STATEMENT OF WORK
TITLE: Upgrade DCI Pump Series 32
I. BACKGROUND INFORMATION
The National Institute of Standards and Technology’s (NIST) Materials Science and Engineering Division develops the measurement science, standards, technology, and data required to support the nation's need to design, develop, manufacture, and use materials. The division is currently developing an instrument for high shear rate rheoSANS, which simultaneously functions as an instrument for rheology and small angle (neutron) scattering, and uses a Volume Pressure Actuator (VPA) Syringe Pump to support this project. The division has a requirement to upgrade a NIST-owned VPA pump from a single syringe to a dual syringe to allow for steady driving and continuous flow.
The current single syringe pump(32S-5-375-400-SS) was purchased from DCI Test Systems in support of this project. Upgrading to a dual syringe system (32D-5-375-400-SS) will enable a constant high pressure flux as the two pumps work together, repeatedly trading off to provide a constant infinite flow. This capability will improve performance at the highest pressures and flow rates.
II. SCOPE OF WORK
The Contractor shall deliver required parts and instructions to perform an upgrade of the current single syringe pump (32S-5-375-400-SS) to a dual syringe pump (32D-5-375-400-SS).
III. SPECIFICATIONS
Maximum pressure: 5,000 psi Maximum flow rate: 400 ml/min Minimum flow rate: 0.001 ml/min Flow Accuracy: 0.1% of Set Flow Rate Volume Accuracy: 0.1% of Vol. Disp.
Pressure Accuracy: 0.1% F.S.
Plumbing Ports: 1/4" Med Pressure Cylinder Temp. Rating: Ambient - 150 C Cylinder Volume: 375 ml Wetted parts: SS Air-operated valves: (4) valve manifold Power Required: 110/220 Vac, 50/60 Hz Ambient Temp. Rating: 10-30 deg C Includes LabVIEW drivers
IV. SPECIFIC TASKS
Delivery only; NIST will perform installation.
Warranty One-year warranty on defective parts.
V. DELIVERY DATE
60 days after award.
VI. ACCEPTANCE AND PAYMENT
Upon delivery, the Technical Point of Contact will inspect the parts and instructions to ensure that all specifications in this statement of work are met. The parts will not be accepted until the Technical Point of Contact has confirmed that they meet all specifications.
Advance payment is not authorized. Payment will be made upon receipt and acceptance of the required deliverables.
VII. NIST POINT OF CONTACT:
Technical Point of Contact (TPOC) Name: Steven D. Hudson Phone: (301) 975-6579 Email: steven.hudson@nist.gov