SATPC0042355 Tab 04 4 SOW.pdf
PDF 70 KB Posted
- Attached to
- Structural Dynamics Lab Power Amplifier Switcher Replacement for electrodynamic Shaker Federal contract opportunity
- Solicitation number
- 80NSSC26941364Q
About this file
This is a Statement of Work for NASA Glenn Research Center's Structural Dynamics Lab (SDL) Amplifier Switcher Replacement project. The contractor must design, manufacture, and deliver a new 3 x 3 Amplifier Switcher System to replace a failed unit. The system shall be compatible with existing lab infrastructure including power, environmental conditions, and physical space; interface with existing amplifiers, electrodynamic shakers, and cooling systems; accommodate future replacement of the MB Dynamics C60 electrodynamic shaker; operate remotely from the SDL control room's control panel; and comply with NFPA 70 National Electric Code (NEC). The contractor must submit the new Amplifier Switcher System design and commissioning test plan to NASA for review and approval at least 4 weeks prior to fabrication. All work must be completed within 26 weeks after receipt of an approved contract (Purchase Order).
The contractor shall remove and replace the existing amplifier switcher system with the new equipment and remote control panels, then reconnect existing amplifiers and shakers and commission the new system in accordance with the approved test plan. All work at NASA Glenn must occur during SDL normal business hours (7:00 AM to 5:00 PM, Monday through Friday), and all contractor personnel requiring facility access must be U.S. Citizens or Lawful Permanent Residents. On-site work must comply with 29CFR1910 (OSHA) and NASA Glenn's Safety and Occupational Health Program Manuals; on-site assembly work requires submission of a Health and Safety Plan (HASP). Deliverables include all documentation associated with the new Amplifier Switcher System (Operating Manual, Wiring Diagrams, Maintenance Plan, etc.) and documentation of successful commissioning.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SATPC0042355 Tab 07 Capability Statement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Structural Dynamics Lab Amplifier Switcher Replacement
Initial Release – July 29, 2026
Background NASA Glenn’s Structural Dynamics Lab (SDL) experienced a failure of its Amp Switcher and desires a modernized replacement to be able to operate the lab at full capacity.
General Requirements The Contractor shall provide personnel, equipment, tools and materials necessary to perform the Tasks below All work at NASA Glenn shall take place during SDL normal business hours (7:00 AM to 5:00 PM, Monday through Friday) All Contractor personnel requiring access to NASA facilities shall be a US Citizen or
Lawful Permanent Resident All work performed under this contract on-site at Glenn Research center shall be in compliance with 29CFR1910 (OSHA) and those policies set forth in the NASA Glenn Research Center's Safety and Occupational Health Program Manuals. For any on-site assembly work the contractor shall submit a Health and Safety Plan (HASP) accordance with the Glenn Safety and Occupational Health Program manuals.
All tasks should be completed within 26 weeks after receipt of an approved contract (Purchase Order
Tasks The Contractor shall design, manufacture and deliver a new 3 x 3
System. The system shall:
o be compatible with existing lab infrastructure (including but not limited to:
power, environmental conditions, physical space available) o be able to interface with the lab’s , electrodynamic shakers, cooling systems, etc.
o be compatible with the planned future replacement of the MB Dynamics C60 electrodynamic shaker with a new shaker of similar size and capacity o be able to be operated remotely from the SDL control room’s control panel o be compliant with NFPA 70 National Electric Code (NEC)
The Contractor shall submit the her System design and a commissioning test plan to NASA for review and approval at least 4 weeks prior to fabrication
The Contractor shall remove and r with the new 3 x 3 Switcher System and remote control panels.
The Contractor shall reconnect the existing and shakers and commission the new system in accordance with the approved test plan.
Deliverables
1. All documentation associated with new Amp
Manual, Wiring Diagrams, Maintenance Plan, etc.)
2. Documentation of successful commissioning