SS Shaft.

e) One control panel – Type 4X PLC Duplex Alternating Control Panel.

f) Basin depth – 100”

g) One level control – Type 1 Duplex Mech Lever No-Alt.

4) Pricing to include all associated electrical connections.

5) Provide, install and seal new basin lid to conform with new vertical pumps.

6) Replace 4” discharge piping. Approximately 50’. Contractor to verify quantity pre-proposal.

7) Contractor responsible for pressure testing all pipes prior to start up.

8) Prior to construction, contractor shall inspect lift station basin for integrity of structure.

9) All work requiring the shut-down of the lift station system shall take place after hours. Contractor must provide at least one “hard badged” employee to supervise work at “all” times (regular and after hours). A definitive schedule of the work must be submitted to the COR at least 14 calendar days prior to shut down.

Government reserves the right to agree or disagree to any proposed repairs prior to the removal and installation of pumps. Please allow up to 90 days to execute if changes are deemed necessary. Current pumps must remain in operation while modification is processed.

Optional Contract Line Item 0002 – Building 2, Mechanical Room.

10) Remove one (1) lift station sewage ejector pump. See as built drawings (Attachment 2). Contractor to verify existing conditions for verification of new pump compatibility.

11) Lift station basin to be cleaned per industry standards prior to the installation of new pump. If entry to pit is necessary, contractor must conform to new OSHA confined space permit required regulation 29 CFR 1926 Subpart AA.

12) Install one (1) new vertical sewage pump:

a) Weil pump Model 1226 (or equivalent)

b) Pump size – 2” discharge, 1750 RPM, Vertical Sewage Pump.

c) HP, Voltage – 1.5 HP, 3/60/208V

d) Pump Adder – 416 SS Shaft.

e) One control panel – Type 4X Simplex Control Panel.

f) Basin depth – 60”

g) One level control – Type 1 Simplex Mech Lever

PAGE 10 OF 70 SB134117RP0028

h) Additional Adders – 20” floor plate

13) Pricing to include all associated electrical connections.

14) Provide, install and seal new basin lid to conform with new vertical pumps.

15) Contractor responsible for pressure testing all pipes prior to start up.

16) Prior to construction, contractor shall inspect lift station basin for integrity of structure.

Government reserves the right to agree or disagree to any proposed repairs prior to the removal and installation of pumps. Please allow up to 90 days to execute if changes are deemed necessary. Current pumps must remain in operation while modification is processed.

1.5 REFERENCE STANDARDS

A. The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract

1.6 DELIVERABLE SCHEDULE

TASK PARAGRAPH

REFERENCE

DELIVERY DUE DATE DELIVER TO WHO

TENTATIVE SCHEDULE 1.4-2 WITH INITIAL

PROPOSAL

COR/CO

FINAL SCHEDULE 1.4-2 10 DAYS AFTER

PROJECT AWARDED

COR/CO

SITE SPECIFIC SAFETY

PLAN

1.4-5 10 DAYS AFTER

PROJECT AWARDED

COR/CO/NIST SAFETY

PUMP SUBMITTAL 1.4-B PRIOR TO

INSTALLATION

COR/CO

CONTROL PANEL 1.4.B PRIOR TO

INSTALLATION

COR/CO

ACTIVITY SHUTDOWN

SCHEDULE

1.4.B 14 CALENDAR DAYS

PRIOR TO SHUTDOWN

COR/CO

OPERATION AND

MAINTENANCE

MANUALS

1.4.B UPON COMPLETION OF

WORK

COR/CO

-END-

PAGE 11 OF 70 SB134117RP0028

C. 2 Attachment 1

PAGE 12 OF 70 SB134117RP0028

C. 3 Attachment 2

PAGE 13 OF 70 SB134117RP0028

SECTION E

INSPECTION AND ACCEPTANCE

E. 1 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)

(Reference 52.236-21)

E. 2 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

(Reference 52.246-12)

E. 3 52.246-13 INSPECTION--DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS (AUG 1996)

(Reference 52.246-13)

E. 4 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

(Reference 52.246-21)

E. 5 1352.271-83 GOVERNMENT REVIEW, COMMENT, ACCEPTANCE AND APPROVAL (APR 2010)

(Reference 1352.271-83)

NIST

325 Broadway Boulder CO, 80305

E. 6 1352.246-70 PLACE OF ACCEPTANCE (APR 2010)

(a) The Contracting Officer or the duly authorized representative will accept supplies and services to be provided under this contract.

(b) The place of acceptance will be:

NIST

325 Broadway Boulder, CO 80305

(End of clause)

PAGE 14 OF 70 SB134117RP0028

SECTION F

DELIVERIES OR PERFORMANCE

F. 1 52.236-2 DIFFERING SITE CONDITIONS (APR 1984)

(Reference 52.236-2)

F. 2 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)

(Reference 52.236-3)

F. 3 52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)

(Reference 52.236-5)

F. 4 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

(Reference 52.236-6)

F. 5 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)

(Reference 52.236-7)

F. 6 52.236-8 OTHER CONTRACTS (APR 1984)

(Reference 52.236-8)

F. 7 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS

(APR 1984)

(Reference 52.236-9)

F. 8 52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)

(Reference 52.236-10)

F. 9 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)

(Reference 52.236-11)

F. 10 52.236-12 CLEANING UP (APR 1984)

(Reference 52.236-12)

F. 11 52.236-13 ACCIDENT PREVENTION (NOV 1991)

(Reference 52.236-13)

F. 12 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)

(Reference 52.236-14)

F. 13 52.236-21 I SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)--ALTERNATE I (APR 1984)

(Reference 52.236-21 I)

F. 14 52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)

PAGE 15 OF 70 SB134117RP0028

(Reference 52.236-26)

F. 15 52.242-14 SUSPENSION OF WORK (APR 1984)

(Reference 52.242-14)

F. 16 52.242-17 GOVERNMENT DELAY OF WORK (APR 1984)

(Reference 52.242-17)

F. 17 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to

(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 90 days after receipt of notice to proceed The time stated for completion shall include final cleanup of the premises.

(End of Clause)

F. 18 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)

(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period.

If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government.

In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor`s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

PAGE 16 OF 70 SB134117RP0028

SECTION G

CONTRACT ADMINISTRATION DATA

G. 1 Wage Determination

General Decision Number: CO170027 06/09/2017 CO27

Superseded General Decision Number: CO20160027

State: Colorado

Construction Type: Building

County: Boulder County in Colorado.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.

The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2017 1 01/13/2017 2 01/27/2017 3 02/03/2017 4 04/07/2017 5 04/21/2017 6 05/19/2017 7 05/26/2017 8 06/02/2017 9 06/09/2017

ASBE0028-002 07/01/2016

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System Insulation)......................$ 29.73 13.93

CARP1607-001 06/01/2016

Rates Fringes

MILLWRIGHT.......................$ 31.38 12.70

ELEC0068-018 06/01/2017

Rates Fringes

ELECTRICIAN......................$ 34.70 14.97

ELEV0025-001 01/01/2017

PAGE 17 OF 70 SB134117RP0028

Rates Fringes

ELEVATOR MECHANIC................$ 42.35 31.58

FOOTNOTE:

a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.

b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

* ENGI0009-017 05/01/2017

Rates Fringes

POWER EQUIPMENT OPERATOR

(Crane) 141 tons and over...........$ 29.82 10.10 50 tons and under...........$ 27.75 10.10 51 to 90 tons...............$ 27.92 10.10 91 to 140 tons..............$ 28.55 10.10

IRON0024-009 05/01/2017

Rates Fringes

IRONWORKER, ORNAMENTAL...........$ 26.30 12.25

IRON0024-010 05/01/2017

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 26.30 12.25

PAIN0079-006 08/01/2016

Rates Fringes

PAINTER (Brush, Roller and Spray; Excludes Drywall Finishing/Taping)................$ 20.00 7.91

PAIN0419-001 07/01/2016

Rates Fringes

SOFT FLOOR LAYER (Vinyl and Carpet)..........................$ 20.00 10.83

PLUM0003-009 06/01/2017

Rates Fringes

PLUMBER (Excludes HVAC Duct, Pipe and Unit Installation)......$ 34.53 16.44

PLUM0208-010 06/01/2016

Rates Fringes

PIPEFITTER (Includes HVAC Pipe Installation; Excludes HVAC Duct and Unit Installation)....................$ 32.90 16.62

PAGE 18 OF 70 SB134117RP0028

SFCO0669-002 04/01/2017

Rates Fringes

SPRINKLER FITTER (Fire Sprinklers)......................$ 36.73 20.47

SHEE0009-004 07/01/2016

Rates Fringes

SHEET METAL WORKER (Includes HVAC Duct Installation;

Excludes HVAC Pipe and Unit Installation)....................$ 32.56 15.96

SUCO2013-003 07/31/2015

Rates Fringes

BRICKLAYER.......................$ 21.96 0.00

CARPENTER, Excludes Drywall Hanging..........................$ 22.66 6.79

CEMENT MASON/CONCRETE FINISHER...$ 20.31 6.76

DRYWALL FINISHER/TAPER...........$ 20.82 6.37

DRYWALL HANGER...................$ 19.24 6.30

HVAC MECHANIC: HVAC Unit Installation, Excludes Pipe and Duct Installation............$ 25.23 9.36

LABORER: Common or General......$ 11.76 0.00

LABORER: Mason Tender - Brick...$ 15.99 0.00

LABORER: Mason Tender - Cement/Concrete..................$ 16.00 0.00

LABORER: Pipelayer..............$ 16.96 3.68

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 20.78 5.78

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 18.58 2.42

OPERATOR: Grader/Blade..........$ 21.50 0.00

ROOFER...........................$ 17.14 0.00

TRUCK DRIVER: Dump Truck........$ 17.34 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this

PAGE 19 OF 70 SB134117RP0028

contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion

PAGE 20 OF 70 SB134117RP0028

date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage

PAGE 21 OF 70 SB134117RP0028

payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

PAGE 22 OF 70 SB134117RP0028

G. 2 1352.201-70 CONTRACTING OFFICER?s AUTHORITY (APR 2010)

The Contracting Officer is the only person authorized to make or approve any changes in any of the requirements of this contract, and, notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely in the Contracting Officer. In the event the contractor makes any changes at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract terms and conditions, including price.

G. 3 1352.201-72 CONTRACTING OFFICER`S REPRESENTATIVE (COR) (APR 2010)

(a) The Contracting Officer's Representative will be designated by separate letter and placed within contract file. Phone number and email will be annotated within this letter. is hereby designated as the Contracting Officer`s Representative (COR). The COR may be changed at any time by the Government without prior notice to the contractor by a unilateral modification to the contract. The COR is located at:

Phone Number: see guidance above.

Email: see guidance above.

(b) The responsibilities and limitations of the COR are as follows:

(1) The COR is responsible for the technical aspects of the contract and serves as technical liaison with the contractor. The COR is also responsible for the final inspection and acceptance of all deliverables and such other responsibilities as may be specified in the contract.

(2) The COR is not authorized to make any commitments or otherwise obligate the Government or authorize any changes which affect the contract price, terms or conditions. Any contractor request for changes shall be referred to the Contracting Officer directly or through the COR. No such changes shall be made without the express written prior authorization of the Contracting Officer. The Contracting Officer may designate assistant or alternate COR(s) to act for the COR by naming such assistant/alternate(s) in writing and transmitting a copy of such designation to the contractor.

G. 4 NIST LOCAL-04 BILLING INSTRUCTIONS

(a) NIST prefers electronic Invoice/Voucher submissions and they should be emailed to INVOICE@NIST.GOV.

(b) Each Invoice or Voucher submitted shall include the following: (1) Contract Number. (2) Contractor Name and Address. (3) Date of Invoice. (4) Invoice Number. (5) Amount of Invoice and Cumulative Amount Invoiced to-date. (6) Contract Line Item Number (CLIN). (7) Description, Quantity, Unit of Measure, Unit Price, and Extended Price of Supplies/Services Delivered. (8) Prompt Payment Discount Terms, if Offered. (9) Any other information or documentation required by the contract.

(c) In the event electronic submissions are not used, The Contractor shall submit an original invoice or voucher in accordance with the payment provisions of this contract to:

NIST: Accounts Payable Office 100 Bureau Drive, Mail Stop 1621 Gaithersburg, MD 20899-1621

PAGE 23 OF 70 SB134117RP0028

SECTION H

SPECIAL CONTRACT REQUIREMENTS

H. 1 1352.208-70 RESTRICTIONS ON PRINTING AND DUPLICATING (APR 2010)

(Reference 1352.208-70)

H. 2 1352.209-73 COMPLIANCE WITH THE LAWS (APR 2010)

(Reference 1352.209-73)

H. 3 1352.209-74 ORGANIZATIONAL CONFLICT OF INTEREST (APR 2010)

(Reference 1352.209-74)

H. 4 1352.228-72 DEDUCTIBLES UNDER REQUIRED INSURANCE COVERAGE- FIXED PRICE (APR 2010)

(Reference 1352.228-72)

H. 5 1352.209-72 RESTRICTIONS AGAINST DISCLOSURE (APR 2010)

(a) The contractor agrees, in the performance of this contract, to keep the information furnished by the Government or acquired/developed by the contractor in performance of the contract and designated by the Contracting Officer or Contracting Officer?s Representative, in the strictest confidence. The contractor also agrees not to publish or otherwise divulge such information, in whole or in part, in any manner or form, nor to authorize or permit others to do so, taking such reasonable measures as are necessary to restrict access to such information while in the contractor?s possession, to those employees needing such information to perform the work described herein, i.e., on a "need to know" basis. The contractor agrees to immediately notify the Contracting Officer in writing in the event that the contractor determines or has reason to suspect a breach of this requirement has occurred.

(b) The contractor agrees that it will not disclose any information described in subsection (a) to any person unless prior written approval is obtained from the Contracting Officer. The contractor agrees to insert the substance of this clause in any consultant agreement or subcontract hereunder.

H. 6 1352.228-70 INSURANCE COVERAGE (APR 2010)

(a) Workers Compensation and Employer?s Liability. The contractor is required to comply with applicable federal and state workers'' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer?s liability section of the insurance policy, except when contract operations are so commingled with a contractor?s commercial operations that it would not be practical to require this coverage. Employer?s liability coverage of at least $100,000 shall be required, except in states with exclusive or monopolistic funds that do not permit workers'' compensation to be written by private carriers.

(b) General liability.

(1) The contractor shall have bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.

(2) When special circumstances apply in accordance with FAR 28.307-2(b), Property Damage Liability Insurance shall be required in the amount of $$0 .

(c) Automobile liability. The contractor shall have automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract.

Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage.

(d) Aircraft public and passenger liability. When aircraft are used in connection with performing the contract, the contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Coverage for passenger

PAGE 24 OF 70 SB134117RP0028

liability bodily injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(e) Vessel liability. When contract performance involves use of vessels, the Contractor shall provide, vessel collision liability and protection and indemnity liability insurance as determined by the Government.

PAGE 25 OF 70 SB134117RP0028

SECTION I

CONTRACT CLAUSES

I. 1 52.202-1 DEFINITIONS (NOV 2013)

(Reference 52.202-1)

I. 2 52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(Reference 52.203-2)

I. 3 52.203-3 GRATUITIES (APR 1984)

(Reference 52.203-3)

I. 4 52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)

(Reference 52.203-5)

I. 5 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006)

(Reference 52.203-6)

I. 6 52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)

(Reference 52.203-7)

I. 7 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)

(Reference 52.203-8)

I. 8 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)

(Reference 52.203-10)

I. 9 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT 2010)

(Reference 52.203-12)

I. 10 52.203-16 PREVENTING PERSONAL CONFLICTS OF INTEREST (DEC 2011)

(Reference 52.203-16)

I. 11 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF

WHISTLEBLOWER RIGHTS (APR 2014)

(Reference 52.203-17)

I. 12 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011)

(Reference 52.204-4)

I. 13 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (OCT 2016)

(Reference 52.204-10)

I. 14 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016)

PAGE 26 OF 70 SB134117RP0028

(Reference 52.204-16)

I. 15 52.204-17 OWNERSHIP OR CONTROL OF OFFEROR (JUL 2016)

(Reference 52.204-17)

I. 16 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MANAGEMENT (JUL 2016)

(Reference 52.204-18)

I. 17 52.209-6 PROTECTING THE GOVERNMENT`S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (OCT 2015)

(Reference 52.209-6)

I. 18 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)

(Reference 52.209-10)

I. 19 52.215-2 AUDIT AND RECORDS--NEGOTIATION (OCT 2010)

(Reference 52.215-2)

I. 20 52.215-8 ORDER OF PRECEDENCE--UNIFORM CONTRACT FORMAT (OCT 1997)

(Reference 52.215-8)

I. 21 52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN CERTIFIED COST

OR PRICING DATA--MODIFICATIONS (OCT 2010)

(Reference 52.215-21)

I. 22 52.219-3 NOTICE OF HUBZONE SET-ASIDE OR SOLE SOURCE AWARD (NOV 2011)

(Reference 52.219-3)

I. 23 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)

(Reference 52.219-8)

I. 24 52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017)

(Reference 52.219-14)

I. 25 52.222-3 CONVICT LABOR (JUN 2003)

(Reference 52.222-3)

I. 26 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS --OVERTIME COMPENSATION (MAY 2014)

(Reference 52.222-4)

I. 27 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014)

(Reference 52.222-6)

I. 28 52.222-7 WITHHOLDING OF FUNDS (MAY 2014)

PAGE 27 OF 70 SB134117RP0028

(Reference 52.222-7)

I. 29 52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)

(Reference 52.222-8)

I. 30 52.222-9 APPRENTICES AND TRAINEES (JUL 2005)

(Reference 52.222-9)

I. 31 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)

(Reference 52.222-10)

I. 32 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)

(Reference 52.222-11)

I. 33 52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014)

(Reference 52.222-12)

I. 34 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS (MAY 2014)

(Reference 52.222-13)

I. 35 52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)

(Reference 52.222-14)

I. 36 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2104)

(Reference 52.222-15)

I. 37 52.222-21…