This is a Statement of Work (SOW) for the repair of a Spectra-Physics Solstice Ace laser system at NASA Langley. The primary issue involves a malfunctioning Ascend pump laser power supply that requires replacement and integration with the overall system. The contractor is responsible for procuring replacement parts, performing labor, and covering travel costs including per diem and zone charges for a service engineer or technician to work on-site.
The contractor's tasks include evaluating the malfunctioning unit, replacing it with purchased parts, and integrating the repaired components into the laser system. Deliverables consist of the replacement hardware and a performance report documenting the results of the repaired laser system. The government will furnish the Spectra-Physics Solstice Ace laser system, which will be located and connected to electricity at the facility. The SOW contains no applicable background documents, milestones, or government-furnished information beyond the equipment itself.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SATPC0041031 Tab 07 Capability Statement.pdf | ||
| SATPC0041031 Tab 06 RDSS..pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For
Spectra-Physics Solstice Ace Laser Repair (Ascend Power Supply)
1.0 Introduction/Background: Spectra-Physics Solstice Ace laser is in need of repair. The current Ascend pump laser within the system is malfunctioning and this appears to be due to an issue with the power supply. A replacement power supply is believed to be needed to remedy the issue.
2.0 Scope of Work: This SOW covers procurement of replacement parts, as well as payment for labor and travel costs.
3.0 Objectives: Our objective is to get the Solstice Ace laser system working again.
4.0 Description of the Work/Contractor Tasks:
There are several tasks that will be accomplished under this contract:
• Evaluation of the malfunctioning unit, expected replacement with the purchased parts, and integration with the overall laser system.
• Labor is required for the above work. Per diem and zone charges are also required to bring the service engineer/technician on site at NASA Langley.
5.0 Deliverables: The deliverables include both the replacement hardware mentioned in 4.0 as well as a report documenting the performance of the overall repaired laser system.
Other Considerations:
Applicable Documents/Background: none
Milestones: none
Government-furnished property – The Spectra-Physics Solstice Ace laser will be provided to the company for these repairs. The system will be located in and connected to electricity.