About this file

This Statement of Work (SOW) details NASA Langley Research Center's requirement to renew ETAP Software maintenance for a 3-User Commercial LAN license with unlimited bus functionality. The comprehensive software license includes extensive electrical engineering and power systems modeling capabilities across multiple domains, such as load flow analysis, panel scheduling, renewable energy modeling, short circuit analysis, arc flash calculations, motor starting dynamics, harmonics analysis, and geospatial electrical network modeling.

The contract covers a one-year performance period from 09/01/2025 to 09/01/2026, to be executed at NASA Langley Research Center. The SOW specifies a single quantity of the ETAP license with features including multi-dimension digital-twin platform capabilities, IEEE and NEC compliance tools, power flow analysis for AC and unbalanced networks, wind and solar renewable energy modeling, HVDC control schemes, network project management, and advanced safety and protection device analysis. Additional functionalities include Excel data import/export, global data change tracking, and consistency checks.

View the file

Other files for this federal contract opportunity

Other files attached to ETAP Renewal, newest first.
File Type Posted
SATPC0039209 Tab 06 RDSS..pdf PDF
SATPC0039209 Tab 07 Capability Statement SAM.gov.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objective/Requirements NASA Langley Research Center (LaRC) has a requirement to renew ETAP Software maintenance.

2. Characteristics, Scope, and Specs

QTY Description

1 ETAP Existing License – 3-User Commercial LAN, Unlimited Bus –

Base Module: Multi-Dimension Digital-Twin Platform, Revisions, Libraries, Wizards IEEE, ICEA, NEC: Cable Ampacity & Sizing - IEEE, ICEA, NEC Load Flow, AC: Power Flow, 3-Phase & 1-Phase Systems, Voltage Drop, Result Analyzer Panel Schedule: Schedules, Calculations, 3-Phase, 1-Phase, NEC, IEC Renewables: Wind Turbine Generator, PV Array - PV Pro, Controls, Libraries, Profiles HVDC: Control Schemes, Dynamic Modes, Rectification, Inversion NetPM: Network/Cloud Project Modeling & Management, Centralized, Simultaneous Users Short Circuit, AC: ANSI & IEC, Balanced 3-Phase & 1-Phase, Duty Evaluation, Analyzer GIS Interface: GIS Interface (Requires Intelligent Geospatial Diagram) Arc Flash, AC: IEEE 1584 2018 & NFPA 70E 2021 - Analyzer, Work Permit, Safety Labels ArcFault: 15kV & Above, OSHA 1910 Appendix E, LG, LL, 3-Phase Arc Faults Arc Flash, DC: Max Power, Stokes & Oppenlander, Paukert, NFPA 70E 2018 Star: Protection, Selectivity, Sequence of Operation, Protective Devices Motor Starting: Dynamic & Static, Seq of Op, Scripts, Result Analyzer Harmonics: Harmonic Load Flow, Frequency Scan, Harmonic Filters & Sizing Cable UG Thermal: UG Raceways, Direct Buried, Neher-McGrath, IEC 60287 Short Circuit, DC: System Faults, Device Duty Evaluation, Reports, IEEE 946 Transient Stability: Dynamics, Inrush, Short & Long-Term, Analyzer Motor Param Est.: Induction Motor Parameter Estimation & Tuning, Nameplate, Characteristic Data Load Flow, UB: Unbalanced Power Flow, AC Networks, 3-Phase & 1-Phase Opt Power Flow: Optimize Power Flow, Energy Costs, Fuel Costs, Security Indices, Power Exchange GIS, Elect.: Intelligent Geospatial Electrical One-Line, Network Wide, Incremental Updates

DataX, Excel: Import / Export MS Excel - Global Data Changes, Consistency Checks, Create Reports

3. Place of Performance NASA, Langley Research Center

4. Period of Performance 09/01/2025-09/01/2026