This is a Statement of Work template for NASA Langley Research Center detailing the procurement of modernized plasma gun components to upgrade an existing Tekna vacuum plasma spray system used for advanced materials research and coating applications. The procurement addresses the need for OEM-compatible replacement parts and custom components that integrate with existing Tekna infrastructure while supporting NASA's materials research under the STMD Dust Mitigation and Environmental Material Solutions (DMEMS) effort.

The contractor shall manufacture and supply specialized plasma gun components including a custom after-sale service torch model PN070-B7-DC-BB, three thick-ended ceramic tubes (PN070-12H), three quartz tubes with shoulder and 55 mm I.D. (PS070-11A), one sheathed probe (SG792-260A0, 260 mm length), and one custom supersonic nozzle for the PN070 plasma torch model. Accessory components required include a brass anti-arc ring (PS070-10C2), two EMI shield female contact rings (Series 192 Fingers, 12" long), and one SL-70 O-ring (073 mm). The contractor must provide component certifications and material documentation, ensure all components meet Tekna specifications for integration into NASA's vacuum plasma spray system, and furnish installation guidance and compatibility verification. Technical documentation deliverables include component specifications, material certifications, and installation and compatibility documentation with Tekna OEM guidance. Delivery timeline will be determined upon receipt of NASA's purchase order. No milestones, government-furnished property, or specific response/award dates are identified in this template document.

View the file

Other files for this federal contract opportunity

Other files attached to Tekna Plasma Gun Modernization Components, newest first.
File Type Posted
SATPC0041871 Tab 07 Capability Statement.pdf PDF
SATPC0041871 Tab 06 RDSS..pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK TEMPLATE

1.0 Introduction/Background: NASA Langley Research Center requires modernized plasma gun components to upgrade an existing Tekna vacuum plasma spray system used for advanced materials research, testing, and coating applications. The current system requires updated components to maintain operational capability and ensure continued research productivity, as the present gun components are outdated and no longer serviced by Tekna. This procurement addresses the critical need for OEM-compatible replacement parts and custom components that integrate seamlessly with existing Tekna infrastructure while providing enhanced performance characteristics essential for NASA's materials research under the STMD Dust Mitigation and Environmental Material Solutions (DMEMS) effort.

2.0 Scope of Work: This Statement of Work covers the procurement of specialized plasma gun components, custom torch parts, supersonic nozzle assemblies, ceramic and quartz tubes, sheathed probes, EMI shielding hardware, O‑rings, and associated accessories from Tekna Plasma Systems Inc. required for full modernization of the PN070 plasma torch model.

3.0 Objectives: The overall objective is to provide NASA with OEM-quality plasma gun components and custom parts that ensure continued operational capability of existing Tekna plasma systems while enhancing performance and reliability for critical materials research applications and testing configurations.

4.0 Description of the Work/Contractor Tasks:

Task 1: Component Manufacturing and Supply The contractor shall manufacture and supply the following components:

• Custom part – After‑sale service Torch model PN070‑B7‑DC‑BB (1 EA)

• PN070‑12H Thick‑ended ceramic tubes (3 EA)

• PS070‑11A Quartz tubes with shoulder, 55 mm I.D. (3 EA)

• SG792‑260A0 Sheathed probe, 260 mm length (1 EA)

• Custom supersonic nozzle for PN070 plasma torch model (1 EA)

Task 2: Accessory Components The contractor shall supply the following accessory components:

• PS070‑10C2 Brass ring, anti‑arc model, single shield (1 EA)

• EMI shield female contact rings, Series 192 Fingers, 12" long (2 EA)

• SL‑70 O‑ring, 073 mm (1 EA)

Task 3: Quality Assurance and Documentation The contractor shall:

• Provide component certification (if available) and material documentation

• Ensure all components meet Tekna specifications for incorporation into NASA’s

VPS system

• Provide installation guidance and compatibility verification

• Support NASA with clarification on component integration as needed Review and Approval Points:

• Pre-shipment component inspection and certification

• Final delivery and acceptance verification

5.0 Deliverables:

5.1 Hardware Components

The contractor shall deliver all components listed in Task 1 and Task 2, including:

• Custom PN070‑B7‑DC‑BB torch part

• PN070‑12H ceramic tubes

• PS070‑11A quartz tubes

• SG792‑260A0 sheathed probe

• Custom supersonic nozzle

• PS070‑10C2 brass ring

• EMI shield contact rings

• SL‑70 O‑ring Delivery timeline will be determined upon receipt of NASA’s purchase order

5.2 Technical Documentation

The contractor shall provide:

• Component specifications and material certifications

• Installation and compatibility documentation

• Any available Tekna OEM guidance for integration into NASA’s existing PN070 plasma torch system Delivery: With components

Other Considerations:

Applicable Documents/Background:

• Tekna plasma system specifications

• NASA materials research requirements

• Applicable industry standards for plasma spray components

Milestones: N/A

Government-furnished property: None

Government-furnished information:

• Existing system specifications

• Integration requirements