About this file

This Statement of Work specifies requirements for Time-Triggered Ethernet (TTE) switches for NASA Johnson Space Center. The procurement requires two different TTE switch models: three units of part #13790 (24-port TTE-Switch Lab Space) and two units of part #13523 (24-port TTE-Switch), both supporting laboratory testing of Time-Triggered Ethernet applications and providing representative flight utilization with TTE-Switch Controller HIRel cores.

Delivery is required to NASA Johnson Space Center in Houston, TX (Building 29, room 139) with an estimated lead time of 6 weeks after receipt of order (ARO). Both switch models are high-performance devices designed for laboratory testing environments, with part #13523 specifically using revision B of the TTE-Switch Controller hiRel.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 TTE Switch, newest first.
File Type Posted
SATPC0037217 Tab 07 Capability Statement FBO Posting.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objective/Requirements

The information listed below is required to complete this purchase.

2. Characteristics, Scope, and Specs

LINE PART NO. DESCRIPTION QTY.

1 13790 The high-performance 24-port TTE-Switch Lab Space supports laboratory testing efforts of

Time-Triggered Ethernet applications. It provides a representative flight utilization by using the

TTE-Switch Controller HIRel at its core.

2 13523 The high-performance 24-port TTE-Switch supports laboratory testing efforts of Time-

Triggered Ethernet applications. It provides a representative flight utilization by using the TTE-

Switch Controller hiRel (rev. B) at its core

3. Place of Performance

NASA Johnson Space Center

2101 NASA Parkway

Bldg 29 rm 139

Houston, TX 77058

4. Period of Performance

Estimated delivery lead-time is 6 weeks ARO.