This document is a Statement of Work (SOW) for an ultraviolet (UV) laser and mass flow controller (MFC) upgrade to be integrated into a Dry Multimaterial Printer. The key requirements are:
-
Integrate a 5W UV laser into the Dry Multimaterial Printer to enable either the UV or existing infrared (IR) laser to be used for sintering nanoparticles. The UV laser integration includes software integration for automatic control, required optics and optical path upgrade, delivery, installation, and operation verification.
-
Integrate an additional 2000 SCCM oxygen MFC into the Dry Multimaterial Printer, including software integration for automatic control, delivery, installation, and operation verification.
The SOW specifies the UV laser and MFC must be integrated into the Dry Multimaterial Printer prior to its delivery, which is due by 10/11/24. The period of performance for this upgrade is from contract signing until equipment delivery, up to a maximum of 5 months.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SATPC0036025 Tab 07 RDSS_Redacted.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW for UV Laser and MFC Upgrade for Dry Multimaterial Printer
1. Objective/Requirement
1. Integrate an ultraviolet (UV) laser into Dry Multimaterial Printer such that either it or the existing infrared (IR) laser can be used for sintering nanoparticles.
2. Integrate an additional mass flow controller (MFC) into Dry Multamaterial Printer.
2. Characteristics, Scope and Specifications
1. The equipment must be integrated into the Dry Multimaterial Printer prior to delivery. The other contract for the Dry Multimaterial Printer specifies delivery or before 10/11/24.
2. UV laser
a. 5W Power
b. software integration for automatic control
c. Required optics and optical path upgrade
d. Delivery, In-system installation, and operation verification
3. Additional MFC
a. 2000 SCCM for oxygen
b. software integration for automatic control
c. Delivery, In-system installation, and operation verification
3. Milestones
Milestone Title Deliverable Schedule
3.1 Purchase of materials none Contract Signed
(CS)+2 weeks
3.2 Installation, integration, test
none (CS)+2-5 months
3.3 Delivery equipment (CS)+2-5 months
4. Place of Performance
5. Period of Performance
From CS date until equipment is delivered, a maximum of 5 months.